20 17 implementation plan of primary school thinning reform project

With the extensive implementation and in-depth development of the thin reform project, how to do a good job of thin reform of wages? The following is part of the implementation plan of the 20 17 primary school reform project for your reference.

20 17 demonstration text of the implementation plan of the primary school thin reform project 1 according to Suixian? Thin change? According to the overall requirements of the project, the hongshan town Central School is specially formulated in accordance with the Equipment Procurement Plan of the Reconstruction Plan for Weak Schools in Compulsory Education in hongshan town and the spirit of relevant meetings, combined with the reality of our school. Thin change? Project work implementation plan.

I. Projects assigned to our school by hongshan town.

1, electronic reading room

Configure 30 computers

2. Art classroom

Equipped with 40 drawing boards, easels and art equipment.

3. Music classroom

Configuration: electronic organ, staff teaching blackboard

4, sports equipment storage room

5, sanitary equipment storage room

6、? Banbantong?

/kloc-class 0/4 equipment

Second, established? Thin change? Work leading group and work special class

Leading Group: Team Leader: Executive Vice President of Zhang Guobin Central School)

Member: Vice President Cai

Ren Yongbing, Vice President

Vice President Nie Aihong

Vice President Hu

Work category: Hu, Chen Jinchuan, Fan,.

Three. Work steps and measures

1, on July 4th, a meeting of leading group and working class was held to convey the spirit of the meeting at the higher level and learn Hongshan Town? Thin change? The preliminary work and equipment purchase scheme of Hongshan town weak compulsory education school reconstruction plan project are explained, and the distribution of our project by superiors is understood.

2. On July 5th, the working class inspected the situation of each room and classroom on the spot, and made a good plan according to the requirements of the preparation work of each room.

① Electronic reading room: located at the east end of the fifth floor of the Science and Education Building.

Lack of air conditioning circuits, network cables, curtains, security doors and windows.

② Art classroom: located at the west end of the fourth floor of Science and Education Building.

Lack of curtains, security doors and windows

③ Music classroom: located at the east end of the fourth floor of Science and Education Building.

Lack of security doors and windows

④ Sports equipment storage room: set up the first floor of the teaching building.

Lack of security doors and windows

⑤ Sanitary equipment: set on the fifth floor of science and education building.

Missing house number sign

⑥? Banbantong? Classroom: Build a teaching building 1? 5 layer

*** 14 classroom, 4 offices, 1 computer room, 1 multimedia classroom.

Lack of network cable, need to transform the circuit.

3. On July 6th, organize the construction personnel to work out the project budget.

4. On July 8th, a working meeting of the leading group and special working class was held to determine the project preparation and the project owner.

On May 7 10, the project owner organized the construction.

6. Organize the project preparation project acceptance at the end of July, and ensure that all preparations are completed before August 10.

20 17 model essay 2 according to the requirements of the "special meeting on teaching equipment engineering of weak schools in rural compulsory education" held by the county education bureau in 20xx 10 on 9 October, in order to ensure the smooth implementation of the reconstruction plan of weak schools in compulsory education in our school, give full play to the efficiency in the use of funds and improve the level of educational equipment in our school, the following schemes are formulated:

First, set up special classes:

Team leader:

Liu Cai (principal) is the first responsible person, who is fully responsible for the planning, coordination and implementation of this project; Deputy team leader:

Cui Changyu (vice president), the second responsible person, is responsible for assisting the client to fully implement the project.

The person in charge of the site, Shen Chuanming (general manager), is responsible for the cleaning and deployment of the site in the early stage. Members:

Wang Qingshu (laboratory administrator) is responsible for taking over the laboratory;

Zhu Liming (distance education administrator) is responsible for the installation of Banbantong;

Xiang Jing (librarian) is responsible for putting books on the shelves;

Tan Chuanzhen (public property manager) is responsible for the takeover of sports equipment;

Zhao Lan (Young Pioneers Counselor) is in charge of music and art.

Second, the site cleaning

Install the equipment that has the installation conditions now, and store the equipment that cannot be installed temporarily on the first floor of the science and education building.

Third, the venue arrangement:

1, class-to-class communication equipment: at present, there are 6 sets of * * * 4 (1) classes installed in the teaching building, 4 (2) classes, 4 (4) classes, 5 (2) classes and 5 (3) classes, and the other 6 sets are temporarily stored in the electronic lesson preparation room.

2. Experimental equipment: experimental storage room.

3. Science and Education Building Library.

4. Sports equipment: Use the existing site to install one by one.

5. Music and art preparation: temporarily stored in the dance classroom on the fifth floor of the science and education building. According to the existing conditions of our school, this scheme is specially formulated.

20 17 model of the implementation plan of the primary school reform project 3 according to the implementation plan of the education equipment construction project of weak schools in rural compulsory education in Hubei Province and the relevant regulations of the Badong County Education Bureau? Thin change? The relevant standards of the project, combined with the actual situation of our school, make this plan.

I. Project Implementation Leading Group and Work Arrangement

The categories involved in this project are: 6 sets of semi-standard communication, standardized laboratory project, library (500 new books) and sports and health art project. A large number of varieties, established through research? Thin change? Project leading group:

Team leader: Jia

Deputy Team Leaders: Chen Cibo and Fan Xingwei

Members: all faculty and staff.

The leading group consists of two working groups:

1, preparatory work class:

Comrade Chen Cibo is the team leader. First, make preparations for the adjustment of supporting houses and venues. The number of supporting rooms and venues required for teaching equipment should meet the specifications and standards. Second, the ground, walls, doors and windows, water and electricity, protective facilities, etc. The supporting rooms should be maintained and rebuilt, and the water source, power supply and drainage system of the laboratory and preparation room should be arranged in the corner of the room. The power cord (air switch) and network cable of class-to-class classroom and computer classroom should be installed near the blackboard and at the bottom of the podium. Three, the basketball stand, horizontal bar, parallel bars and other equipment installation site to implement. Project schools should make preparations for foundation pit installation, cement, sand and gravel in advance, and at the same time do a good job in the safety protection of foundation pit installation to prevent students from falling into the foundation pit and causing injuries. The fourth is to prepare the transit warehouse, be on duty, and cooperate with the installer. According to the progress of the project, all equipment should be properly kept before construction.

2. Special categories of equipment receiving, cleaning, storage, installation and debugging:

Team leader Fan Xingwei, according to the requirements, the equipment installation shall be carried out by the project winning company. After the arrival of the equipment, be responsible for counting the variety and quantity of the arrival, signing the receipt list and appointing a special person to keep it. In the process of construction, it is necessary to provide necessary cooperation, provide necessary personnel, tools and accommodation arrangements, and pay for themselves. In order not to affect the normal teaching order in the construction process, the project school should adjust the arrangement of school teaching activities according to the construction progress and try its best to make it correct.

Second, the facilities steps

1. Project preparation and preliminary design: (completed before June 10)

First, make preparations for the adjustment of supporting houses and venues; Second, the ground, walls, doors and windows, water and electricity, protective facilities and other necessary maintenance and transformation. The third is to implement the installation site of basketball stands, horizontal bars, parallel bars and other equipment.

2. Receiving goods and equipment installation (65438+ 10/030)

According to the installation of the Education Bureau, it depends on the specific situation.

3. Equipment testing (165438+ 10 month)

4. Project acceptance (facilities arranged by the Education Bureau)

5. Asset registration (according to the facilities arranged by the Education Bureau)

6. Technical training (after installation)

7. Teaching application (after installation)

8. Archives construction (completed by stages)