The waste treatment plant involves the urban environment and public **** hygiene, the government does have to co-ordinate arrangements to solve the problems that cannot be solved by the relevant enterprises and provide financial support.
Build a comprehensive waste treatment plant steps:
1, according to the investment project, such as the county comprehensive waste treatment plant, the establishment of a legal person company;
2, in the name of the newly established waste treatment plant company to invest in the total garbage treatment project to invest in the government where the total treatment of the project and the competent authorities to submit the investment in the comprehensive treatment of garbage project application documents. After the approval of the local government, you can invite the local land bureau, construction bureau, environmental protection bureau in collaboration with the site selection, comprehensive waste treatment plant site requirements from the village distance of about one kilometer, as far as possible away from the village, if the village is close to the village, then selected in the village crowded point downwind;
3, looking for the production of garbage sorting and fermentation of fertilizer sets of equipment to determine the company technical staff to determine the comprehensive garbage treatment plant process plan, determine the BT,BOT operation mode, process layout is reasonable, fully taking into account the government's requirements and the enterprise's own profit model, and do the garbage treatment plant project proposal;
4, the newly established garbage treatment plant company and the local government to sign a "municipal garbage franchise agreement";
5, commissioned by the design institute to do the "Feasibility Study", and get the approval of all levels of the Development and Reform Commission;
6, commissioned by the design institute to do the "feasibility study", and get the approval of all levels of the Development and Reform Commission;
6, commissioned by the local qualified environmental assessment department to do the "Environmental Impact Assessment Report", and get the local development and reform commission approval;
7, comprehensive waste treatment plant "Feasibility Study Report" and "Environmental Impact Assessment Report" came out, but also need to get the approval of the local development and reform commission, you can apply for the province, the city of the project subsidies and state bond funds; p>
8, "Feasibility Study Report" and "Environmental Impact Assessment Report" and other work done to get the local government agreed to build approval, the land department, "land siting opinion", you can start construction, construction side by side to do other procedures.
9, integrated waste treatment plant investment:
① apply for funding from the Development and Reform Commission, the local government to invest in their own, entrusted to operate (generally no more than eight years);
② BOT investment in construction, that is, corporate investment, the government to provide incentives, including the allocation of land at no cost to assist in the construction period to apply for provincial and municipal project grants and national bond funds. General business operation 25 - 30 years, and then transferred to the local government without compensation. ③ BOO investment mode of construction, i.e., the enterprise invests, the government provides preferential policies, and assists in applying for provincial and municipal project subsidies and national treasury funds during the construction period. The land is purchased by the enterprise itself, and the property rights will always belong to the enterprise.10, build a comprehensive waste treatment plant local government support:
①The Ministry of Construction stipulates that the waste treatment project can have a 25-30 year franchise, and the enterprise can have a monopoly on the operation for 25-30 years;