Question 2: engineering cost management in the management of enterprise management fee rate is how to calculate or how to take the value? 1, the project cost of management fees, profit is calculated on the basis of: (labor + mechanical costs) x rate
Rate according to the different types of projects to take the rate is also different, the rate of different provinces is also different, the specific reference to the cost of each province in the cost of various related rates of the fee standard ("Provincial Construction Project Costing Rules") on the specific instructions.
2, fees
Fees refers to *** and the relevant departments must pay the fees (referred to as fees). Including:
(1). Engineering quota determination fee. (Engineering quota determination fee = fee base x fee rate)
(2). Engineering sewage charges. (Calculated in accordance with the relevant regulations of the project location)
(3 ) D Social Security and Housing Provident Fund (Basic Pension Insurance, Unemployment Insurance Premium, Basic Medical Insurance Premium, Housing Provident Fund). . Social security and housing provident fund = withdrawal base x withdrawal rate
(4) Dangerous operations accidental injury insurance. (For construction workers to participate in the construction of accidental injury insurance construction enterprises shall not be charged for this cost)
3, tax refers to the national tax law should be included in the cost of construction and installation works of business tax, urban and rural maintenance and construction tax and education surcharge of the three taxes payable.
Tax calculation basis: tax = pre-tax cost x calculation factor (pre-tax cost = direct project cost + measures + other project costs + management fees + profit + fees; calculation factor selected according to the location of the project.)
Question 3: How to charge the management fee of home decoration project is appropriate, how to calculate the specific method? Decoration companies are different, the fees charged are also different.
Decorative companies, depending on the price point, are generally charged at 6% to 8%!
Question 4: how to calculate the comprehensive rate of construction first knock you what is the comprehensive unit price it
"Pricing Code" in the list of quantities of work comprehensive unit price refers to the completion of a prescribed unit of measurement of the list of items of the list of items of the volume of work of the sub-parts or the list of items of the measures of the labor costs, materials,,, the use of construction machinery and corporate overhead and profit, and a certain scope of the Risk costs within a certain range. Note that does not include fees and taxes and other non-competitive fees, so it is not the full meaning of the comprehensive unit price.
The calculation steps are as follows:
(1) determine the combination of quota subheading: generally a bill of quantities of items corresponding to the quota on several subheadings.
(2) Calculate the quantities of fixed subheadings: that is, calculate the quantities of bill of quantities corresponding to the items on the fixed quantities of several subheadings.
(3) Measurement of manpower and machinery consumption: you can refer to the contract or project local consumption quotas.
(4) to determine the unit price of manpower and machinery: according to the specific circumstances of the project and the market demand and supply of resources to determine, and consider the price adjustment factor.
(5) Calculate the list of items of engineering direct engineering costs
Direct engineering costs: Σ priced volume of work × (Σ labor consumption × labor unit price + Σ material consumption × material unit price + Σ shift consumption × shift unit price)
(6) Calculation of the list of items of management fees and profits
Management fee = direct engineering costs × management fee rate
Profit = (direct cost + management fee) × profit rate
(7) Calculate the list of items of the comprehensive unit price
Comprehensive unit price = (direct cost + management fee + profit) / list of works
(8) Approved comprehensive rate
Comprehensive rate = (comprehensive unit price - direct cost of works / list of works)/comprehensive unit price
Comprehensive rate = (comprehensive unit price - direct cost of works / list of works)/comprehensive unit price
It can be seen that the comprehensive rate = (direct cost of works / list of works) / comprehensive unit price
It can be seen that the comprehensive rate = (management fee + profit) / list of works (non-full cost)
If you add the fees and taxes, then the comprehensive rate = (management fee + fees + profit + taxes) / list of works (full cost)
The above mentioned management fee, fees, profits, taxes are calculated on the basis of the list of works corresponding to the direct cost of the project.
Question 5: How to calculate the construction management fee There are relevant provisions in the engineering construction quotas. There may be different places. According to the level of construction enterprises, take the respective rate calculation.
Question 6: How much is the construction project management fee ● Highway Project Management Fee Article 1 In order to strengthen the construction management of highway projects, standardize the behavior of highway project design changes to ensure the quality of highway projects, to protect people's lives and property safety, according to the "People's Republic of China *** and the State Highway Act", "Regulations on the Management of Quality of Construction Works", "Regulations on the Management of Construction Investigation and Design" and other relevant laws and administrative regulations, the development of these measures. Laws and administrative regulations, the formulation of this approach.? Full text
● River Engineering Maintenance and Management Fee
"Shandong Province River Engineering Maintenance and Management Fee Collection and Use Management Measures" has been approved by the provincial ***, is hereby issued and shall come into force. Full text
● Project Management Fee Definition
Project Management Fee refers to the capital construction staff wages, office expenses, travel expenses, depreciation of fixed assets for infrastructure, the use of tools, stamp duty and other management expenses related to the project. Full text
● construction project management fee
The project is the issuer of direct subcontracting project bidding, civil engineering for the general contractor, we are subcontractors, now the civil engineering party asked to pay 3% of the total contracting management fee and the total contracting with the fee of 3% is reasonable? Full text
● Subcontracting management fee
I contracted the project and subcontracted to the subordinate engineering team, the subordinate engineering team should pay us management fee. In the settlement of the subordinate engineering team, the management fee is deducted, and the outstanding payment of the project account. Now the subordinate engineering team to party A filed a lawsuit (we are party B), the court received the total settlement is not deducted the amount of management fee, now from party A to implement the project back to the money, including our management fee should be withdrawn, management fee has been into our account.
Question 7: construction project a class of costs, two types of costs how to calculate? Sub three types of enterprises, four types of works.
That is, enterprise one, two, three categories. Engineering one, two, three, four categories.
The fee categories of enterprises are assessed by the construction authorities in each province, and issued a certificate of recognition of enterprise fee categories, enterprises can get what kind of fee categories and this is related.
The project fee category, is the seal of the department of the examination of the map recognized. Of course, it is the same as the rate quota in the engineering class Bean division.
Enterprise fee categories directly affect the indirect cost
Project categories directly affect the direct cost of fee
Question 8: the project cost of direct engineering costs how to calculate the direct cost of direct engineering costs is the amount of labor, the amount of materials used, the amount of machinery used, respectively, multiplied by the unit price of their respective quotas.
Question 9: How to calculate the management fee of sub-parts? According to the bill of quantities, the management fee is based on the direct cost of the project, the profit is based on the direct cost of the project and the management fee and the calculation of the base, the calculation of the rate according to the management level of the construction unit and the project to determine the difficulty of the program, there is no uniform provision, the above costs are competitive costs, the bidders or the construction unit will be determined by the market conditions in general.
According to the unit price method or in-kind method of pricing, that is, fixed price, the basis for calculating the management fee is not necessarily, depending on the specific requirements, generally have a base of labor costs, or labor and machinery costs as a base, or direct engineering costs as a base, the profit is based on the direct and indirect costs and the calculation of the base, and finally calculate the tax, coupled with the purchase of equipment and appliances to arrive at the cost of the project
.
Question 10: project management fee in the end what is the cost of all the decoration company's decoration quotation will generally have a called "project management fee" charges and different companies vary greatly, some of the total cost of the project 5%, some of the total cost of the project 8%, some of the total cost of the project 10%! Charge, assuming that the total price of 200,000 yuan of home improvement projects, according to 5% charge is 10,000, according to 10% charge is 20,000 yuan. Only this amount, the maximum difference of 10,000 yuan. What is the reason for such a big difference in charges? Is there any specific legislation to regulate the so-called "project management fee"? At present, most of the ordinary residential interior decoration should be referred to the Ministry of Construction promulgated in 2002 Order No. 110, "Residential Interior Decoration and Decoration Management Measures" to implement, but we did not find the Ministry of Construction Order No. 110 in the relevant provisions of the collection of project management fees. So "project management fee" in the end what is going on? Decoration company on the "project management fee" is explained: half of the project means that the owners need to buy some of their own doors, hardware, sanitary ware, kitchen and bathroom facilities and other materials, these materials are placed on the site of the renovation need to decorate the company's personnel to manage the scene to avoid being damaged, which needs to be paid for a certain amount of management costs, and at the same time, during the construction period, the artificial Scheduling, material arrangements, coordination of various types of work and other costs are also included in the "project management fee". Some industry insiders say: the so-called "project management fee" is nominally for all the costs associated with the project staff, to put it bluntly is an unwarranted charges, that is, the decoration company disguised as a fee. Some people say that "project management fee" is a gimmick used by the decoration company to discount, in order to compete for customers, they will make "free", "discount concessions" tricks, in fact, is The "project management fee" as a buffer space of interest. In fact, the decoration is divided into two categories of engineering decoration and home furnishing, engineering decoration management fee is clearly defined, but home furnishing project management fee does not have a fixed and clear standards, charging home furnishing "project management fee" has become a decorative decoration industry rules of the industry, and there is no relevant departments to regulate this charge. So consumers in the face of this situation can only be helpless to accept, I hope that the relevant departments will soon be able to introduce provisions to standardize the "project management fee" charge standard