What information does the cyclone floating coil heat exchanger have when it leaves the factory?

Contents of ex-factory inspection

1 Review the quality certification documents, raw material qualification certificates and re-inspection reports (if necessary), manufacturing process inspection data, test data, supervision and inspection reports and other material certification documents prepared by the supplier before leaving the factory; Appearance inspection of equipment and materials before delivery, including conformity inspection of drawings (especially interface orientation, installation size, mating flanges, supports, etc.). ) and technical conditions of equipment and materials; Issue a release form.

2 packaging inspection of equipment and materials before leaving the factory.

3. Check the transportation scheme of equipment and materials.

4. Other contents that need to be checked.

I hope it helps you.