I. Processing Conditions

Applicants who meet all of the following conditions may apply: 1. Upon examination, it is necessary to demolish and relocate the people's air defense siren communication facilities; 2. The demolition unit will be responsible for all the costs of reinstalling and relocating the siren communication facilities.

Two, processing materials

(two copies) "

Three, the process

Online Process

1, the applicant registers and logs in the Shanwei City Online Office Hall, access to the online office page, read the required office guide.

2, the applicant according to the needs of the office in the online office hall to find the appropriate matters to apply, and upload electronic materials to submit confirmation. Need to provide paper materials at the same time, according to the prompt to the Municipal Government Service Center window to submit or mail paper materials.

3, the department receives the online application within 2 working days after the review of electronic materials. The applicant meets the eligibility requirements, and complete materials, format specifications, in line with the statutory form, to be accepted, eligible for online that issued a "receipt of receipt" or "acceptance of receipt"; does not meet the eligibility requirements for acceptance of online issued a "notice of correction of application materials" and one-time notification to the applicant needs to make corrections to all the materials. The applicant to make corrections to all the materials to be accepted. Applicants approved online by printing the relevant application form and the required paper application materials to the municipal government service center window to the official acceptance.

4, after acceptance, the reviewer within 8 working days of the paper and the information submitted online for review, meet the approval conditions, the issuance of approvals; review of the adoption of the decision, the decision maker within 2 working days based on the results of the review of the issuance of a decision to produce the results of the instrument; do not pass the issuance of the results of the issuance of the "decision not to pass". And one-time notification of the reasons for not passing. The applicant is required to make the required corrections and then re-admissible for review.

5. Applicants according to the SMS prompts in the online review of the situation, to the Municipal Government Service Center window to receive or mail the results.

Window process

1, the applicant to the Municipal Government Service Center window to apply, submit application materials.

2. Window staff to verify the application materials, on the spot to make a decision on acceptance. The applicant meets the eligibility criteria, and materials complete, standardized format, in line with the statutory form, to be accepted, issued on the spot "receipt" or "acceptance of receipt"; the applicant does not meet the eligibility criteria or does not meet the statutory form, the window staff is not admissible and issued on the spot "notification of inadmissibility". Applicant materials are incomplete, issued on the spot, "application materials correction notice" and one-time notification to the applicant needs to make corrections to all the materials. The applicant will be accepted after the material is corrected.

3. Accepted, the reviewer within 8 working days to review the material in writing, the decision maker within 2 working days based on the results of the review issued a decision. Review to be passed, within 1 working day to issue a "notice of approval", and produce the results of the document sent to the applicant. If the review does not pass, within 1 working day to issue a "decision not to pass" sent to the applicant.

4, section closure. Notify the applicant to the Municipal Government Service Center window to receive or mail the results.

Special links

None

Four, the location

Shanwei City, Shantou City, Honghai Avenue, Shantou Municipal People's Government Government Service Center, first floor

5, processing time limit

10 (working days)

Six, the agency

Shanwei Municipal Office of Human Defense

Seven, the cost of processing

7, the fee<

No charge

VIII. Legal basis

Guangdong Provincial Implementation Measures (2010)

Article 17 The competent department of the people's air defense shall carry out regular inspections of the alarm facilities set up in the units concerned.

The demolition and relocation of people's air defense alarm facilities required for urban construction must be approved by the competent people's air defense department at or above the county level where they are located, and the funds for their reconstruction shall be the responsibility of the units to be demolished and relocated.

Article source: Guangdong Province online office hall (/)