Acceptance is divided into factory acceptance, equipment arrival acceptance and user site installation and commissioning acceptance, the specific requirements are as follows:
Second, equipment factory acceptance
Equipment factory acceptance in accordance with the contents of the technical agreement for test acceptance. Factory acceptance of the main technical documents related to equipment appearance, key indicators such as verification, test acceptance should form a record.
Three, the equipment arrived at the opening and acceptance
The supplier is responsible for the transportation of the winning equipment, storage, and bear all the costs incurred in these processes. After the arrival of the equipment unpacking acceptance by the purchaser hosted and organized by the use of equipment, equipment, suppliers, such as acceptance of the acceptance of the group for acceptance and confirmation of the signature.
Equipment parts arrive at the unpacking acceptance mainly includes: quantity counting, appearance inspection, data review and so on.
The purchaser receives the equipment shipped by the supplier, that is, notify the supplier to send staff to the equipment storage place *** with the unpacking and acceptance.
Equipment unpacking inspection is completed, the purchaser and supplier inspection representative signed the inspection record. In the inspection process found in the supplier's defective parts and quality problems, the supplier to deal with timely, and bear the corresponding costs.
Four, the user site commissioning acceptance
Equipment transported to the user's designated site, the supplier should be equipment installation, commissioning, until the equipment to fully meet the technical specifications to ensure that the product meets the relevant technical requirements.
On commissioning, in addition to the purchaser is responsible for the provision of water, wind, electricity, gas, site, raw materials, other than the supplier is responsible for, so that the equipment has the conditions for commissioning, and to carry out on-site testing, testing the integrity of the equipment function, stability and technical parameters, compliance with technical requirements.
When the supplier's personnel carry out on-site operation, the construction personnel must comply with the laws and regulations on production safety and the relevant management regulations of the construction site, and go through the relevant formalities according to the requirements, and in case of accidents, the supplier's personnel will take the responsibility by themselves.
Confirmation of documents and information: verification of process records, inspection records, etc. of the manufacturing process: inspection of factory quality documents: inspection of random documents (including product qualification certificates of the equipment and its accessories, material certificates, complete flow charts of the mechanical and electrical systems (including electronic version), test reports, calibration certificates, calibration certificates, etc.).
V. Ensure that the goods acceptance of commissioning preparatory measures
Equipment installation preparations are mainly the following:
(1) Preparation of the necessary equipment operating instructions, and in accordance with the process procedures to prepare a good trial of raw materials or processed workpieces, as well as the necessary tools and process equipment.
(2) Train operators and maintenance personnel in advance. Staff participating in the installation must be trained to ensure the effectiveness and quality of the installation.
(3) Check and finalize the equipment installation layout plan.
(4) Remove obstacles from the installation site to provide sufficient and effective space for equipment installation.
(5) If necessary, improve the environmental conditions of the installation site.
(6) Check the necessary auxiliary facilities, such as power supply.