The correct installation of dust bag, skeleton and blowing of cloth bag dust collector is very important for improving the service life of dust bag and preventing leakage, bad installation of dust bag will bury a great hidden danger to the normal operation of dust collector in the later stage, such as dust bag falling, dust bag bag mouth ash, dust bag abnormal wear and tear and so on, bad installation of dust skeleton affects the use of time, bad installation of blowing pipe. The poor installation of the dust skeleton affects the use of time, and the poor installation of the blowpipe causes the poor dust cleaning effect of the dust collector, and the blowpipe falls and other failures.
So how to install the bag duster bag, the following we graphic introduction for user reference
1. Before installation, the bag cage into the bag, check whether the bag is suitable.
2. Clean up the material on the flower plate, clean and tidy, no material.
3. Bag installation pedals, to ensure that two people work inside the bag filter at the same time.
4. Bag filter bag set into the bag cage, there is a blockage phenomenon shall not be forced into, so as not to touch the bag.
5. When installing the bag, be careful and careful, do not let the bag and sharp hard objects collision, hook scratch, even if it is a small scratch, will cause the life of the bag is greatly shortened. The correct method of installing the bag is to first put the bag into the room from the hole of the box body, and then pinch the upper part of the pocket spring into a concave shape and put it into the hole of the box body, and then make the spring ring recover, and finally insert the bag cage gently from the mouth of the bag until the upper part of the bag cage cover really presses on the hole of the box body. In order to prevent the bag from being stepped on, it is required that a bag cage be installed for every bag loaded.
6. Installation order is from the sides to the center, from top to bottom, according to the order of installation.
7. Bag filter bag mouth installation 5 * 5mm PTFE sealing tape, sticking, fixed at the flower plate, the pressure deviation, shedding, need to be re-installed, specifically whether to add PTFE sealing tape according to the site conditions.
8. After fixing the pressure plate, use the pressure strip to lock it.
9. Install the air blowing pipe, and the air blowing port should be right at the mouth of the bag.
10. A blowing pipe should be installed on the top of each row of dust bag in the bag filter, and the blowing pipe should be positioned with the blowing pipe positioning mold supplied with the bag as the base, so that the blowing pipe spray holes and the center of the bag are aligned with each other. Each blowpipe is connected to the external air bag through a steel connector near the frame of the dust collector room, the other end of the blowpipe is fixed on the clamping bracket, the blowhole of the blowpipe facing down should be coaxial with the dust bag and venturi after the blowpipe is fixed.
11. Finally, after the installation of the re-inspection: skeleton after the end of the installation, to check all the installation of the skeleton, dust bag one by one to determine the quality of the installation, focusing on the inspection of the skeleton of the top cover with the bag pocket and the stability of the skeleton with the bag mouth of the situation and the skeleton of the stability of the performance.
In a word, the flower plate holes should be uniformly arranged, dust skeleton and dust bag will also be uniformly flat cloth in the flower plate, pay attention to the installation of dust bone and dust bag must be installed firmly, sealed, so that there will be no air leakage, it is good to clear the dust. In order to improve the utilization rate of dusting bone and dusting bag.