Information category: VIP project
Industry: energy and chemical industries
Location: Inner Mongolia
Progress stage: Construction in progress.
Construction period: 2008 -20 10.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project Description: The project plans to build a 2×600MW+2× 1000MW supercritical coal-fired air-cooled generator set with a total investment of 5 1 100 million yuan.
Anshun Power Plant (Phase III) Expansion Project
Information category: VIP project
Industry: energy and chemical industries
Location: Guizhou
Progress stage: preparation of project application report
Construction period: 20 10 -20 12.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The project will build two 660,000 kW coal-fired generating units. The total investment of the project is 5 billion yuan.
Xinjiang Luntai Power Plant (Phase I) Project
Information category: VIP project
Industry: energy and chemical industries
Location: Xinjiang
Progress stage: construction preparation
Construction period: 2009 -20 1 1 year.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The project will build two 350,000 kW supercritical air-cooled generating units. The total investment of the project is 2.794 billion yuan.
Expansion Project of 2×300MW Heating Unit in Zhumadian Thermal Power Plant (Update)
Information category: VIP project
Industry: energy and chemical industries
Location: Henan
Progress stage: engineering design (the fourth batch of auxiliary equipment is under tender)
Construction period: 2009-20 10.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The project plans to build a 2×300MW heating unit, which will form a heating capacity of120,000 square meters after completion.
The total investment of the project is 310.50 billion yuan.
Pearl River Power Plant 1× 1000MW Reconstruction and Extension Project
Information category: VIP project
Industry: energy and chemical industries
Location: Guangdong
Progress stage: engineering design
Construction period: 20-200911September.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal mills, coal mills, coal ploughs, wipers, transformers, lightning arresters, water filters, iron separators, frequency converters, exhaust pipes, calibration devices, resistance cabinets, switch cabinets, gates, compressors, cables and fire-fighting devices.
Project introduction:
The expansion project of this project is to build 1× 1000MW ultra-supercritical intermediate reheat condensing steam turbine-generator set+/kloc-0 /× 3110t/h high-efficiency ultra-supercritical primary intermediate reheat pulverized coal boiler, which is directly cooled by seawater from the Pearl River.
The total investment of the project is 3.5 billion yuan.
Pingdingshan No.2 Power Plant Phase I 2× 1 10,000 kW Unit Project
Information category: VIP project
Industry: energy and chemical industries
Location: Henan
Progress stage: construction in progress (bidding for the sixth batch of auxiliary equipment is under way)
Construction period: 20/2008-20 10/0 year.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The project plans to build 6 sets of 6,543,800 kilowatts.
The project is the first phase, and two 654.38+0 million kilowatt ultra-supercritical household coal-fired generating units will be built.
The total investment of the project is 7.49636 billion yuan. It is planned that 1 # unit will be put into production at the end of April 20 10, and 2 # unit will be put into production at the end of June 20 10.
Dalian Ganjingzi Thermal Power Plant Phase II Project
Information category: VIP project
Industry: energy and chemical industries
Location: Liaoning
Progress stage: Construction in progress.
Construction period: 2008-2009, 10 month.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The total planned capacity of the project is 4×300MW subcritical coal-fired heating unit. This project is the second phase of the project, and a 2×300MW subcritical coal-fired heating unit is built.
The total investment of the project is 3 billion yuan.
Luneng Chagan Naoer Power Plant (Phase I) Project
Information category: VIP project
Industry: energy and chemical industries
Location: Inner Mongolia
Progress stage: preparation of project application report
Construction period: 20/200912
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The project will build two 660,000 kW supercritical air-cooled coal-fired generating units, and reserve expansion conditions.
The total investment of the project is 5 billion yuan.
2× 1000MW expansion project of Lu 'an Power Plant Phase III
Information category: VIP project
Industry: energy and chemical industries
Region: Anhui
Progress stage: approval of feasibility study
Construction period: 2009-20 10.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The planned installed capacity of the project is 3600 MW. The first phase of the project is a 2× 135MW circulating fluidized bed coal-fired generator set with a total investment of 65438+220 million yuan.
Huaneng Yan 'an Power Plant Phase I Project
Information category: VIP project
Industry: energy and chemical industries
Location: Shaanxi
Progress stage: preliminary design (preliminary construction projects have been carried out, feasibility reports and special reports on land, environmental assessment, soil and water conservation and power grid access system have been compiled and passed the examination, and all special reports have been approved by the provincial level. )
Construction period: 2009-20 10.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The planned installed capacity of the project is 3.2 million kilowatts, with a total investment of 9 billion yuan. The first phase of the project is to build a 2× 600,000 kW domestic supercritical air-cooled coal-fired unit with an investment of 5 1 100 million yuan. After the completion, the annual power generation will be 654.38+03.2 billion kWh, and the profit and tax will be 560 million yuan.
The project plans to build a 2× 600,000 kW domestic supercritical air-cooled coal-fired generator set, and at the same time build supporting facilities for flue gas desulfurization and denitrification, leaving conditions for further expansion.
The total investment of the second phase project is 5 1 100 million yuan.
The second phase project of Zhejiang Neng Yueqing Power Plant "takes the big with the small"
Information category: VIP project
Industry: energy and chemical industries
Location: Zhejiang
Progress stage: approved by the state on March 20th.
Construction period: 2009-20 10.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The construction scale of the project is 4× 600,000 kW units, which will be built by stages, with a total investment of 654.38+0.08 billion yuan. There is still room for further expansion of the site layout. The 2× 600,000 kW domestic supercritical coal-fired generator set in the first phase of the project has been completed for power generation, and the annual power generation will reach more than 654.38+035 billion kWh after all the projects are completed.
In the second phase of the project, two 660,000 kW domestic ultra-supercritical coal-fired units will be built, desulfurization and denitrification devices will be built, and 793,500 kW small thermal power units in Zhejiang Province will be shut down accordingly.
The total investment of the project is 4.865438 billion yuan.
Nanjing Xiaguan Power Plant's "Big Pressure and Small Pressure" New Construction Project in Different Places
Information category: VIP project
Industry: energy and chemical industries
Location: Jiangsu
Progress stage: approval stage
Construction period: 2009 -20 1 1 year.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
Two 600,000 kW ultra-supercritical coal-fired generating units will be built in this project, and 275,000 kW small units in Jiangsu Province and 82,450 kW small units in Hunan Province will be shut down accordingly, occupying 600,000 kW of thermal power construction scale in Jiangsu Province.
The total investment of the project is 510.20 billion yuan.
Huozhou Power Plant's Project of "Taking the Big with the Big, Taking the Small with the Small"
Information category: VIP project
Industry: energy and chemical industries
Location: Shanxi
Progress stage: engineering design
Construction period: 2009 -20 1 1 year.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal mills, coal mills, coal plows, wipers, transformers, lightning arresters, water filters, iron separators, frequency converters, exhaust pipes, calibration devices, resistance cabinets, switch cabinets, gates, compressors, cables and fire-fighting devices.
Project introduction:
The project is to shut down and dismantle the original four 65,438+10,000 kW and 1 6 MW high-energy and small-capacity generating units, and build two 600,000 kW supercritical air-cooled coal-fired generating units. After the project is completed and put into production, the coal consumption of power generation will be reduced from 400 ~ 4 10g to about 300g. The water consumption for power generation is less than one-third of the original, and the water source is changed from the original groundwater to mine drainage.
The total investment of the project is 4965438+200 million yuan.
Changchun Southeast Thermal Power Plant 2×350MW Phase I Project
Information category: VIP project
Industry: energy and chemical industries
Area: Jilin
Progress stage: approval of feasibility study
Construction period: 2009-20 1 1 year.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The project plans to build two 300 MW and two 600 MW heating units. In the first phase of the project, it is planned to build two 350,000 kW domestic supercritical coal-fired power generation and heating units, and simultaneously build flue gas desulfurization and denitrification facilities, which have the conditions for further expansion.
The total investment of the project is about 2.55 billion yuan.
Cogeneration project of Huangtai Thermal Power Plant
Information category: VIP project
Industry: energy and chemical industries
Location: Shandong
Progress stage: preliminary design
Construction period: 20/2009 -20 10/0.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
Huangtai Power Plant has passed the sixth phase of construction, with 8 units and installed capacity of10.025 million kilowatts. In this phase of the project, two 350,000 kW supercritical coal-fired cogeneration units will be built by means of "high pressure and low pressure", and desulfurization and denitrification devices will be built simultaneously. Used to replace the original 1 ~ 6 high-energy heating unit in power plant. At present, 1-4 units have been shut down and will be dismantled soon, and units 5-6 will be dismantled after the completion of this project.
Dalu 2×300MW Kengkou Coal Gangue Thermal Power Plant Project
Information category: VIP project
Industry: energy and chemical industries
Location: Inner Mongolia
Progress stage: preliminary design
Construction period: 2009-20 10.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
In this phase, a 2×300MW subcritical, once-reheated, double-cylinder and double-row steam direct air-cooling extraction steam-heating turbine-generator set is constructed, and a 2× 1062 t/h subcritical natural circulation fluidized bed boiler is configured; The planned capacity is 4×300MW generator set.
The total investment of the project is about 2.5710.07 billion yuan.
Shuangyashan Coal Gangue Comprehensive Utilization Power Plant Project
Information category: VIP project
Industry: energy and chemical industries
Location: Heilongjiang
Progress stage: being approved.
Construction period: 20/200912
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The project will build a 300,000 kW generator set.
The total investment of the project is 65.438+89.78 million yuan.
Yanshan power plant 2× 1 MW unit project
Information category: VIP project
Industry: energy and chemical industries
Location: Henan
Progress stage: preparation of project application report
Construction period: 20 10 -20 12.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The project will build two 654.38+0 MW ultra-supercritical coal-fired generating units.
The total investment of the project is 7 billion yuan.
Wuhu Power Plant (Phase V) 1 Unit Project
Information category: VIP project
Industry: energy and chemical industries
Region: Anhui
Progress stage: construction preparation
Construction period: 2009 -20 1 1 year.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The project plans to build two 660,000 kW ultra-supercritical coal-fired units.
The project is a 1 unit project, and 660,000 kw ultra-supercritical coal-fired units will be built, with an annual coal consumption of 1.4 million tons.
The total investment of the project is 2.776 billion yuan.
2×600MW Project of Fugu Qingshuichuan Power Plant Phase II
Information category: VIP project
Industry: energy and chemical industries
Location: Shaanxi
Progress stage: Construction in progress.
Construction period: 20/2008-20 10/0 year.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet and gate.
Project introduction:
The total planned installed capacity of the project is 6×300MW, supporting 6 million tons/year Fengjiata Coal Mine, and the total investment scale is estimated to be 1 1 100 million yuan.
This project is the second phase with a planned capacity of 2600MW. In this phase, 2×600MW air-cooled coal-fired units will be built, and there is room for expansion.
The total investment of the project is 4 billion yuan.
Pingdingshan Luyang Power Plant (Phase II) Expansion Project
Information category: VIP project
Industry: energy and chemical industries
Location: Henan
Progress stage: preparation of project application report
Construction period: 20 10 -20 12.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The project will build two 654.38+0 MW supercritical units. Coal is provided by Pingdingshan Coal Group and transported by the first-phase railway.
The total investment of the project is 7 billion yuan.
Taishan Power Plant Phase II Extension Project (the first two 1000MW units)
Information category: VIP project
Industry: energy and chemical industries
Location: Guangdong
Progress stage: Construction in progress (chimney construction bidding in progress)
Construction period: May 28th-August 20th, 200810.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The total capacity of five units in the first phase of the project is 3 million kilowatts, and in the second phase, four ultra-supercritical coal-fired generating units with a capacity of 6.5438+0 million kilowatts are planned to be built in stages.
This project is the second phase project of Units 6 and 7, and 2× 100 kW coal-fired generator set will be built. And reserve 2× 100 kW unit site.
Unit 6 is scheduled to be put into production on April 28th, 20 10, and Unit 7 is scheduled to be put into production on August 28th, 20 10.
The total investment of the project is 8 billion yuan.
Jincheng Thermal Power Plant Phase I (2×300MW) Project
2009-04-20
Information category: VIP project
Industry: energy and chemical industries
Location: Shanxi
Progress stage: construction in progress (the third batch of auxiliary equipment bidding is under way)
Construction period: March 20, 20091010.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The project is located in Shangxin 'an Village, Jincun Town, Zezhou County, Jincheng City, Shanxi Province. A 2×300MW air-cooled turbo-generator set is newly built in this period. It is planned to put the first unit into production in August of 20 10, and the second unit into production in June of 20 10.
The total investment of the project is 3 1 100 million yuan.
2×600MW project of You Ke Middle Thermal Power Plant, Inner Mongolia.
Information category: VIP project
Industry: energy and chemical industries
Location: Inner Mongolia
Progress stage: approval of feasibility study
Construction period: 2009-20 1 1 year.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The first phase of the project expanded the 2× 600,000 kW coal-fired generator set.
The total investment of the project is 4.83 billion yuan.
2×600MW Project of Gongxian Power Plant Phase I
Information category: VIP project
Industry: energy and chemical industries
Location: Sichuan
Progress stage: Construction in progress.
Construction period: 2008-20 1 1 year.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
In the first phase of the project, a 2× 600,000 kW domestic supercritical coal-fired generator set will be built, and two sets of flue gas desulfurization devices and # 1 set of flue gas denitrification devices will be built simultaneously, and the conditions for installing the flue gas denitrification device of #2 set will be reserved. The planned capacity of the power plant is 2.4 million kilowatts, and expansion conditions will be reserved.
The total investment of the project is about 5 billion yuan.
2× 1000MW Phase II Extension Project of Suizhong Power Plant
Information category: VIP project
Industry: energy and chemical industries
Location: Jiangsu
Progress stage: planning stage (bidding for start-up and commissioning of subsystems and complete sets of units #3 and #4 is under way).
Construction period: 2009-20 10.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Transformer, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The second phase of the project will build a 2× 1000MW ultra-supercritical thermal power unit.
In this project, the #3 and #4 units of Suizhong Power Plant's 2× 1000MW second-phase expansion project have been debugged in sub-system, whole set of start-up, special test, networking test and performance test, and the No.3 unit is planned to be debugged.
Group B was put into operation on February 30th, 2009, and Unit 4 was put into operation on March 30th, 20 10.
Pipe pile foundation treatment project of Binhai thermal power plant
Information category: VIP project
Industry: energy and chemical industries
Location: Zhejiang
Progress stage: construction preparation
Construction period: 2009-20 1 1 year.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The scale of this project is 2×300MW coal-fired heating generator set, and at the same time, flue gas desulfurization facilities and 1 unit full flue gas denitrification device will be built. This project is for pipe pile foundation treatment.
The total investment of the project is about 2.7 billion yuan.
Tianjin Junliangcheng Power Plant Phase V "Taking the Big with the Small" Project
Information category: VIP project
Industry: energy and chemical industries
Area: Tianjin
Progress stage: construction in progress (the eighth batch of auxiliary equipment bidding is under way)
Construction period: 2009-20 10.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Overview of the project: The project will build two 350MW sub-critical parameter double extraction heating steam turbine-generator sets with a total investment of 2.6 billion yuan.
2× 660 MW Unit Expansion Project of Shangdu Power Plant Phase III
Information category: VIP project
Industry: energy and chemical industries
Location: Inner Mongolia
Progress stage: preliminary design
Construction period: May 20, 200910.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project Description: The project plans to build a 2×66 MW domestic supercritical direct air-cooled coal-fired generator set with a total investment of 6 billion yuan.
Kailuan Guye Gangue Kengkou Power Plant Project
Information category: VIP project
Industry: energy and chemical industries
Location: Hebei
Progress stage: being approved.
Construction period: 2009 -20 1 1 year.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project Overview: The project will build two 300,000 kW direct air-cooled units with a total investment of 3 billion yuan.
Expansion Project of Coal Gangue Comprehensive Utilization Power Plant (Phase II)
2009-04- 15
Information category: VIP project
Industry: energy and chemical industry, environmental protection
Location: Henan
Progress stage: preparation of project application report
Construction period: 20 10 -20 1 1 year.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The project will build a 300,000 kW circulating fluidized bed unit. The total investment of the project is 65.438+0.3 billion yuan.
Ningxia Ningdong Coal Gangue Power Plant (Phase I) Project
Information category: VIP project
Industry: energy and chemical industry, environmental protection
Location: Ningxia
Progress stage: Construction in progress.
Construction period: 2008 -20 10.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
In this project, two 330,000 kW subcritical air-cooled circulating fluidized bed pure condensing generator sets are built. The total investment of the project is 2,998.84 million yuan.
Comprehensive Utilization of Coal Gangue Power Plant (Phase I)
Information category: VIP project
Industry: energy and chemical industries
Location: Henan
Progress stage: being approved.
Construction period: 2009 -20 1 1 year.
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The project will build a 300,000 kW circulating fluidized bed unit. The total investment of the project is 65.438+0.4 billion yuan.
Qitaihe Tiedong Coal Gangue Power Plant Project
2009-04-09
Information category: VIP project
Industry: energy and chemical industry, environmental protection
Location: Heilongjiang
Progress stage: preparation of project application report
Construction period: 20/200912
Main equipment: generator, steam turbine, boiler, pump, valve, fan, crane, coal crusher, coal feeder, coal pulverizer, coal plough, wiper, transformer, lightning arrester, water filter and iron remover.
Frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate and compressor.
Project introduction:
The enclosure of the project covers an area of 250,000 square meters, and a 300,000-kilowatt subcritical coal gangue and coal slime mixed combustion unit is built, equipped with1.025t/h subcritical and natural circulating fluidized bed boiler. The total investment of the project is 65.438+978 million yuan.
Southeast thermal power plant project
Information category: VIP project
Industry: energy and chemical industry, environmental protection
Area: Jilin
Progress stage: preparation of project application report
Construction period: 2009 -20 1 1 year.
Main equipment: generators, steam turbines, boilers, pumps, valves, fans, cranes, loaders, coal pulverizers, coal feeders, coal mills, coal ploughs, wipers, transformers, lightning arresters and water filters.
, iron remover, frequency converter, exhaust pipe, calibration device, resistance cabinet, switch cabinet, gate, compressor, cable and fire fighting device.
Project introduction:
The project will build two 350,000 kW heating generating units. The heating range includes Jingyue Development Zone, Shuangyang Economic Development Zone, Shuangyang Cultural Development Zone and Shuangyang City Zone. The construction contents include factory area, standby ash yard, special railway line, ash conveying road and water supply system. The total investment of the project is 2.55 billion yuan.