Hospital power outage emergency plan drill plan
In order to ensure that things or work are carried out in an orderly and effective manner, it is often necessary to formulate an excellent plan in advance, which is a type of planning document. What are the format and requirements of the plan? Below is the hospital power outage emergency plan drill plan I compiled for you. You are welcome to share it.
Hospital power outage emergency plan drill plan 1
1. Purpose of the drill:
To improve the ability to respond to sudden power outages and ensure the normal development of medical work.
2. Exercise content:
Quickly switch the department where the normal 1 transformer fails and causes a power outage to be powered by the normal 2 transformer.
3. Exercise time: 13:30 pm on May 31, 20xx
4. Exercise location: Outpatient building, inpatient building, high-level rooms.
5. Emergency command team:
Commander-in-chief: XXX
Deputy commander-in-chief: XXX
6. Working group
Team leader: XXX
Deputy team leader: XX
Team members: Engineering Department, Security Department
7. Preparation before the exercise:
p>Notify all power outage departments of the drill plan and prepare emergency lights, etc.
8. Description of the exercise:
On May 30, 20xx, the Chang 1 transformer in the high-end distribution room suddenly failed, causing power outages in many departments of the outpatient building, medical technology building, and inpatient building. The engineering department quickly carried out emergency repairs according to the plan. After 15 minutes, the power supply was switched to the normal 2 transformer and the power supply was restored. (This exercise will not affect key departments such as the operating room, hemodialysis room, and ICU, because these departments are equipped with terminal automatic switching devices, which can automatically and instantaneously switch to the normal 2 transformer in an emergency to ensure normal power supply)
< p> 9. Exercise procedures:1. Commander-in-Chief XXX announced the start of the exercise.
2. The transformer fault light in the high-end distribution room is often on, and the staff quickly reports it to the logistics support department and property manager, and implements emergency repairs at the same time.
3. After receiving the report, the Logistics Support Department immediately commanded the security center, used the public broadcasting system to issue a sudden power outage notice, and notified medical staff in outpatient and emergency departments and wards to maintain order. Carry out consoling publicity to stabilize the mood of outpatient and emergency departments and patients or family members in elevators (implementation of emergency plan for trapped people in elevators).
4. After the property management department received the notice, six staff members from the engineering department were divided into three groups and entered the high-end distribution room and main high-end distribution room of the gate building and inpatient building respectively, and switched the power supply transformer from Normal 1 to Normal 2. Restore power supply and troubleshoot Chang 1.
5. The elevator team is responsible for inspecting each elevator.
6. Security guards are responsible for patrolling outpatient and emergency departments.
7. Fill in the emergency information afterwards and report it to the hospital office.
10. Notes:
1. Sufficient preparations must be made before the exercise, and publicity work must be in place.
2. Electricians must strictly follow operating procedures when switching power supplies. Hospital power outage emergency plan drill plan 2
1. Purpose of formulation
In order to respond to a sudden large-scale power outage in the hospital, organize and restore power supply quickly and orderly to ensure the safety of patients and In order to reduce property losses, ensure the smooth flow of electricity in the hospital, and promote the institutionalization and standardization of accident emergency response, this plan is formulated in accordance with relevant national laws and regulations and combined with the actual situation of our hospital.
2. Scope of application
The so-called "sudden large-area power outage accident" (hereinafter referred to as "large-area power outage accident") in this plan refers to the damage to important facilities due to serious natural disasters. Or due to damage or other reasons, the safety defense line of the entire hospital's power system suddenly failed, and the power grid suffered a large-scale collapse or collapse.
3. Emergency Principles
The handling of large-scale power outage accidents implements the policy of "prevention first, constant preparation" and follows the principle of "unified leadership, improving mechanisms, clarifying responsibilities, strengthening cooperation, The principle of quick response and decisive measures.
IV. Organizational structure
The hospital has established an emergency leading group for large-scale power outage accidents, with an emergency repair team under it.
1. Hospital Large-area Power Outage Emergency Leading Group
Team Leader: General Manager
Deputy Team Leader: Dean
Members :Manager of the Human Resources and Administration Department
Logistics Supervisor
Responsibilities of Electrical Maintenance Workers:
(1) Do a good job in daily safe power supply work, implement the safety production responsibility system, and prevent A large-scale power outage occurred.
(2) When a large-area power outage occurs, emergency response to the power outage should be carried out promptly and the power supply should be restored as soon as possible.
(3) Determine the activation and termination of emergency plans based on the severity of large-scale power outage accidents.
(4) Report the accident situation to superiors in a timely manner and announce it to the public.
(5) Request external support when necessary.
(6) The leader of the leading group is the first person responsible for fulfilling the provisions of this plan. Member units should, under the unified command of the leading group, perform their duties and responsibilities, and work together to do a good job in comprehensive social emergency response in the event of a large-scale power outage.
2. Emergency Repair Team
Captain: Logistics Supervisor
Members: Electrical Maintenance Workers
Responsibilities: When an accident occurs, organize personnel Carry out rescue operations; report the accident situation to the command team, send a request for help to the power supply department when necessary, and summarize the experience and lessons learned in emergency rescue work afterwards.
5. Emergency procedures
(1) Emergency procedures for the electrician class of the logistics department
1. Emergency procedures for planned power outages
(1 ) When electricians receive a call from the power supply company notifying them of a power outage or other forms of power outage notification, they must ask clearly when the power outage occurred, how long it lasted, and the reason for the power outage. Handover is clear.
(2) Notify the leader of the emergency leadership team (notify the general person on duty in the middle of the night), explain the cause of the power outage, the specific time of the power outage, how long it will be outage, and make preparations for the backup second power supply.
(3) If during normal working hours, time permitting, the Human Resources and Administration Department shall issue a written notice to each department.
(4) If the time is urgent, after receiving the notice from the power supply company, the leader of the emergency leading group (notify the general staff on duty at night) should be notified immediately, explaining the situation, and the Personnel and Administration Department will issue a notice to each department. Notice: Important departments must clarify the time for power outage with the head nurse and make a plan for power outage.
(5) Go to the power distribution room 30 minutes before the power outage and conduct preliminary inspections for switching to the backup second power supply. In the event of a power outage, the normal start-up and delivery of the backup second power supply must be ensured within 15 minutes.
(6) 10 minutes before the power outage, park all passenger elevators on the first floor.
(7) When the external network fails, start the generator power supply to ensure power supply to key departments such as the operating room and emergency department.
(8) Keep records of the operation of the backup second power supply and records after the mains power supply is restored.
2. Temporary power outage emergency procedures
(1) When a temporary power outage occurs, you should immediately call the power supply company to find out the cause of the power outage and the length of the power outage.
(2) Notify the emergency team leader or the general on duty to explain the situation.
(3) If the power outage is short (within 10 minutes), you should wait for the mains power to come before sending high and low voltage electricity.
(4) If the power outage lasts for a long time, you should immediately prepare to switch to the backup second power supply.
(5) Due to various reasons, the dual power supply fails to start. The backup generator should be started as soon as possible to ensure the power supply of key departments.
(6) Keep records of the operation of the backup second power supply.
(7) When there is a power outage due to internal reasons in the hospital, it is necessary to find out the cause of the power outage, whether it is a high-voltage circuit or a low-voltage circuit. If the high-voltage circuit fails, the hospital electrician should immediately introduce the backup power supply and contact the power supply department's emergency repair team in time to restore it as soon as possible to ensure power supply; if the hospital's mortgage circuit fails, the cause should be quickly identified and the circuit restored according to operating regulations.
(2) Emergency procedures for departments and departments
1. After receiving the power outage notice, each department should cut off all power supplies and power supplies if permitted, and wait until the circuit returns to normal. Put into use.
2. After receiving the power outage notice, immediately prepare for the power outage. Use backup power if rescuing patients.
3. After a sudden power outage, immediately find ways to rescue patients and power their operations, maintain rescue work, and turn on emergency lighting, etc. And the electrician or general on-duty should be notified promptly.
4 Critically ill patients who use ventilators during surgery should always have a simple respirator next to the machine. In the event of a sudden power outage, medical staff should immediately disconnect the ventilator and use a simple respirator to maintain breathing. For patients using electric nitrogen inhalation, use a 50ML syringe connected to a nitrogen suction tube to inhale nitrogen.
5. If there is a sudden power failure in both lines, before the generator in the hospital supplies power, the medical staff should first ensure the patient's rescue; the nurse should remain calm, and those who are put on the ventilator should use the hand-holding ball method and monitor the patient. The instrument operator uses manual measurement of blood pressure and pulse, and the electric nitrogen inhaler uses a 50 ml syringe connected to the nitrogen suction tube for suction, etc., and closely observes and asks for changes. The remaining staff immediately call the electrician, the personnel and administration department, and use emergency lights for lighting. .
6. Strengthen inspections of wards, comfort patients, and pay attention to fire and theft prevention.
7. After the elevator encounters a sudden power outage, the logistics staff must do a good job in thinking about the passengers, call the outside, and use manual methods to release all passengers.
6. Safeguard measures
1. Electricians should perform daily maintenance on the generator to ensure that the generator is put into use at any time.
2. Electricians must master power supply knowledge and operating specifications, and pay attention to operating safety.
3. Clinical departments regularly have emergency lights, flashlights and other lighting supplies, which should be inspected regularly and kept in good condition.
4. The logistics department should organize emergency power outage drills 1-2 times a year. Through the drills, everyone will be familiar with the emergency response procedures for sudden power outages to ensure patient safety. ;