How to write a program for the implementation of the construction of a special program?

How to write a program for the implementation of ad hoc construction?

xxxx city center hospital

Ward building project construction implementation plan

First, the guiding ideology

In order to accelerate the pace of construction of the ward building, to ease the hospitalization of the hospital district tense situation, to improve the patient's hospitalization environment, to meet the needs of patients, and to better provide patients with high-quality services, and at the same time to make the ward building to play the economic benefits as soon as possible. To complete the 2011 economic income targets and five-year plan to lay the foundation.

Two, construction goals

The construction of the ward building to meet the design requirements, that is, the completion of the internal and external decoration, the installation of internal devices in place, with the conditions for receiving patients.

Third, the establishment of the organization

Leader: xxx

Deputy Leader: xxx

Members: xxxx,xxxx

Fourth, specific measures

1, the development of the construction plan, drawing construction nodes to complete the detailed drawings.

2, in accordance with the construction plan, the organization of construction units to discuss, analyze, and determine the unit construction program and progress.

3, the main line of construction of the interior decoration, the development of monthly and weekly construction plans. Installation and other ancillary construction according to the interior plan to develop construction programs and implementation of the construction plan. Ensure that the progress of the renovation to the end.

4, take cross construction, shift work way to promote the construction progress.

5, the development of incentives and penalties to ensure that the construction of the ward building construction progress on schedule.

5, evaluation and rewards and punishments

1, the ward building put into use, the early completion of the target tasks related to the hospital with the department and individuals to reward.

2, the implementation of monthly quantitative assessment of the progress of the project, the amount of work completed on time to plan the construction unit in the allocation of funds to give priority to. Failure to complete the construction program on time to give economic penalties.

Sixth, the progress of the plan

1, the external decorative works: February 25 - May 27 to complete the construction of decorative panels on the exterior walls. Including the east elevation completed before March 8th. West elevation completed before March 11th. North elevation completed before March 25th. South elevation to be completed by April 18th. Roof and sixth floor to be completed by April 30th. Decorative board painting, completed before May 27th.

2, interior decoration works: March 1 - May 20 to complete the decoration works. Among them, the construction of floor and wall tiles was completed on April 12th. Ceiling, curtain box, sealing wall construction completed before May 20th. Stairwell, ward, office room wall paint construction completed on May 10th. Stainless steel tie rod construction completed on May 12th.

3, civil engineering: March 1-April 30 to complete the civil rough construction.

4, water supply and drainage works: March 1 - June 2 to complete the construction of water supply and drainage works. Among them, hot and cold water system construction completed before May 25th. Drainage system construction completed before May 17th. Sanitary ware installation completed before June 2nd.

5, strong electrical engineering: March 1 - June 9 to complete the construction of electrical engineering.

Among them, layer bridge, wire pipe, wiring, cable. completed before April 10th. Distribution box installation and pressure line completed before May 9th. Cable laying and pressure line completed before April 24th. Lighting, panel installation completed by June 2nd. Bathroom exhaust fan hanger and duct installation completed before March 26th. Lightning protection and grounding completed before April 19th. Energized execution in addition to the wrong June 9 to complete.

6, other projects: fire systems, weak power systems, air conditioning systems, medical gas systems, purification systems, corridor construction, peripheral pipeline construction and hardening and other ancillary construction to actively cooperate with the internal and external renovation construction progress, before May 30th, with the conditions for delivery.

7, the project follow-up work: July reported to the competent authorities to give the organization acceptance, and organization of all engineering information to verify, do a good job before the audit of the preparatory work. August will be the final account of the project information reported to the audit department for audit. Strive to end the audit before the end of the year.

Seven, the central hospital ward building 2011 progress schedule (attached)

March 13, 2011

Engineering project proposal to write

Chengdu Zhongzhe for your answer

Engineering construction cost in our country for a long time there is a proposed budget over the estimate, the budget over the proposed budget, the final account over the budget of the three over the phenomenon, a serious plague of construction project investment efficiency and management. Construction project investment efficiency and management. Project construction project proposal is to optimize the construction program, design program on the basis of the various stages of the construction program, the use of certain methods and measures to control the cost of the project within a reasonable range and approved cost limits and put forward the project proposal.

An engineering construction project from the plan to build to put into operation, generally through the construction decision-making, construction implementation and delivery of three stages. Zhongzhe consulting suggests that the main steps are:

1, project proposal

Project legal person according to the national economy and social development of long-term planning, industry planning and construction of the unit where the town planning requirements, according to the unit's development needs, after the investigation, prediction, analysis, compilation of project construction project proposal.

2, feasibility study report

After the approval of the project proposal, the project legal person entrusted with the appropriate qualifications of the professional writing agency, the proposed project in the technical, engineering, economic and external collaborative conditions and other aspects of the feasibility of a comprehensive analysis, demonstration, comparison of the program, recommend the best program.

3, preliminary design

After the approval of the feasibility study report, the project legal person entrusted the appropriate qualification of the design unit, in accordance with the requirements of the approved feasibility study report, the preparation of preliminary design. After the approval of the preliminary design, the design estimate is the maximum limit of investment in the project, without approval, shall not be arbitrarily exceeded.

4, construction design

After the approval of the preliminary design, the special legal person entrusted with the appropriate qualifications of the design unit, in accordance with the approval of the preliminary design, the organization of the construction design.

5, the annual investment plan

Engineering and construction project proposal, feasibility study report, preliminary design approval to the competent authorities to apply for inclusion in the investment plan.

6, start report

7, completion and acceptance

To control the choice of design options and preliminary design cost estimates with investment estimates; cost estimates to control the technical design and revised estimates cost; engineering construction projects must be used properly, with the cost estimates or revised estimates to control the construction drawings design and budget costs. In order to rationalize the use of human, material and financial resources, to achieve better investment efficiency.

How to write the construction program plan?

Construction Organization Design

A project overview

(a), the preparation of the basis, design specifications and construction standards

1, engineering construction design files and construction design drawings and related design files.

2, bidding files, bidding Q&A minutes and other relevant information.

3, the state and higher units and the company's safety production, civilized construction regulations, rules.

4, the natural conditions of the construction site and specific circumstances. (hydrogeology, meteorological environment, transportation, water supply and power supply, etc.).

5, the company's quality system based on ISO9001 relevant files.

6, the current national mandatory standards for engineering construction:

7, provincial, industry regulations, norms:

8, quality acceptance norms, standards:

9, China's other current construction acceptance norms and operating procedures.

10, our company's existing technology, equipment and years of accumulated construction experience in similar construction projects information.

(ii), the location of the project

(c), architectural design

(d), structural design

(e), process design

(f), quality standards

The quality of this project to meet the standards of qualified.

Second, the overall construction program and construction preparation

(a), the mobilization cycle

(b), the construction guiding ideology

(c), the construction unfolding sequence

(d), the project schedule

Specific construction period:

(e), the division of construction tasks

(f), Temporary Facility Works

(vii) List of Provisional Facility Works

No. Name Area m2 Location Starting Date

(viii) Main Construction Machinery and Installation Requirement Plan

List of Construction Machinery and Installation

No. Name Specification Requirement Remarks

Number of Units

3. General Sub-parts Project construction program

(a) construction sequence

(b) construction measurement

1. Measuring instruments

Construction measuring instruments see "Measuring Instruments Selection Table". As follows:

Measuring Instruments Selection Table

Name Model Quantity Accuracy Usage

2. Measuring Position Copying

(C) Earthwork

1. Earth Excavation

2. Earth Transportation and Backfilling

3. Construction Right-of-Way

(D) Ground Treatment

(E), Reinforcing steel works

Specific allowable deviation (mm) test method

(F), template works

(VII), concrete works

(VIII), expansion joints, construction joints, the retention of

(IX), scaffolding works

(X), full water test

Fourth, the construction of technical measures

(A), bedding construction

(B), footing construction

(C), column construction

(D), wall construction

(E), the top construction

(F), the construction of watering zones

(V), the prevention and control of concrete quality problems

V. Project quality assurance system and measures

(I.) Quality policy:

(II.) Quality objectives:

(III.) Quality Management

Quality Management Programs

1. Quality Assurance Programs

2. Process Quality Execution Programs

(IV.) Quality Control

VI. Safety Measures to Ensure the Project

(I.) Management Objectives

(II.) Organizational Management

(III.) Safety Management System

(IV.) Behavioral Control

(V.) Management of Labor Employment

(VI.) Construction Safety Precautions

VII, Civilized construction and environmental protection measures

(a) Management objectives

(b) Organizational guarantees

(c) Work system

(d) Civilized construction measures

(e) Preventing atmospheric pollution

(f) Preventing water pollution

(g) Preventing construction noise pollution

<(h) Waste management

(i) Management of materials and devices

(j) Selection of environmentally friendly and energy-saving materials and devices

(k) Other measures

(8) Construction organization and staffing plan

(a) Construction organization structure

(b) Block diagram of construction organization

(a), schedule commitment

(b), to ensure that the construction progress plan of the technical and organizational measures

xiii, winter, rainy season construction measures

(a), seasonal construction technical measures

(b), the rainy season construction program

(c), the winter construction technical measures

Fourteen, financial security and construction measures to reduce construction costs

(a), financial security measures

(b), construction measures to reduce construction costs

Fifteen construction organization to ensure that measures ...

Engineering construction bidding program, is there a model?

MBA Think Tank document should have this kind of reference model, you go there to find a look at it.

Engineering construction report outline how to write?

General product production project project feasibility report outline Zhengzhou Jingliu Zhicheng enterprise management consulting preparation

General

1.1 Project name and project unit

1.2 Project construction location

1.3 Project construction scale and content

1.4 Project investment estimation and financing

1.5 Scope and Basis of Preparation

1.6 Conclusion and Recommendation

1.7 Main Technical and Economic Indicators

Chapter 2 Background and Necessity of Construction of General Product Manufacturing Project

2.1 Background of Construction of General Product Manufacturing Project

2.2 Necessity of Construction of General Product Manufacturing Project

Chapter 3: Market Demand Analysis

Chapter 4: Construction Conditions and Site Selection for General Product Manufacturing Projects

4.1 Geographic Location

4.2 Natural Conditions

4.3 Socio-Economic Condition

4.4 Infrastructure Condition

4.5 Transportation Condition

4.7 Site Selection.

Chapter 5 General Product Manufacturing Project Construction Program

5.1 Construction Content

5.2 Construction Principles

5.3 General Product Manufacturing Project Planning Program

5.4 Engineering Program

Chapter 6 General Product Manufacturing Project Utilities

6.1 Water Supply & Drainage /p>

6.2 Power Supply and Distribution

6.3 Ventilation and Air Conditioning

6.4 Maintenance

Chapter VII General Product Manufacturing Project Project Energy and Water Conservation Measures

7.1 Energy Consumption Standards and Energy Conservation Norms

7.2 Energy Conservation Measures

7.3 Energy Conservation Management

7.4 Water Conservation Measures<

7.5 Comprehensive Utilization of Resources

Chapter 8 Environmental Protection

8.1 Enforcement Standards for Environmental Protection

8.2 Major Pollution Sources and Pollutants

8.3 Environmental Protection Measures

8.4 Conclusion on Environmental Protection

Chapter 9 General Product Manufacturing Engineering Projects Labor Safety and Health and Fire Protection

<9.1 Labor Safety and Health

9.2 Fire Safety

Chapter 10 General Product Manufacturing Project Organization and Human Resource Allocation

10.1 Organization

10.2 Labor Staffing

10.3 General Product Manufacturing Project Management

Chapter 11 General Product Manufacturing Project Project Implementation Progress and Bidding

11.1 Implementation Progress

11.2 Bidding

Chapter 12 Investment Estimation and Financing of General Product Manufacturing Project

12.1 Investment Estimation

12.2 Financing

Chapter 13 Financial Evaluation of General Product Manufacturing Project

13.1 Basis and Scope of Financial Evaluation

13.2 Selection of Basic Information and Quotations

13.3 Estimation of Financial Benefits and Costs

13.4 Financial Analysis

13.5 Analysis of Uncertainty

13.6 Conclusion of Financial Evaluation

13.7 Analysis of Risks

Chapter Fourteen. Conclusion and Recommendation

14.1 Conclusion

14.2 Recommendation with Figures and Schedules

How to Write Construction Proposal for Building Engineering Bidding Program Knowing

(1) Bidding Letter;

(2) Appendix of Bidding Letter;

(3) Bidding Deposit;

(4) Certificate of Identity of Legal Representative;

(5) Bidding file to sign the power of attorney;

(6) Bidding file requires the bidder to submit other information (this item is not in the form, if necessary, by the bidder in the form of text or tables).

The commercial part mainly includes the following:

If the comprehensive unit price form is used:

(1) Requirements for bidding price;

(2) Summary table of bidding price;

(3) Quotation table of list of main materials;

(4) Quotation table of list of fixtures;

(5) Quotation table of list of quantity of work;

(6) List of works ad hoc price calculation form;

(7) other information required for the tender offer (there is no format for this item, and if needed, it will be put forward by the bidder in the form of text or form, or by the bidder at the time of the tender offer).

Using the form of unit price of work and materials:

(1) the requirements of the tender offer;

(2) the summary table of the tender offer;

(3) the list of the main materials offer table;

(4) the list of the fixtures offer table;

(5) the calculation table of the price of work and materials of the divisional works;

(6) the cost of the division of the project Calculation table;

(7) other information required for the tender offer (this item is not in the form, when needed by the bidder in text or form, or the bidder in the tender offer).

11.4 The technical part mainly includes the following:

(1) construction organization design or construction program

a. The main construction method of each sub-part of the project;

b. The main construction machinery and equipment invested in the project, and the main construction machinery on-site plan;

c. The labor force arrangement plan;

d. The technology to ensure the quality of the project. Technical organization measures to ensure project quality;

e. Technical organization measures to ensure production safety;

f. Technical organization measures to ensure civilized construction;

g. Technical organization measures to ensure the duration of the project;

h. General layout of the construction;

I. It is necessary to explain the other contents.

(2) Project Management Organization Equipped

a. Project Management Organization Equipped Table;

b. Resume Table of Project Manager;

c. Resume Table of Project Technical Leader;

d. Other auxiliary explanatory information. (3) The name of the special project to be subcontracted and the subcontractor.

The application for qualification examination includes:

(1) General information of the bidder;

(2) Annual turnover information sheet;

(3) List of works completed in the last three years;

(4) List of works currently under construction;

(5) List of financial status in the last three years;

(6) List of status of the joint body

(7) experience in similar projects;

(8) construction experience in similar site conditions;

(9) other information required by the bidder to submit.

Engineering and construction procurement files need to write technical bids, special implementation program to write how ah? Write specific construction methods? Or something else?

Description of the bidding file for the model, the bidding unit bidding should be based on their own actual situation and bidding files, bidding applicants pre-qualification instructions and other files to prepare the bidding file, bidding file by the bidding letter part, the business part and the technical part of the three parts. Engineering construction tender bidding file Special case No.: Special case name: Bidding file content: Bidding file Bidding letter part Bidder: (seal) legal representative or his proxy: (signature or seal) Date: Table of Contents legal representative identity certificate Bidding file signing power of attorney Bidding letter Bidding letter Bidding letter Appendix Bidding stretcher Bank Guarantee Format Bidding Guarantee Bidding file requires the bidder to submit the other bidding information Name of organization: Nature of organization: Date of establishment: Period of operation: Name: Sex: Age: Position: He is the legal representative of (Name of Bidder). Hereby certify that. House building and municipal infrastructure construction bidding file model two, bidding file signing power of attorney This power of attorney declares: I (name) is the (name of the authorized person) of the legal representative of the (name) is authorized to entrust the (name) of the (name of the unit) for my company to sign the bidding file of the project's legal representative of the authorized agent, I acknowledge that the agent of the bidding file signed on behalf of my full authority for the project. Content. I recognize that the agent has full authority to sign the bid file for this project on my behalf. The agent does not have the right to subdelegate and is hereby authorized. Agent: (signature) gender: age: ID card number: position: legal representative: (signature or seal) entrusted to authorize the date: to: (name of the bidder) 1, according to your bidding file number for the project bidding file, in accordance with the relevant provisions of the site and the study of the bidding file of the bidding instructions, the terms of the contract, the drawings, construction standards and bills of quantities of the project and other relevant files, we are willing to sign the tender file on behalf of me. After visiting the site and studying the bidding instructions, contract terms, drawings, construction standards and bill of quantities and other relevant files, we are willing to bid in (currency, amount, unit) (lower case) for the construction and completion of the above mentioned project according to the above mentioned drawings, contract terms, construction standards and bill of quantities and assume the responsibility of warranty for any quality defects. 2, We have audited in detail all the bidding files, including the modification files (if any) and the relevant attachments. 3, We acknowledge that the addendum to the bid letter is an integral part of our bid letter. 4, If we are awarded the contract, we guarantee to complete and hand over all the work within the calendar days of the construction period specified in the contract agreement. 5, If we are awarded the contract, we will submit a bank guarantee for % of the above total price or a performance guarantee for % of the above total price issued by a qualified and competent surety organization as a performance guarantee in accordance with the provisions of the contract. 6,We agree that the bidding file submitted shall be valid for the period of validity of the bidding as specified in Clause 15 of the Instructions to Bidding Applicants and we shall be bound by the same if we are awarded the bid within this period. 7, Unless otherwise agreed and effective, your notification of award and this bid file will become part of the contract file binding the parties. 8,We will submit (currency, amount, unit) as a bid security together with this bid letter. Legal representative or agent: (Signature or seal) Name of the bank: Account Bank Account Number: Date 4, the bid letter appendix No. special case content of the contract terms No. agreed content Remarks performance bond bank guarantee performance bond amount of the contract price of the % of the construction of the construction of the preparatory time after the signing of the contract in the days after the miss the liquidated damages amount of yuan days miss the limit of compensation for the early award of the construction of a total construction period of calendar days of quality standards of the quality of the project Advance Payment Amount Advance Payment Guarantee Amount Progress Payment Time Days after Issuance of Monthly Payment Voucher Completion Settlement Payment Time Days after Issuance of Completion Settlement Payment Voucher Warranty Period Based on the Period Agreed in the Warranty Letter IV. Bidding Files V. Bid Guarantee Bank Guarantee Format (Specific Format to be Provided by Guarantee Bank) VI. (hereinafter referred to as the Bidder) and (Bid Guarantee Agency) as the Guarantor (hereinafter referred to as the Guarantor)*** together assume the responsibility to pay (currency, amount, unit) (lower case) to (name of Bidder) (hereinafter referred to as the Bidder), and both the Bidder and the Guarantor shall be bound by this Guarantee. The Guarantor is willing to provide the Bidder with a Bid Security in view of the Bidder's participation in the Bidding of the Bidder's (Bidding Project). This guarantee is conditional upon the Bidder failing or refusing to sign the Contract Agreement as required by the Bidding Instructions, failing or refusing to submit the Performance Bond as required by the Bidding Instructions, or withdrawing the Bidding File during the Bidding Period if the Bidder receives a Notice of Award from you during the Bidding Period. Insofar as you specify the conditions that give rise to any of the foregoing, the ......

What is the difference between the planning design program and the construction engineering program design

The engineering construction process is as follows: ad hoc proposal ---------- preliminary design stage - - construction drawings design stage - - bidding stage - - contract implementation stage - completion and acceptance of the stage and feasibility of the stage of the paragraph ||||| investment estimate ---------- design estimate - ----- budget cost ---------- contract price ------- settlement price ----- actual cost (final price) Estimates have feasibility study investment estimates and preliminary design estimates of two kinds, the budget and construction drawings design budget and construction budget, the capital construction project budget is the general name of the above estimates, estimates and budgets. In the different stages of the project, the project investment has estimates, estimates, budgets, settlements and final accounts and other different names, these "calculations" based on different roles, its accuracy is also "progressively more detailed", one more than a more realistic reflection of the actual investment in the project. 1. Estimates, also known as investment estimates, occur in the project proposal and feasibility study stage; estimates are based on the project planning program (program design), the project project project may incur engineering costs (including construction and safety works, outdoor works, installations and installations, etc.), engineering and construction costs, reserve costs and construction period interest (if there is a loan) for calculating the size of the investment project and the choice of financing options For the ad hoc investment decision-making departments for reference; estimates should pay attention to accurate and comprehensive calculation of other costs of construction, this part of the cost of regional and policy is strong. 2. Estimates, also known as the design estimates, occurred in the preliminary design or expansion of the preliminary design stage; estimates need to have a preliminary design or expansion of the preliminary design drawings, the construction costs of the ad hoc construction costs calculated to determine the cost of the project; preparation of budget estimates should pay attention to not omitted, missing or double-counting, the standard should be consistent with the fixed amount of the cost. Budget, also known as construction budget, occurs in the construction design stage; budget needs to have construction drawings, summarize the special case of man, machine, material budget, to determine the cost of construction and safety works; the key to preparing the budget is to calculate the amount of work, accurately applying the budget quota and fee standards. 4. Settlement, also known as the completion of the settlement, which occurs in the stage of completion of acceptance of the project; the settlement of the general by the engineering contractor (construction unit). Contractor (construction unit) submitted, according to the case of the construction process of change negotiation, adjust the construction budget, to determine the final settlement price of the project case; settlement is based on the construction contract and change negotiation records (note that all parties sign), accurate calculation of the tentative price and the actual amount of the deviation, compared with the relevant amount of standards, calculating the construction budget of the omission and lack of part of the project cost entitlement.

How to write a construction project is construction contracting "program".

Wenshan County, the new Pingba urban village renovation project implementation program

First, the project renovation implementation program

In order to improve the village appearance of the new Pingba village, so that the village to become a set of logistical support with the Wenshan Panax ginseng park, ethnic customs, food culture as one of the new rural areas, to solve the villagers in the loss of the land of the life of the way out of the issue of the full implementation of the Wenshan County, the old city of urban renovation, accelerate the pace of urban construction. The old city of Wenshan County will be remodeled to speed up the pace of urban construction, add bricks and tiles to the cityscape, and create a better economic atmosphere. With reference to the State Council Decree No. 305 "urban housing demolition and relocation management regulations" and the Yunnan Provincial People's *** Decree No. 109 "Yunnan Provincial Urban Housing Demolition and Relocation Management Provisions" of the relevant provisions of the actual situation, combined with the new Pingba villagers group, the new Pingba villagers group to apply for the Wenshan County People's *** study agreed to by the Wenshan County People's *** approved by the Wen Zhengban Fa [2005] No. 487 file approved by the new Pingba villagers group to organize the implementation of the old village renovation of the new Pingba village. Implementation of the new Pingba village old village renovation work, in order to make this work smoothly, especially the development of this implementation plan.

(a) the scope of the demolition

New Pingba old village within the scope of the renovation, farmers owned land, houses and appurtenances.

(2) demolition and resettlement work steps and time

1. The legal title of the farmers' houses and appurtenances for the assessment of the farmers' land (containing the use of certificates, undocumented, self-reserved land) for the measurement of the announcement. (From November 2005 to February 2006)

2. Publicity and mobilization, and release of the demolition notice. (November 2005-February 2006)

3. Signing the agreement on old village reconstruction with each farmer. (From January 2006 to March 2006)

4. Organize the demolition of houses and appurtenances of the farmers and the construction of temporary houses. (From February 2006 to March 2006)

5. Leveling the site of the planning area and building the road rough. (March 2006-April 2006)

6. The land for the resettlement of farmers was honored and the houses were built by each farmer. (Time for March 2006-December 2006)

7. Collectively improve the construction of roads and electricity, telecommunications, water supply and drainage, and put into use. (Before December 30, 2006)

(C) Compensation method

After the assessment report on the farmers' house property rights was made by Lianyi Appraisal Company, Xinpingba villagers' group gave one-time compensation according to the assessed price. There is no monetary compensation for homesteads, self-reserved land, or vacant land.

The contracted land expropriation price is unified at 62,600 yuan/mu, and the Xinpingba villagers group will give compensation at once.

(D) resettlement

1. old village transformation of farmers land cash

(1) local resettlement of farmers, according to the original certificate area and the area of the undocumented (including self-reserved land) of the total area of the resettlement of the land cash, the land according to the 10-meter-wide unit, the resettlement of the area of the area of the calculation of the area of the land includes housing footprints, the area in front of the door to the concession area, the area of open space behind the house. Less than a unit of area, by the collective 100 yuan / square meter to the farmers to buy, the farmers can not be privately transferred to the outside world.

(2) local resettlement of farmers, according to the original certificate area and the total area of undocumented area (including self-owned land) to cash resettlement land, land allocation according to the 10-meter-wide unit, the resettlement area is calculated to include the area of the house, the area of the front concessions, the area of the open space behind the house, less than the area of a unit of $ 100 / square meter by the farmers to the collective to buy, but farmers can not be used for the external The company's website is not available to the public.

(3) Land use certificates are issued for state-owned land use certificates according to the actual realized area. The houses, walking roads and green areas within the scope of the land use certificates are constructed by the user in accordance with the planning (the part of the setback next to the carriageway is constructed by the collective), and all the constructions must be implemented in strict accordance with the planning.

(4) resettlement plots in accordance with the first signed agreement to the order of the day of the drawing of lots to prioritize the selection of land for local resettlement. Not in the local resettlement of farmers, by the villagers group in accordance with the assessment of the company's compensation price to implement the resettlement, the collective is responsible for the resettlement of the area of the road, water supply, power supply work. Farmers who are not in the planning area (bounded by Wenma Highway) are willing to participate in the planning, according to the area of each farmer's own land as the standard land allocation, such as less than one, the difference in the area of the part of the area of 500 yuan / square meters to the collective purchase.

(5) Temporary resettlement land arrangement and resettlement subsidy compensation

Demolition and relocation is carried out in accordance with the first group by leaning against the Sanqi Industrial Park 70 meters away, and the second group 60 meters inward in turn. Temporary resettlement land in Sanqi Industrial Park, each household is allocated 80 square meters of temporary resettlement land, the first demolition of the first recognition of the land. In February 15, 2006 before the signing of the agreement, February 28 before the relocation of the demolition of the farmers, by the villagers group to give 1000 yuan / household resettlement subsidy fee incentives, the construction of the planning area of the farmers must be in March ......

How to write an application for construction project planning

A certain limited company file so-and-so [2007] No. 06 on the request to give "so-and-so" district construction project report Luqiao District Development and Reform Bureau: Luqiao District "so-and-so "District (tentative name) is located in the streets of Luqiao District, the land by the Taizhou City Bureau of Land and Resources Luqiao Branch on December 8, 2005 announcement by auction. December 29, 2005 by the Taizhou City Limited company to ten thousand yuan price bidding to obtain the right to use the land, and pay the deed tax of ten thousand yuan, and June 16, 2006 to obtain the land certificate. The project has obtained Taiwan Road environmental construction [] No. on the Taizhou City, Ltd. new road community project environmental impact report form of the approval of the reply and road water sea fishery [] No. on the Luqiao District Lotus Pond Jiyuan community project soil and water conservation program of the approval of the reply. In accordance with the approval reply of No. Taijian Gauge [] on the detailed construction plan of Luqiao District, Taizhou City, the land area of Luqiao District "" district is from the land boundary in the north to the land line, from the planning road in the south, from the east to the Yinyuan Road and from the planning road in the west, with the area of requisitioned land of square meters and the area of net land of square meters. The total construction area is square meters (excluding basement), of which the residential construction area is square meters, the club building area is square meters, and the property management is square meters. The basement construction area is square meters. It consists of a small high-rise residential building and a clubhouse. It is expected that the project construction investment of 100 million yuan (excluding land payment), the funds will be invested by our company in batches, to take the side of the development and sales, the lack of bank loans and self-financing to solve the problem. I implore your bureau to be a project. Hereby report! Taizhou city limited company July 4, 2007 Subject: construction project project report Taizhou city limited company office July 4, 2007 issued must be the red header file way (internal information was deleted by me please understand)