After a certain project entered the installation and commissioning stage, a fire occurred due to lightning. The construction unit shall notify the project supervision agency within 24 hours after the

After a certain project entered the installation and commissioning stage, a fire occurred due to lightning. The construction unit shall notify the project supervision agency within 24 hours after the fire ends.

Questions: 1. This loss is caused by lightning and is a force majeure.

Question: 2. The liability should be shared as follows:

(1) The medical expenses required by the construction unit personnel are estimated to be 150,000 yuan, and the damage compensation for the leased construction machinery is 100,000 yuan; The construction unit shall bear the loss of 20,000 yuan for idle construction machinery and the 10,000 yuan for necessary management and security personnel costs;

(2) A vehicle worth 250,000 yuan temporarily parked on site by other units If the car is burned, other units will be responsible for it;

(3) The project itself will suffer a loss of 1.5 million yuan; and it is estimated that the cleaning and repair costs required for the project will be 2 million yuan, which will be borne by the construction unit;

(4) Equipment to be installed with a total value of 1 million yuan; since the background information does not mention whether it is supplied by A or purchased by the construction party as stipulated in the general construction contract, the responsibility cannot be determined; if it is supplied by A, it will be borne by the construction party , if it is stipulated in the contract that the construction party purchases it, the construction party will bear it.

Notes on power installation projects

After the power installation project is completed, inspection and debugging are required to ensure the normal operation of the entire power supply and distribution system. Through the power installation and debugging process, errors in the power installation process are checked to ensure normal power supply.

After the busbar is installed, check whether there is any damage, observe whether there is any discoloration of the paint and the heat film, and determine whether the busbar joint is overheated. Busbars and insulators must also be cleaned regularly, fasteners and joints must be inspected, and rusted bolts and other components must be replaced.