Construction site contract labor, sign a contract to pay attention to what details?

Template sub-projects labor subcontract

Party A:

Party B:

Project name:

Project address:

Party A will be constructed by the Mau Chau Shan Industrial Zone plant engineering template sub-projects contracted to party B. According to the relevant provisions of the Contract Law; in line with the principle of equality and mutual benefit, by Party A and Party B **** the same study, full consultation to reach the following terms.

I, the main work content, scope

1, all concrete involved in supporting the template (foundation bedding, bearing platform, frame columns, structural columns, beams, slabs, elevator shafts, shear walls, stairs, air-conditioning panels, convex window panels, filler walls within the belt, daughter wall, window sill pressure roof, fire pool, janitorial, crane foundation, septic tank template) and all the templates production and installation and removal.

2. The support system of all the above formwork items and the fixed scaffolding system of all foundations, columns and shear wall insertion positions, regardless of whether they are super-high or not, shall be erected and dismantled by the formwork team itself.

3. Party B will provide its own machinery and equipment: six table-top electric saws, six hand electric saws, ten electric drills, and a number of boarders, and the above machinery and materials shall be submitted to Party A with certificates of conformity.

4, all the templates of the molding diagram must be reviewed by the project director, technical director, foreman, before assembling the production according to the diagram, the template is assembled, the number of the template, sealing brush sealant, template site assembly, wood square planer support, correction, reinforcement, pouring concrete templates to look after as well as repair and reinforcement, the template removal of the ash after the cleanup of the potpourri.

5, Party B's own small materials and appliances: nails, wire, pistol drills, pistol drill bits, fishing line, ink bucket, pencil, horizontal pipe, broom, glue bucket, 3.5 meters of aluminum square (5) line drop, ink, paint number, etc. In addition to the Party to provide materials for all the other sporadic materials, appliances, machinery are prepared by Party B.

6, after demolding the template, wooden square, frame materials, fasteners, etc., all the carpentry materials cleaning, tie rod cleaning, nailing on the template, and in the specified time sub-specification, variety of classified in the designated location of the stacking neat, the floor of the template left behind by the material (including wood shavings, crumbs, PVC casing, the wall of the tie rod), such as the slag of the cleanup.

7, templates, frame materials, fasteners lifting, running in the field must be in accordance with the safety and technical briefings and construction programs, violators of the 200/person fine.

8, party B template engineering materials used in the field by party B is responsible for getting off the pile, must be in accordance with the requirements of civilized standardized construction.

9, the floor on the line, by party A control of the main axis, by party B sent two people to cooperate with the put fine size.

10, Party B is equipped with more than two full-time quality inspectors, follow the work, with the project quality inspector, foreman, check the quality of the project.

Second, the project contracting method and the total contract price

1, contracting method: labor cost contracting.

2, the total contract price:

The total price of the project is a package fixed, and according to the construction drawings of the construction area of 52646.3 square meters settlement, the unit price of the project is 32.8 yuan/m2, the total price of ¥ 1726798 yuan (RMB 172,712,000,798 yuan in capital letters).

3, a, b both sides signed this contract, party b in three days to pay the work period, quality deposit of 30,000 yuan to party a, after the completion of the project by party a confirmed qualified no legacy of the problem, in ten days the full amount of interest-free return.

Three, the payment method:

1, Party B completed from the foundation to ± 0.00, Party A pay Party B 100,000 yuan, complete the three-storey structure to pay two hundred thousand yuan, complete the six-storey structure to pay three hundred thousand yuan, complete the nine-storey structure to pay three hundred thousand yuan, the main body of all the roof as well as all the completion of the ladder pool to pay two hundred thousand yuan, all the works belonging to the scope of the template class contracting to pay two hundred thousand yuan within 10 days of the completion of the project. After all the works belonging to the scope of contract of formwork class are completed, 200,000 yuan will be paid within 10 days, and the balance will be settled within three months after the completion of the main works, and within 10 days from the date of Party A's acceptance confirming that the works are qualified and there is no quality problem.

2. When Party B withdraws each progress payment, it must prepare the part of workers' salary in the progress payment into the employee's salary table and provide it to Party A. Party A will pay this part of the progress payment directly to the employees according to the content of the employee's salary table provided by Party B, and the rest of the progress payment will be paid to Party B directly.

3, Party A found that Party B in the construction process there are technical and quality problems, Party B should be unconditional immediate rectification and rework, rectification of ineffective Party A has the right to require Party B to withdraw from the scene, and the total amount of work completed by 70% of the final payment.

Four, project quality requirements

1, the template of this project requires Party B to demold, fully meet the specification requirements, the construction process at any time to accept the site engineer's inspection test.

2, beams, slabs, columns, shear walls, the surface must be smooth and clean, the line corners square and straight, no leakage of slurry, pockmarked.

3, axis, door and window opening size should be accurate, the flatness of all templates should be controlled within 3㎜, the verticality within 3 meters should be controlled within 5㎜, the total height should be controlled within 0.5 ‰, and the height difference at the joints should be controlled within 1㎜, and all the corners of yin and yang should be straight and neat, and not more than 5㎜ per 3 meters.

4, finished product protection:

Party B bottom mold support, finished product protection is particularly important, with steel, water and electricity installation with the process of pouring concrete, Party B must have someone to watch the mold, this person must have a high degree of responsibility, or else, out of a problem in addition to a fine of 200 yuan each time, such as material wastage, that is, punished with a fine of double the price of materials.

5, all work must be in accordance with the specifications and construction technology construction, or each point by 200 yuan penalty.

Five, schedule requirements

When the project is under construction, Party B must be prepared in accordance with Party A, the total construction period, monthly, ten days, day plan schedule on time and qualified to complete. If it is not completed, it will be penalized according to 300 yuan/day, and those less than one day will be calculated according to one day.

Sixth, safety requirements

In order to implement the "safety first, prevention first" policy, according to the Chinese people *** and the country "construction safety management regulations" and the relevant state laws and regulations, to clarify the safety of their respective rights, obligations and responsibilities, as follows:

1, A and B must conscientiously implement the national, provincial and municipal labor protection, production safety authorities issued by the relevant production safety, fire safety guidelines and policies, and strictly implement the relevant labor protection laws, regulations and provisions.

2, Party B shall strictly abide by the safety operation procedures formulated by Party A, the special operators of the certification and assessment system; safe production job responsibility system safety inspection system; safe production rewards and penalties system; safety education system and so on.

3, A and B of the relevant personnel must be seriously on the unit of production safety system and technical knowledge of safety education, enhance the concept of the rule of law, improve the workers' awareness of production safety and self-protection ability to urge workers to consciously abide by the discipline of production safety, systems and regulations.

4. Before construction, Party A shall educate Party B's management and construction personnel on entering the site for safety production, and introduce relevant safety production management system, regulations and requirements. Party B shall organize and convene a meeting for construction personnel to educate them on production safety and notify Party A to appoint relevant personnel to attend the meeting to introduce the relevant regulations and requirements on safety and fire prevention in construction, and Party B must check and supervise the construction personnel to strictly abide by them and earnestly implement them.

According to the project content, characteristics, Party A and Party B should do a good job of safety and technical briefing, and written briefing

materials, to fulfill the signature formalities, briefing materials archived for inspection. Weekly project safety meeting system and make good records.

5, during the construction period, Party B assigned responsible for the project's safety, fire prevention work, Party A supervision, inspection and guidance. Party A has to assist Party B to improve safety, fire prevention management, as well as the obligation to supervise and inspect, for the detection of hidden dangers, Party B must be rectified within the deadline, the expiry of the rectification, will be fined 200 yuan each time.

6, in the process of production and operation of personal protective equipment and protective equipment, must have "three certificates" (i.e.: production license, product certification, product testing reports). Party A shall supervise Party B construction site personnel correctly wear protective equipment, such as Party B violators per person / times 30 yuan fine.

7, Party B personnel on the construction area, operating facilities and equipment, tools, etc. must be carefully inspected, found that the hidden danger, should immediately stop construction, and the implementation of corrective action by the relevant units before allowing construction. Once the construction, it means that the construction unit confirms that the construction site, operating environment, facilities and equipment, tools, etc. meet the safety requirements and are in a safe state, Party B is responsible for the consequences of accidents caused by the above factors during the construction process.

8, Party B shall operate strictly according to Party A's technical safety instructions, such as Party B's brutal, unauthorized construction of safety accidents occurring by Party B is responsible.

9, Party B in the construction of various equipment and tools used during the construction period should be self-prepared by Party B. If Party B needs to borrow from Party A, it will be responsible for the safety accidents. If Party B needs to borrow or rent from Party A, it should be handled by both parties for borrowing or renting formalities, and formulate the relevant safety use and management system. Party A should ensure that the loaned equipment and tools are in good condition and meet the safety requirements, Party B must be inspected, and make a written record, once Party B receives, equipment and tools should be responsible for the custody and maintenance of Party B, and the strict implementation of safe operating procedures. Due to the equipment, tools factors or the use of improper operation and casualties caused by the borrowed party responsible for the use.

10, Party B personnel on the construction site scaffolding, all kinds of safety facilities, safety warning signs, shall not be removed without authorization, change. If you really need to dismantle the change, must be responsible for the construction site and Party A assigned safety management personnel agreed, and take the necessary, reliable safety measures before dismantling. Party B personnel unauthorized demolition of the consequences caused by the party to be held responsible for the responsibility of the parties involved, resulting in work-related accidents, are Party B responsible.

11, special operations must implement the "special operators safety training and assessment of management regulations" by the special operations of the safety and technical assessment and then licensed to work. Small and medium-sized machinery operators must be in accordance with the provisions of the "fixed machine and fixed person" and licensed to operate; lifting and hoisting operators must comply with the "ten do not hang" provisions, is strictly prohibited unauthorized, unlicensed operation, is strictly prohibited do not understand the electrical appliances, machinery and equipment, unauthorized operation of electrical appliances, machinery and equipment.

12

12, party B must strictly implement all kinds of explosion-proof system, flammable and explosive places are strictly prohibited smoking and open flame, fire fighting equipment is not allowed to be diverted to other uses. Welding, gas cutting operations should be in accordance with the provisions of the fire procedures. Strictly abide by the provisions of the "ten do not burn", is strictly prohibited the use of electric stoves and other large-capacity tableware cooking and heating, winter construction, such as open-flame heating operations must be used to implement the anti-freeze measures for fire prevention and heating, should obtain the consent of the site supervisors, the implementation of fire prevention, anti-poisoning measures, and assign a person on duty.

13, Party B need to use the electrical equipment provided by Party A, should be tested before use, and make a good record of the test, such as does not meet the safety regulations should be promptly proposed to Party A, Party A should actively rectify the rectification of qualified before use, violation of the provisions of the unauthorized pulling of the electrical wiring or without the permission of Party A, the consequences of the party responsible for the Party.

14, Party B in the construction, should pay attention to the protection of underground pipelines and high-voltage overhead lines. Party A shall give detailed instructions on underground pipelines and obstacles, Party B shall carry out the requirements of the instructions, and in case of any situation, it shall contact Party A and relevant departments in time to take protective measures.

15, implement the principle of who is responsible for the safety of construction. Party B personnel during the construction of casualties, fire, fire, machinery and other major accidents caused by Party B is responsible for, Party A should cooperate in emergency rescue of the injured, protect the scene, and according to the procedures reported to the next level.

16, Party B must provide Party A with a list of construction management personnel and workers on site and related documents, including copies of identity cards of operators and relevant documents, personnel should be relatively stable after the determination of the personnel, where changes are required, must notify Party A in a timely manner, and only after obtaining the consent of the change.

17, where workplace accidents occur, in accordance with the principle of "four do not spare" investigation and treatment of the responsible party to bear all the economic losses and the corresponding legal responsibility.

18. In case of work-related accidents, Party B will be responsible for the medical expenses up to RMB 3,000 yuan, and the insurance company will be responsible for the expenses exceeding RMB 3,000 yuan.

Seven, the loss of materials

1, all materials into the field by the Party materials, foreman *** with the signing acceptance, all non-template *** need to use the template, Party B has the responsibility to assist in the management.

2, standard layer loss: steel pipe ≤ 1%, fasteners ≤ 2%, wood template, wood square ≤ 3%, plywood whole sheet ≤ 1%, tensile screw ≤ 1%.

3, Party B use more than the loss of standard compensation to Party A according to the price of materials, if the discovery of sawing templates square wood, construction management personnel will be on-site fines.

4, after the completion of the project, more than 1 meter plywood nails, cement concrete potpourri cleanup.

Eight, civilized construction site and standardized site requirements

1, Party B site use of all materials must be stacked neatly, clearly marked. Semi-finished products of the production room must be stacked neatly, hanging signs conspicuously, marked with parts, production date, producer.

2, where Party B has violated the phenomenon of civilized construction, Party A will punish Party B by 50 yuan / time.

3, the construction site must be achieved after the site clear.

4, when Party A's project requires uniform clothing, Party B will bear 50% of the cost, and the rest will be borne by Party A.

5, each worker dormitory covers, bowls, shoes, towels must be neat, living garbage must be piled up according to the designated location.

6, for access card deposit of 10 yuan per person, leave the site to return the access card, Party A to return the deposit.

7, Party B shall improve other standardized civilized construction requirements by itself.

Nine, Party A and Party B responsibilities

1, Party A timely provision of materials that Party A should provide (steel pipe, wood, plywood, construction drawings, change orders, meeting minutes).

2, Party A provides accommodation and food for Party B. In principle, Party B provides its own living expenses, but Party A's foreman can lend living expenses at his discretion depending on the completion of the project, and the expenses will be deducted from the settlement of Party B's labor cost.

3, Party A's management personnel should do their best to organize cross construction, to prevent or minimize Party B's work.

4. Party A shall provide tower crane and night lighting facilities.

5. Party A and Party B must sign a safety construction contract at the same time they sign a labor contract.

6, Party A's project department to organize meetings, Party B must attend the person in charge, otherwise Party A to absent each 100 yuan, late each time 50 yuan to punish Party B.

7, Party B timely provision of machinery and other materials, tools, to ensure the smooth construction of the project.

8, the person in charge of Party B (or designated person) must be 24 hours on site (special circumstances must be to the host foreman and the foreman in charge of leave), or Party A to punish Party B with 100 yuan each time.

9, Party A for the project for the smooth construction of the entire project needs, Party B must comply with Party A's project arrangements, adjustments, or by delaying the schedule penalties.

10, Party B, if you need to apply for a temporary residence permit, work permit, ID card, family planning certificate, Party A to assist in the process, the cost is borne by Party B.

11, the person in charge of party B must accompany party A's project manager, host foreman, foreman to participate in the quality inspection station quality inspection and record, if absent party A by 200 yuan each time to penalize party B.

12, such as Party B does not listen to Party A's arrangements, Party A has the right to order the team to withdraw at any time, and not to settle all the works.

13. If Party B withdraws from the site or has unfinished work, the unfinished work will be deducted from the completed work by three times of the contracted unit price until it is finished.

14, Party B is strictly prohibited to recruit child labor under the age of 16.

Ten, if there is any outstanding issues, the two sides to form a separate supplementary contract negotiated settlement.

Xi, Party B does not obey the site management or fail to meet the contract requirements, Party A has the right to terminate the contract, and will not return the warranty.

Twelve, the number of copies of the contract: four copies of this contract, Party A three, Party B one.

Thirteen, the duration of the contract: the contract signed by both parties to enter into force, after the completion of the financial settlement, the automatic expiration.

A unit: (Chapter) B unit: (Chapter)

A signature: B signature:

A entrusted representative: B entrusted representative:

Contact number: Contact phone number: Contact phone number:

Signing date: Date of signing: