Real estate approval procedure

The program flow of real estate development project is development contract; Development and operation license; Individual project review; Pre-sale permit; Qualification certificate for comprehensive acceptance of real estate development project completion (comprehensive acceptance by stages); Transfer registration.

I. Development contract.

Work basis: Service Specification for Engineering Construction Management, Regulations on Urban Real Estate Development and Management, and Regulations on Urban Real Estate Development and Management in Shandong Province.

Time: After obtaining the land use right certificate and planning confirmation.

Submit:

1, feasibility study report

2, qualification documents

3, real estate development project approval

4 land procedures (land certificate or land auction scheme and transaction confirmation)

5. Planning plan, location map, elevation map and pipeline map recognized by the planning department.

6. Pre-property management contract (agreement)

7. Proof of payment of relevant expenses

8, project development fund supervision agreement.

Release: development contract, project manual.

Second, the development and operation license

Work basis: Service Specification for Engineering Construction Management, Regulations on Urban Real Estate Development and Management, and Regulations on Urban Real Estate Development and Management in Shandong Province.

Time: After obtaining the development contract.

After the examination and approval of the Housing Management Branch, it shall be reported to the Municipal Bureau for handling.

Third, the single project review

Act in accordance with the Management Rules for Urban Real Estate Development and Operation and the Management Rules for Urban Real Estate Development and Operation in Shandong Province.

Time: after signing the development contract and planning permit, the project construction drawing review initiated by the planning commission, but before the construction project planning permit.

Submit:

1, when the Planning Commission approved the plan.

2. Construction drawings of individual projects (reviewed by the Drawing Review Center)

3, construction plan and investment plan

4. Development contract and development business license.

Issued: single project evaluation form.

Fourth, the pre-sale permit

Work basis: Measures for the Administration of Urban Real Estate Development and Operation, Measures for the Administration of Urban Commercial Housing Pre-sale, and Trial Measures for the Quality Assurance and Description of Commercial Housing in Shandong Province.

Time: the construction investment of a single project reaches one quarter, and the construction permit is obtained.

Submit:

1. Business license:

2 qualification certificate, development contract and development business license;

3. Land use right certificate or legal land use document;

4, the construction project planning permit;

5. Work permit;

6, single project review form;

7. Construction contract;

8, the project construction schedule;

9, the project construction investment of more than 25% proof materials;

10, pre-sale plan for commercial housing;

1 1, filing receipt;

12, floor plan and building list;

13, Agreement on Supervision of Commercial Housing Pre-sale Funds;

14, commodity house quality certificate and instruction manual.

Issue: Pre-sale permit.

Five, the real estate development project completion comprehensive acceptance (phased comprehensive acceptance) certificate.

Work basis:

The urban real estate management law,

Construction and delivery of new houses and supporting facilities in Shandong Province

Management measures. "

Time: after planning, greening and quality acceptance, but before the initial registration and use of the house.

Submit:

1. Application for comprehensive acceptance of development project;

2, development project completion drawings;

3, single project review form;

4, planning, greening, quality inspection and acceptance report;

5. Report on the implementation of property management.

Issue: certificate of comprehensive acceptance (comprehensive acceptance by stages).

Six, the initial registration of housing

Time: After comprehensive acceptance (comprehensive acceptance by stages).

Submit:

1, land use right certificate or legal land use document;

2, the construction project planning permit;

3. Construction project commencement certificate;

4, the construction project completion acceptance certificate;

5. Building plan;

6, the initial registration of housing application form;

7. Liaocheng housing questionnaire;

8. A copy of the business license;

9, comprehensive acceptance (phased comprehensive acceptance) file.

Issued: Property Ownership Certificate.

Seven. Transfer registration

Time: After the mortgage is completed, the house purchase contract needs to be filed.

Submit documents:

1. Copy of ID card,

2. Purchase contract,

3. Liaocheng housing questionnaire,

4. Purchase invoices,

5. Deed tax invoice,

6. Commercial housing handover settlement agreement,

7. Housing transfer registration application and approval,

8. Surveying and mapping invoices,

9 maintenance fund payment certificate.

Issued: Property Ownership Certificate.

Extended data:

Project examination and approval is a system and procedure for relevant government departments to examine and approve projects that need management and supervision.

basic content

The establishment of a development project is the first step of real estate project development, that is, to obtain the approval documents of the competent government departments (provincial and municipal development and reform commissions, referred to as NDRC) for the project.

Project approval of engineering construction projects

Steps:

The first step is to set up a real estate development company

The second step is the establishment and feasibility study of real estate development projects.

Legal procedures in the project establishment and feasibility study stage of real estate development projects.

1. Select the project and sign the letter of intent for cooperation.

2. Determine the development plan initially?

3. What are the main points of report planning?

4. Declare and approve the project proposal?

5. Prepare the feasibility study report of the project

6. Declare and approve the feasibility study report of the project.

Taxes and fees related to the establishment and feasibility study of real estate development projects.

1, feasibility study fee?

2, the construction project planning permit license fee

The third step is the planning and design of real estate development projects and municipal support.

The first step is to set up a real estate development company

Legal procedures in the establishment stage of real estate development companies

First, establish a domestic real estate comprehensive development company.

1. Company preparation

2. Apply for qualification grade approval

3. Apply for pre-approval of enterprise name.

4. Registered in industry and commerce.

5. Deal with tax registration

Second, establish foreign real estate development companies.

6. Apply for approval of the project proposal

7. Enterprise name registration

8. Joint venture or cooperation contracts and articles of association submitted for review

9. Apply for the approval certificate of foreign-invested enterprises.

10. Enterprise registration

Relevant taxes and fees in the establishment stage of real estate development company

1. Business registration fee for enterprise as a legal person

2. Registration fee for change of enterprise legal person

3. Annual inspection fee of enterprise legal person

4. Replacement, replacement and licensing fees

The second step is the establishment and feasibility study of real estate development projects.

Legal procedures in the project establishment and feasibility study stage of real estate development projects.

1. Select the project and sign the letter of intent for cooperation.

2. Initially determine the development plan

3. Report the main points of the plan

4. Declare and approve the project proposal

5. Prepare the feasibility study report of the project

6. Submit and approve the feasibility study report of the project

Taxes and fees related to the establishment and feasibility study of real estate development projects.

1. Feasibility study fee

2. Construction project planning permit license fee

The third step is the planning and design of real estate development projects and municipal support.

Legal procedures in the planning and design of real estate development projects and municipal supporting stages

I. Planning and design of real estate development projects

1. declare the site selection and location.

2. Statement of planning and design conditions

3. Commissioned the production planning and design scheme.

4. Conduct civil air defense audit.

5. Conduct fire control audit.

6. Examine and approve the planning and design scheme

7. Expert group review of residential design scheme

8. Implement the environmental protection "three wastes" treatment plan.

9. Entrust environmental impact assessment and submit it for approval

10. Construction engineering survey and bidding

1 1. Entrusted geological exploration

12. Entrust the preliminary design

13. Declaration and approval of preliminary design

Second, the municipal facilities of real estate development projects

14. Seek the review opinions of the competent authorities.

15. Implement the supporting scheme of municipal public facilities.

16. Approval of municipal supporting scheme

17. The municipal administrative department put forward the municipal supporting opinions.

18. municipal pipeline synthesis

Relevant taxes and fees in the planning and design of real estate development projects and municipal supporting stages

1. Engineering survey (survey) fee

2. Engineering design fee

3. Construction project planning permit license fee

4. Deposit for completion files

5. Temporary land use fee

6. Temporary construction cost

7. Management fee for construction project survey bidding

8 survey and design supervision and management fees

9. Design fee for ancient architecture garden project

The fourth step is to obtain the land use right of real estate development projects.

Legal procedures for obtaining land use right of real estate development projects

I. Transfer of State-owned Land Use Rights

1. Handle the construction land planning permit.

2. Handling the entrustment of construction land.

3 for the transfer of state-owned land use rights application.

4. On-site investigation by the competent department

5. Pre-examination of land valuation report

6. Entrusted land price evaluation

7. Go through the land price verification procedures.

8. Handle the examination and approval of land transfer.

9. Sign a contract for the assignment of the right to use state-owned land.

10. Obtain temporary state-owned land use certificate

1 1. Obtain the official state-owned land use certificate.

12. Return of transfer fee of state-owned land use right

Second, the allocation of state-owned land use rights.

13. Application for allocation of state-owned land use right

14. On-site investigation by the competent department

15. Examination and approval of land allocation application

16. Obtain approval for land allocation

Three. Expropriation of collective land

17. Application for collective land expropriation

18. file with the district (county) real estate bureau that intends to requisition land.

19. Sign the land acquisition agreement.

20. Sign the compensation and resettlement agreement.

2 1. Determine the labor placement plan

22 district (county) real estate bureau to review the agreement.

23 land expropriation by the municipal government below

24 pay vegetable fund, farmland occupation tax and other taxes and fees.

25. Processing land grant documents and maps.

26. Handling frozen accounts

27. Investigate the household registration and verify the labor force

28. Dealing with the transformation from agriculture to industry.

29 for the transfer of rural residents.

30. Do a good job in the resettlement of super-transfer personnel.

3 1. Price compensation for above-ground property

32. Land expropriation has ended.

Relevant taxes and fees for obtaining the land use right of real estate development projects

1. Land price (land transfer fee)

2. Capital occupation fee

3. Late payment fee

4. Land use fee

5. Land use fees of foreign-invested enterprises

6. Management fee for flood control project construction and maintenance

7. Land idle fee

8 land ownership survey and cadastral surveying and mapping costs

9. Urban land use tax

10. Land price appraisal fee

1 1. Land transfer deposit

12. Land acquisition management fee

13. Land compensation fee

14. compensation for young crops and trees

15. compensation for overground objects

16. Labor resettlement fee

17. Resettlement fee for supernumerary personnel

18. New vegetable field development and construction fund

19. Farmland occupation tax

The fifth step is the demolition and resettlement of real estate development projects.

Legal procedures in the stage of demolition and resettlement of real estate development projects

1. Entrust the demolition work

2. Apply for demolition.

3. Approve and obtain the demolition permit.

4. Sign a letter of responsibility for house demolition.

5 for the demolition notice and notice.

6. the account is frozen.

7. Suspend related matters

8. Determine the relocation and resettlement plan

9. Sign a written agreement on demolition compensation.

10. hold a mobilization meeting for demolition and resettlement.

1 1. Pay compensation for operation and demolition.

12. Management of dust pollution in demolition construction site

13. handover of demolition files

14. adjudication of house demolition disputes

15. Forced demolition

Relevant taxes and fees in the demolition and resettlement stage of real estate development projects

1. Compensation for house demolition

2. Mobile subsidies

3. Incentive fee for moving in advance

4. Temporary resettlement subsidy (turnover fee)

5. Cleaning fee

6. Comprehensive subsidies for suspension of production and business

7. Subsidies for residents who move from better urban areas to poorer areas or suburban counties.

8. One-time resettlement subsidy

9. Housing demolition management fee

10. House demolition service fee

Step 6: Start-up, construction and completion stages of real estate development projects.

Legal procedures in the starting, construction and completion stages of real estate development projects

First, the real estate development project preparation before construction

1. Get the real estate development project manual.

2. The project is transferred to the formal plan.

3. Pay the construction fee of the gas (natural gas) plant.

4. Pay the construction fee of waterworks

5. Pay the construction fee of sewage treatment plant

6. Pay the construction fee of heating plant

7. Pay the power supply subsidy fee and power supply construction fee.

8 paid land transfer project for the "four sources" access procedures.

9. The design unit issued the approval drawings.

10. Construction drawing

1 1. Prepare and submit the project file and pay the file deposit.

12. Handling fire control audit opinion form

13. examine and approve civil air defense projects and apply for civil air defense permits.

14. issuance of construction project planning permit

15. Get the approval form for commencement and handle the commencement registration.

Second, the real estate development project construction bidding

16. Processing bid registration and bid application

17. Bid preparation

18. Tender notice

19. Prepare bidding documents and approve them.

20. Prepare the pre-tender estimate of the project subject to tender

2 1. The pre-tender estimate submitted for approval shall be confirmed by the contract budget review office.

22. Send the pre-tender estimate to the Municipal Bidding Office for examination and approval, and formally apply for bidding.

23. Qualification examination and approval of tendering units

24. Prepare and submit the tender.

25. Hold a tender meeting and inspect the site.

26. Hold a bid opening meeting and conduct bid opening.

27. Bid evaluation and award

28. Send an acceptance letter

29. Sign a project contract

30. Project contract review

Third, the real estate development project construction procedures

3 1. Go through the registration formalities for quality supervision.

32. Construction project supervision

33. Handle the statistical registration of commencement.

34. Pay the restricted use fee for solid clay bricks.

35. Conduct pre-construction audit

36. Pay the investment direction adjustment tax

37. Obtain a license for investment in fixed assets

38. Apply for water, electricity and roads for construction.

39. Coordinate the street sanitation department

40. Coordinate the traffic management department

4 1. Pay the greening construction fee and sign the greening agreement.

42. Get the construction permit.

Fourth, the construction of real estate development projects.

43. Construction site "three links and one leveling"

44. The construction unit comes into play and temporary construction

45. Project foundation, structure construction and equipment installation

46. Engineering quality supervision in the process of construction

Verb (abbreviation of verb) Real estate development project completion acceptance

47. Go through the acceptance formalities for individual projects.

48. Handle the comprehensive acceptance of development projects and receive the verification certificate of project quality completion.

49. Appraisal of commercial housing performance

50. Registration of completion statistics

5 1. Surveying and mapping completed houses

52. Property registration