1. Familiarize with the design and construction drawings and survey the construction site.
2. Develop the construction program, drawing anti-static floor grounding system diagram, grounding terminal diagram and ground network layout.
3. According to the requirements of the construction process to prepare a variety of construction materials, equipment, tools, and neatly arranged.
4. Demonstration laying should be done before formal construction.
5. The construction site should meet the following requirements; lead wires, grounding body and other content.
Elevated 40cm high static floor grounding construction methods are as follows:
1. Delineation of the baseline should be based on the geometry of the room to determine a reasonable.
2. Conductive copper foil grid should be laid according to the ground network layout. Vertical and horizontal intersections of copper foil should be in the center of the panel. Copper foil strips should be laid straight, not curled, nor interrupted. The copper foil strips connected to the grounding terminal should be left long enough.
3. Configuration of conductive adhesive: carbon black and glue should be configured according to 1:100 weight ratio, and stirred evenly.
4. Should be on the ground, respectively, has been laid on the top of the conductive copper foil, coating should be uniform, comprehensive, natural drying after coating.
5. Paving veneer panels, to be coated with dehydrated ground drying to non-stick hands, should be produced immediately start paving. Paving should be two right-angled edges of the veneer panel aligned with the baseline, paving should be fast and quick, between the board and the board should leave a gap of 1-2mm, with a rubber mallet to evenly tap the board, the edge of the ground should be applied to non-standard veneer panels paving to make up for the non-standard veneer panels from the standard veneer panels with a cutter cut and become.