A construction project acceptance should be based on the national, provincial and municipal engineering quality requirements, quality standards, norms and design documents reviewed and qualified construction drawings. The project must be accepted before delivery.
Second, the acceptance of the completion of the construction project shall have the following conditions:
1, the construction project has been completed according to the design and contractual agreement of the contents;
2, there is a complete set of technical files and construction management information;
3, the main building materials used on the project, fittings and equipment have certificates of conformity and incoming test reports;
4, there are survey, design, construction, engineering supervision and other units signed by the quality of qualified documents;
5, there is a construction unit signed by the engineering warranty.
Third, the quality of the project acceptance to check the quality of the project perception and the use of functional quality, mainly check the following:
1, floor, wall and ceiling;
2, doors and windows and their installation;
3, railing and guardrail installation;
4, waterproofing;
5, water supply and drainage system installation;
6, installation of indoor electrical work;
7, whether there is any violation of strong regulations and safety hazards aspects of the project;
8, other content.
Four, the construction project completion acceptance procedures:
1, when the unit project reaches the completion of acceptance conditions, the construction unit should be the first to organize self-examination, self-checking, self-assessment, self-assessment work is completed, fill in the completion of the project inspection form, and all the completion of the project information to the project supervisory unit, apply for the completion of the project initial inspection. At the same time, the Infrastructure Management Office should arrange for all kinds of special tests and related acceptance in advance (fire, water quality, air, energy saving and heat preservation, lightning protection, integrated wiring, biogas digesters, human security, piped gas, etc.).
2, the project supervision unit in conjunction with the Infrastructure Management Division and the construction unit of the completion of the data and the object for a comprehensive initial inspection. Initial inspection of the project should be made by the project supervision unit to make a written record of the inspection, found that the quality of engineering perception and use of function does not meet the specifications or design drawings, should be rectified in the form of a rectification notice ordering the construction unit to rectify the main contents include: defects in parts, the existence of the problem, the rectification period, the signature of the responsible person, etc.. After acceptance of the rectification results, the superintendent engineer to sign the project completion report, and to the Jinhua City Engineering Quality Supervision Station to submit a project quality assessment report and application for acceptance of the completion of the project report.
3, the infrastructure management office should actively cooperate with the Jinhua City Engineering Quality Supervision Station to do a good job of acceptance, and invite the relevant departments of the school to participate in (Supervision Department, Logistics Management Office, Security Department, Logistics Group, the use of the department, etc.). After acceptance by the Jinhua City Engineering Quality Supervision Station, the Infrastructure Management Office will arrange for various types of special acceptance (planning, environmental protection, sanitation, archives, greening, etc.).
4, Jinhua City Construction Bureau for the final completion acceptance record.
Fifth, the date of acceptance of the completion of construction works shall be completed within 15 days of the date of acceptance of the completion of housing construction works for the record. For the record need to submit the following information:
1, the owner of the organization of the completion of acceptance report;
2, construction project construction permit;
3, unit project quality completion acceptance of the record sheet;
4, geological survey report;
5, construction drawings and design documents review opinion;
6, the construction contract for construction works;
7, the construction unit signed by the project quality warranty;
8, commercial housing quality assurance and instruction manual (real estate projects);
9, the owner of the project issued by the completion of water, electricity, roads and their ancillary facilities to prove;
10, the construction project completion of the planning of the special audit opinion;
11, fire acceptance Qualified opinion;
12, environmental protection department completion acceptance certificate;
13, file quality certification;
14, sanitation facilities qualified opinion;
15, green acceptance certificate;
16, lightning protection facilities qualified opinion;
17, acceptance of human defense works qualified opinion (for human defense works);
18, piped gas project completion acceptance record form;
19, provide proof of payment of property warranty (real estate projects).