PPT 1.0 How many days before the finalization of the general contracting bidding need to complete the evaluation and to shortlist each bidding unit to

The bid validity period is counted from the closing date of the bidder's submission of bidding documents, during which the evaluation of bids, finalization of bids and signing of contracts are to be completed. At the end of the bid validity period of 30 working days before the end of the day to complete the finalization of the bid, bid evaluation is more than this time before. If the bid evaluation is valid for 90 days, the finalization of the bid is to be completed within 60 days from the date of the bid.

Expanded information:

"The People's Republic of China*** and the State Tendering Law Provisions on Relevant Contents in the Law on Bidding and Tendering

Article 37 The evaluation of bids shall be the responsibility of the bid evaluation committee formed by the bidder in accordance with law.

The bid evaluation committee shall be composed of representatives of the bidder and experts in technology, economy and other aspects, and the number of members shall be five or more singular, of which experts in technology, economy and other aspects shall not be less than two-thirds of the total number of members.

The experts in the preceding paragraph shall be engaged in the relevant field of work for eight years and has a senior title or has the same level of professionalism, by the bidder from the relevant departments of the state council or the relevant departments of the people's governments of provinces, autonomous regions and municipalities directly under the central government to provide the expert roster or bidding agency's expert library of experts in the relevant specialties in the list of experts to determine; general bidding projects can be taken by random sampling, special bidding projects Can be determined directly by the bidder.

People who have an interest in the bidder shall not be allowed to enter the bid evaluation committee for the relevant project; those who have entered shall be replaced.

The list of members of the bid evaluation committee shall be kept confidential until the result of the winning bid is determined.

Article 38 The bidder shall take the necessary measures to ensure that the evaluation of bids in strict confidentiality.

No unit or individual shall unlawfully intervene in or influence the process and results of bid evaluation.

Article 39 The bid evaluation committee may require the bidders to make necessary clarifications or explanations on the unclear contents of the bidding documents, but the clarifications or explanations shall not go beyond the scope of the bidding documents or change the substantive contents of the bidding documents.

Article 40 The bid evaluation committee shall evaluate and compare the bidding documents in accordance with the bidding documents to determine the bid evaluation standards and methods; there is a bidding price, shall refer to the bidding price. After completing the evaluation, the bid evaluation committee shall submit a written report to the bidder, and recommend qualified candidates for the winning bid.

The bidder according to the bid evaluation committee puts forward a written evaluation report and recommended winning candidate to determine the winning bidder. The bidder may also authorize the bid evaluation committee to determine the successful bidder directly.