Construction why progress so slow

Since the beginning of this year, by the gradual tightening of land policy, the bank continues to tighten the root of the impact of macro-policies, the region's fixed-asset investment growth has slowed down, especially the slow progress of the key project construction. As of the end of May, the region's 103 key projects completed investment of 4.98 billion yuan, an increase of only 16.9% year-on-year, to complete the annual plan of 22.7%, behind the schedule of 19 percentage points. Among them, the new project completed investment of 1.031 billion yuan, only 41.8% of the progress of the plan, accounting for 17.4% of the annual plan; renewed projects completed investment of 3.947 billion yuan, accounting for 24.7% of the annual plan; short of the sequential progress of 17 percentage points. Key project investment and construction is mainly manifested as:

A, most of the key projects construction progress is slow

In the 103 key construction projects,*** there are 80 projects did not reach the sequential progress, more than seventy percent of the total number of projects, amounting to 77.7%. Among them, there are 27 projects have not started construction, accounting for 26.2% of the total number of projects, the year's planned investment of 3.453 billion yuan, accounting for 15.7% of the annual planned investment in key projects; 53 projects that have not reached the progress of the year's planned investment of 12.469 billion yuan, accounting for 56.9% of the annual plan of investment in key projects.

Second, the planned investment of more than 100 million yuan of large projects to complete the progress of relatively poor

In the project has not begun and did not meet the schedule, this year's planned investment of more than 100 million yuan of projects 39 projects, accounting for 100 million yuan of investment in 86.7% of the project. These projects completed investment of 4.302 billion yuan from January to May, completing 23.2% of the annual plan, lagging behind the sequential progress by 18.5 percentage points.

Among the 27 projects that have not yet begun, the number of projects with investment of more than 100 million yuan planned for this year has reached 8, accounting for 17.8% of the investment projects with more than 100 million yuan. These projects include: Jiangjin Business Center Construction Project (800 million yuan), Aiping Mountain Park Construction Project (520 million yuan), Chongqing General Aviation Emergency Rescue Base Project (500 million yuan), S106 Luhuan to Shunjiang section of the reconstruction and expansion of the project (200 million yuan), fertilizer factory to Shuangbao Road Reconstruction Project (170 million yuan), Yuduhe to Shukousi to Toudaohe Highway (120 million yuan), Jiangjin District Renewable Resources Trading Market Construction Project (120 million yuan), Zhicheng Machinery Motorcycle Parts Production Base Project (100 million yuan).

Three, government-led key investment projects to complete the progress is not ideal

42 government-led investment projects completed investment of 2.176 billion yuan, 31.4% of the annual plan, short of 10.3 percentage points of the sequential progress. Among them, 32 projects failed to meet the sequential progress, 16 projects did not start, accounting for 38.1% of the government-led projects. These uncommenced projects are scheduled to invest 1.553 billion yuan this year, accounting for 7.1 percent of the region's key projects.

From previous years, the key project investment accounted for about 70% of the region's investment completion, so the key projects to promote the fast and slow directly affect the region's investment process. From the current situation, such as to complete the annual target task, after seven months of the region to complete at least 3.11 billion yuan of investment per month, and accounted for most of the share of the key projects to complete at least 2.18 billion yuan per month, from the current situation, the completion of this goal is extremely difficult.

Caused by the current slowdown in investment growth in our region, the low rate of new projects, some of the main reasons for the continuation of the project stoppage, there are five main aspects:

A, land use indicators are particularly tight. According to the survey, in the key projects, at present **** there are 63 projects with varying degrees of land indicators, planning land 81,139 acres, the recent demand for land 28,712 acres. As of now only 9,717 acres of land requisition approvals have been issued, with a recent shortfall of 19,004 acres and a long-term shortfall of 71,422 acres. Involved projects include several rivers bridge, north-south avenue and other infrastructure construction projects; Guangdong large Yangtze River and other industrial development projects as well as reservoir area small towns living garbage disposal, sewage treatment and public **** rental housing and other people's livelihoods category of new central investment projects.

Two, demolition and relocation is very difficult. First, in the project land has been implemented in some of the new projects, due to the demolition and relocation work is blocked, can not be built according to plan, such as Yu Hui Agricultural Products Wholesale Market project, Jiayu Hotel Tourism Management College project, etc.; Secondly, some of the projects that have been initiated by demolition and relocation issues, the construction progress has slowed down, such as the welcome to the Yangtze River Bridge, the South Approach Bridge, the Star River Olympics and the Jiangzhou Interchange, the Pingqiao distribution station demolition and relocation is still unresolved, the Riverfront New City North and South Boulevard Project, three three factory demolition has not been able to be resolved; three is part of the slow progress of land transfer of agricultural projects, such as Huaguo Mountain Urban Ecological Agricultural Park project, there are still 40 farmers have not signed land subcontracts, home base replacement transfer contract.

Three, the promotion is not enough. Such as the Orient Light plastic fiber optic project, the plant has been basically completed, but the equipment is delayed in place, affecting the commissioning; Jiachuan automobile production project, the investor has not yet reached an agreement on the content of the construction, the project can not be started; Zhicheng motorcycle parts project, Rui En agricultural project, can not be promoted, the owner is ready to terminate the contract.

Four, construction funds have not yet been implemented. Such as the district archives relocation project, the funding program is still not implemented; Jiangjin District 2011 dilapidated housing reconstruction project, the funding program is still not determined; social welfare institutions, mental rehabilitation hospitals relocation project, including the central investment project elderly care center project district-level matching funds document is still not issued.

Fifth, the impact of other factors. Such as the district hospital relocation project, the design drawings rough, resulting in more engineering changes, affecting the construction progress; urban and rural new housing project, "two rules" adjustment is not completed; De sense of the old city renovation, "revision of the rules" compilation is not completed; Jincan modern agricultural and cultural theme parks and Project, has been transferred to the land of the farmers in the process of land reclamation construction of additional requirements, hindering the progress of the project; Riverside New City North and South Avenue, due to land acquisition indicators are not implemented, the masses have strong views, long-term petition.