I. Emergency plan
Once the operating pressure exceeds 0.56Mpa, the inspector or the operator will immediately shut down the container inlet valve, cut off the gas input port, and at the same time Stop the host operation, open the container sewage valve, gas to air emissions, so that the gas pressure inside the container to reduce to the normal pressure range.
Second, several measures to control pressure
1, the staff often carry out equipment inspection, observe a variety of instruments to express the indication of the state, observe the air compressor military training parameters, strengthen the compressor routine maintenance, especially pressure regulators and other pressure control and indication components of the inspection and adjustment to ensure that the equipment works in a good state.
2, the gas storage tank safety valve weekly manual opening experiment, according to daily experience to determine whether the safety valve open sensitive, if necessary, safety valve replacement.
3, to ensure that the gas storage tank drain valve smooth, necessary for dredging or replacement.
4, with the special equipment monitoring department to do a good job of regular inspection of the container flaws, to ensure that the hardware is good ` use of state.
Third, the emergency plan rescue measures
Due to other reasons caused by the gas tank pressure is too high resulting in the vessel burst, rescue measures should be obtained as follows:
1, the establishment of the gas tank emergency plan leading group
Leader: Lei Qilin
Deputy Leader: Wang Jung-ming
Members: Hu Peng Long from the payment Zhao Desong Zhao Deyong Zhao Xing Guo Taifu
2, the mine has a safety production dispatch office telephone contact information, in the event of casualties, you should immediately contact the duty leader or Maneiling Township Hospital rescue.
3, the container near the operator quickly evacuated to a safe place, observe the actual situation on the scene, according to the specific situation to report and take a safe way to control the accident reoccurred.
4, once the accident scene casualties, the rest of the staff to ensure their own safety in the organization of practical rescue methods to rescue, to ensure that the rescue method is correct.
5, the mine has a duty vehicle in the mine, duty personnel on 24-hour standby, once there is an emergency, immediately out of the car to implement rescue.
Nayong County, Maneiling Township, Dahe Junction Qingrong Coal Mine
February 10, 2009
Special equipment accident emergency plans and measures [Part 2]
I. Purpose: In order to make the special equipment accidents and casualty accidents or attempted accidents, quickly eliminate the source of the accident in a timely manner to rescue the injured and repair the damaged equipment, as far as possible to reduce the negative impacts of accidents, to reduce losses. Negative impact, reduce the loss of the accident.
Second, the scope: boilers, pressure vessels and other special equipment explosion and other accidents and accidents in the process of casualties and special major accidents, major accidents, major accidents and general accidents.
Third, the accident emergency rescue organization and division of responsibilities:
The company set up a general manager as the commander-in-chief of the accident emergency rescue organization, under the sub-scene command, rescue group, evacuation group, rescue group, liaison group, fire alarm group, power repair group, the division of responsibilities as follows:
1, the commander-in-chief: the overall command and coordination of the accident processing work.
2, on-site command: command of the accident scene scheduling, coordination work.
3, the risk group: the organization excluded the source of the accident distress.
4, evacuation group: isolation protection, evacuation, transfer of goods, reduce losses.
5, rescue group: immediately organize personnel and scheduling vehicles, as soon as possible to send injured people to the hospital for treatment.
6, liaison group: do a good job of communication between the departments.
7, fire team: in the shortest possible time to the scene of the accident rescue fire.
8, power repair group: responsible for electrical equipment, power outages, repair work.
Fourth, accidents and accidents of the emergency rescue measures:
1, the company accident and incident, the duty officer should immediately do everything possible to cut off or isolate the source of the accident, at the same time by the workshop leader to decide whether to stop the emergency equipment operation, and the fastest possible speed to the company leadership report, and the relevant departments to get in touch. Serious accidents can be directly reported to the relevant functional departments or emergency rescue leading group. Call the fire alarm "119", medical emergency telephone "120". The report should include: the accident unit department, the time and place of the accident, the nature of the accident (explosion, fire), as well as casualties and the name and contact number of the reporter.
2, the company's leadership to the scene should be quickly organized to identify the source of the accident, parts and causes, to carry out rescue and self-help work. According to the accident damage and casualties, the company leadership should immediately decide whether to start the company's emergency rescue plan, such as the decision to start the company's emergency rescue plan, the immediate establishment of the emergency rescue headquarters, the accident emergency rescue organization personnel should be alerted to the scene as quickly as possible to participate in the accident emergency rescue rescue work. When dealing with accidents, quickly take measures to rescue injured people and property, to prevent the expansion of the accident, and at the same time should protect the scene of the accident.
V. Emergency rescue drill system for accidents and incidents:
1, at least one emergency drill should be carried out every year, and members must participate.
2, the content of the exercise, time, risk management methods, first aid plan approved by the company leaders to implement.
3, the end of the exercise should be a written record of the exercise, and summarize the problems one by one to adjust and modify.