Rectification of medical equipment bidding in 2022

Answer: a, c, d, e

2022 textbook P 142

This topic studies the characteristics and classification of materials and equipment procurement contracts. The priority order of contract documents for equipment procurement contract interpretation is as follows:

(1) contract agreement;

(2) Letter of acceptance;

(3) Letter of Bid;

(4) Business and technical deviation table;

(5) Special contract terms;

(6) General contract terms;

(7) Supply requirements;

(8) itemized quotation sheet:

(9) A detailed description of the technical performance indicators of the winning equipment;

(10) technical service and warranty service plan;

(1 1) Other contract documents.