The reason for the acceptance application should be sufficient, reasonable, factual, not boastful and fabricated, otherwise it is difficult to get the approval of the higher leadership. The following is the application for acceptance of the request I brought to you Sample, I hope it can help you!
Application for acceptance request sample 1
___ Investment and Development Limited Liability Company:
Subject: Report on the application for quality inspection of the sixth contract section of the ___ Bridge North Shore Connection Project
Report content:
The sixth contract of the Hangzhou Bay Bridge North Connection starts from Buyun Junction of Shanghai-Hangzhou Expressway, Pile No. K24+000, and finally ends at the north bridge head of ___ Bridge, Pile No. K48+785, with a total length of 24.785 kilometers. The total contract price of pavement is 272,237,000 Yuan, which was awarded by ASEAN Company on January 24, 20__, and the contract period is from February 15, 20__ to November 15, 20__. After careful organization and reasonable planning and arrangement of our department, we have now completed all the construction contents as agreed in the contract.
I unit according to the Ministry of Transportation of highway engineering inspection and evaluation standards JTG F80/1-20__, the Ministry of Transportation on March 31, 20__ promulgated and implemented the "highway project completion (handover) acceptance methods" and related provisions of the requirements of the quality of the project for self-check. Each sub-item, sub-projects are qualified, and each sub-item, sub-projects are greater than 90 points, the rate of excellence is 100%, the self-assessment grade is excellent, to meet the design and quality requirements.
Now my unit has organized personnel to carry out the preparation of completion data, the information is complete, and strictly in accordance with the Ministry of Transportation and Communications of the content of the preparation is completed, in line with the provisions of the requirements. My project manager and supervision engineers have completed the contract section of the work summary.
So far, my unit has completed the Ministry of Transportation March 21, 20__ promulgated and implemented the "highway project completion (handover) acceptance methods" in the provisions of the handover quality testing before the completion of the work, with the handover quality testing conditions, now I apply for my unit of ___ Bridge North Bank Connection Project, the sixth contract section of the quality testing.
Hereby report.
___
20__ year ___ month ___
Application for acceptance request sample 2
First, the project overview and completion of the situation:
____ field of returnees workers capital building project, located in Nanning City, Jiangnan District, Youyi Road, Wu Wei section of the 26th compound, the cost of the project 318, 80,000 yuan, a total construction area of 3009, 552 square meters, the structural form of concrete frame structure / ground 6 floors, the total height of the building is 17, 15 meters, indoor and outdoor height difference of 300mm application for acceptance Report model application. Building structure category for three, seismic intensity of six degrees, the reasonable service life of the building 50 years, waterproof grade for the third level, the building structural safety level for the second level.
Our company has completed the foundation and foundation division project, main structure division project, building decoration division project, building roof division project, building water supply and drainage and heating division project, building electrical division project, building energy saving project construction tasks in accordance with the requirements of the design drawings and related design documents.
Second, acceptance conditions check results:
According to & lt; building construction quality acceptance standard & gt; the relevant provisions of the project has been completed according to the design requirements of the project construction tasks, engineering structural safety and use of functionality are in line with the requirements, have the project completion acceptance of the initial inspection conditions. The remaining individual details of the finishing work after the initial inspection by the construction and supervision unit to put forward rectification requirements, our company according to the requirements of the rectification is completed in the form of a written report to the construction and supervision unit.
____ Construction Engineering Company Limited
____ Phase II Project Department
Project Manager:___
____ Year __ Month __ Day
Application for Acceptance Requisition Sample 3
__ Municipal Public Security Fire Department:
The fire protection facilities of the __ School Project developed by our organization are in good condition. ___ school project, fire protection facilities and equipment have been in accordance with the design and construction program construction is complete, the fire detection company of the project in the fire alarm system level linkage system, a comprehensive test, and has obtained the appropriate report, all the information is complete, is now applying for your fire department of the fire inspection and acceptance of my project.
Hereby report!
Application for acceptance request sample 4
First, the completion of the project:
___ County ___ Homes 1, 2 # building project by the ___ County Housing Construction Company eleven project department in November 15, 20__ started construction, 20__ the end of March fully completed, which lasted 16 months, in accordance with the design of the approved program has been Completed the main works, namely: civil decoration and renovation works; water supply and drainage works; electrical equipment installation works.
Second, the acceptance conditions check results:
According to the relevant provisions of the state, the project has been designed to complete the main engineering construction tasks. Reasonable use of investment in the project, the completion of the information has been prepared, the quality of engineering construction has passed the quality inspection of the quality supervision station, and issued a "project quality inspection and evaluation report", the quality of the project is qualified, has the formal acceptance conditions.
Third, the proposed acceptance time, location and participating units:
According to the completion of the project and the relevant requirements of the provincial and municipal authorities, ___ County ___ Homeland 1, 2 # building project completion acceptance is proposed to be drawn up on the day of the month of the year, acceptance of the location in the, participate in the unit has the project sponsor, design, supervision, construction, quality supervision and other relevant units.
In summary, ___ County ___ Homeland 1, 2 # building project has the completion of acceptance conditions, I implore the higher authorities to arrange for formal acceptance.
__ County Housing Corporation Project Department
First, the construction unit to apply for the construction project completion acceptance of fire protection record should provide the following information
1, "Construction Project Completion Acceptance Fire Protection Record Form";
2, "Construction Project Fire Protection Design Record Acceptance Vouchers," a copy of the construction project fire protection design, or "Construction Project Fire Protection Design Audit Opinions," a copy of the
(1) fire protection design for the record was identified as the object of random inspection, the need to record the system to check whether the fire protection design for the record has been sampling qualified, if the sampling failed to also need to provide the "construction fire protection design fire review opinion";
(2) fire protection design for the record is not identified as the object of sampling, you need to provide the planning permission to prove the document. Is September 1, 1998 has been put into use before or have received a property certificate of the construction project declaration of fire design for the record, you can provide proof of ownership of buildings and other legal evidence;
3, project completion acceptance report.
Second, was sampled to the construction unit should be received within five days from the date of the record voucher to the public security organs of the fire agency to provide the following materials
1, "construction project completion acceptance of fire protection for the record";
2, "construction project completion acceptance of fire protection for the record acceptance of the voucher," a copy of the copy of the voucher;
3, "construction project fire protection design acceptance of the record voucher". Copy or "construction project fire design review letter" copy;
4, the construction unit's business license and other legal identification documents;
5, construction, project supervision, testing units legal identification and qualification level documents;
6, project completion inspection report;
7, fire product quality certification ( Compulsory product certification of fire protection products and licensing inspection report, or type approval certificate and licensing inspection report, or the validity of the type inspection report; has not yet formulated national standards or industry standards for fire protection products should be provided with the identification of opinion and type inspection report; the above information shall be stamped with the official seal of the manufacturer, and provide the certificate of conformity of the product);
8, the fire performance requirements of the building components Construction materials, interior decoration and decorative materials, product type inspection reports, public **** place of use of flame retardant products and components to provide "flame retardant products labeling certificate of use" and inspection reports;
9, with the legal effect of fire protection facilities, electrical fire safety technology testing of qualified documents ("fire protection facilities, qualified documents") " can be issued by the corresponding fire facilities testing qualification of the organization: "electrical fire technology testing documents" is not required as a record of information);
10, proof of supply of fire protection products (filled out by the manufacturer and stamped with the official seal);
11, _ Spraying Steel structure fireproof coating construction program, records and its construction unit business license copy;
12, hidden project records;
13, construction project completion drawings (civil and fire facilities construction unit should be in the corresponding completion of the completion of the map on the completion of the seal).
Third, other requirements
For the masses with the "project completion acceptance report" and "construction project completion acceptance fire acceptance voucher for the record" to the business window to request the public security organs to stamp the seal of the fire agency, if presented for the record acceptance vouchers and in the fire hall for the record system in the query results are consistent, and can be submitted to the above record of information can be filed for the record acceptance vouchers on the stamp. Window business acceptance seal.
Application for acceptance of the request model 5
____ (unit name)
On ___ project completion acceptance application report
First, the project completion
___ County (township) ___ project by the __ (construction unit) in ___ years ___ month ___ started construction, ___ the end of the month of the full. It was fully completed at the end of __ year, which lasted for __ months, and the main works have been completed in accordance with the approved design (program), i.e.: ........... (e.g. civil decoration works, water supply and drainage works, electrical equipment installation works, etc.).
Second, the acceptance conditions check results
According to the relevant provisions of the state, the project has completed the main engineering construction tasks according to the design requirements. Reasonable use of project investment, completion information has been prepared, the quality of engineering construction has passed the quality inspection of the quality supervision station, and issued a "project quality inspection and evaluation report", the project quality is qualified, has the formal acceptance conditions.
Third, the project completion acceptance application
According to the completion of the project and the relevant requirements of the higher authorities, is now applying for the county construction project (project) completion acceptance of the work of the leading group of the ___ County (township) ___ project as soon as possible to organize the completion acceptance work.
Hereby report
Name of applicant (seal)
Year month
Application for acceptance of the request example 6
Project completion acceptance of the application report is based on the project funding report for the type of funding application, the nature of the project to comprehensively assess the situation of the availability of funds, the use of funds and management, the completion of the project construction content. Management, the completion of the project construction content, construction project quality and technical equipment operation, production readiness and a series of project completion and issued after the construction of the project description.
1, completion and acceptance of the basis
(1) project approval (for the record) documents, project funding application report, project investment plan.
(2) Environmental impact assessment report and approval, energy saving assessment report and its review, as well as land, planning, safety and production and other matters of approval.
(3) National and provincial standards and specifications for engineering construction, environmental protection, energy conservation, safe production, and other aspects of the product technical standards.
(4) Project supervision, bidding and important equipment, raw materials procurement contracts.
2. Acceptance conditions
(1) The project is completed in accordance with the requirements of the capital application report, the project investment plan construction, production and economic and technical indicators to meet and be able to meet the requirements of production and use. Production preparations to meet the needs of production.
(2) The main process equipment and ancillary facilities by the linkage load test run qualified to produce qualified products in line with the provisions of the capital application report, the formation of production capacity, and can achieve the expected economic and social benefits.
(3) The quality of the project reaches the relevant national standards, and the products meet the technical standards.
(4) Environmental protection, energy conservation, production safety, fire and other facilities have been built and used in accordance with the design requirements and the main project at the same time, to meet the national requirements.
(5) The project completion of the financial accounts report preparation is completed, and audited by the corresponding qualification accounting firm.
(6) project technical documents, information filed in accordance with the requirements to meet the needs of production, use and maintenance.
The project basically meets the conditions listed in the preceding paragraph, there are still sporadic civil works have not been implemented or a small number of non-major equipment is not in place, but does not affect the normal production and use of the main project, and the uncompleted investment accounted for the proportion of the total estimated investment is less than 10%, by the competent department of industry and information technology, the financial sector, can also apply for the completion of the acceptance.
3, the completion of the acceptance content
(1) investment completion. Including project funds in place, the use of special funds for technological innovation and management, completion of the financial accounts audit and bidding.
(2) the completion of the project construction content. Including the project land acquisition, civil engineering, equipment acquisition, installation, construction of public utilities and other auxiliary facilities.
(3) construction project quality and operation of technology and equipment. Including environmental protection, production safety, energy-saving facilities, fire safety facilities, etc. to achieve results.
(4) After the project was completed and put into operation, the level of technology and equipment, product technology level, quality level, production capacity, economic and social benefits, energy saving and environmental protection, production safety and so on.
(5) production readiness. Including production working capital, raw material supply, energy supply, personnel training and so on.
(6) project technical documents, information archiving. Including approval, design, supervision, bidding and other aspects of the documents, as well as construction and installation works, process equipment, utility support facilities and other technical documents, drawings filed.
(7) need to eliminate backward production capacity of the project to eliminate backward production capacity.
Application for Acceptance Request Sample 7
Lin'an City Environmental Protection Bureau:
Hereby Hangzhou Lin'an ___ Co., Ltd., 20__ by the environmental protection approval on ___, 20__ put into trial production so far on ___, Approval No.: Lin Environmental Protection [200_] ___ No. or Registration Form Approval [200_] __ No. ; Project Name: annual production of ____ how many tons or (pieces); Address: ----------; Contact Person: -----------; Contact Tel: ------------. According to the EIA approval I have commissioned ____ environmental protection company to carry out planning and design, and in accordance with the design requirements to carry out the following environmental protection management work:
1, wastewater: the implementation of rainwater and sewage diversion system in the plant, rainwater Connected to the outside of the plant rainwater ditch (pipeline) discharge; domestic wastewater, "such as no production of wastewater enterprises, (canteen wastewater by the grid oil pool treatment into the buried wastewater treatment device) other domestic Wastewater by three compartments buried wastewater treatment device after treatment to meet the discharge standards" and production wastewater by ____ method after treatment to meet the discharge standards. The wastewater of enterprises in the park is incorporated into the sewage network of the park together with domestic wastewater after pre-treatment and reaching the standard of pipeline (with a copy of the wastewater pipeline agreement).
2, exhaust gas: in the ___ process of the ___ exhaust gas by the fan collection, through the ___ adsorption purification device treatment, through the ___ meters high chimney emissions; boiler exhaust gas by the water film dust collector treatment, through the ___ meters high chimney emissions, dust removal of wastewater through the three-format precipitation tank with precipitation and recycling of waste water is not externally discharged.
3, noise: machinery and equipment have been installed shockproof sound insulation pads, all doors and windows in the workshop use soundproof glass sound insulation, production and processing of sealed closed doors and windows to ensure that the noise can meet the emission standards.
4, solid waste: (1), industrial waste: collected by the classification of comprehensive utilization; (2), living garbage: collected by the unified collection of regular collection and disposal by the sanitation department.
4, dust: the use of ____ dust removal facilities to meet the standard discharge after collection and treatment.
5, cafeteria fumes: has installed a fume purifier, the fume exhaust generated by the purifier after treatment and discharge at high altitude (or the project does not have a cafeteria).
Now all have been put in place, and I would like to apply to your office to organize the completion acceptance monitoring of the environmental protection facilities supporting the construction project of my company. (With EIA materials and approval documents, park enterprises need to provide sewage natatorium agreement)
Hereby report!
Hangzhou Lin'an ___ Co., Ltd. (seal)
February 0 ___, ___ month ___
Application for acceptance of the request for sample 8
Note: This form must be submitted in duplicate (original); state classified projects need to be marked in the declarations of classified materials.
Shanghai ___ Bureau system 20__-3
Declaration: I hereby confirm that the contents of this application form and the attached documents and materials are true. I / my unit promises to be responsible for the authenticity of the submitted materials, and bear the consequences of the content is not true.
(construction unit seal)
Construction project engineering completion of environmental protection "three simultaneous" acceptance registration form
Project manager (signature):
Fill in the form of unit (seal): fill in the form (signature):
Note: 1, the emission of incremental and decremental: (+) indicates an increase, (-) indicates an increase, (-) indicates a decrease
2, (12) = (6) - (8) - (11), (9) = (4) - (5) - (8) - (11) + (1)
3, unit of measurement: wastewater emissions - 10,000 tons / year; emissions of waste gas -- million standard cubic meters / year; industrial solid waste emissions -- million tons / year; water pollutant emissions concentration -- mg / l; air pollutant emissions concentration -- mg/m3; water pollutant emissions -- tons/year; air pollutant emissions -- tons/year
Application for Acceptance Request Sample Essay 9
___Construction unit
The construction of the first bidding section of the roadbed project of the road of Wu Shan Dong Road undertaken by our company, and now the construction of ancillary structures has been completed. After the supervision unit to verify the quality of the division of the project are qualified, quality control information and testing information about the function of the integrity. In this regard, I would like to ask you to organize the acceptance of the subordinate structures sub-division project before 26 November 20__. The sub-division of all the technical files of the project has been organized in accordance with the requirements of the relevant provisions, with the report sent for inspection.
Signature of Project Manager:
Applicant:
20__ Year __ Month __ Day
Application for Acceptance Request Sample 10
Xinjiang Electric Power Engineering Quality Supervision Center Station hereby has my unit responsible for the construction project Shichengzi Grade 1 Hydroelectric Power Plant Project, Shichengzi Grade 2 Hydroelectric Power Plant Project. Has been in accordance with the relevant national norms and regulations, in accordance with the design requirements to complete the construction of the project. Now to your unit to submit an application for acceptance.
First, the completion of the project
Shichengzi power station project by the Sichuan University Engineering Design and Research Institute is responsible for the design work, by the Yunnan Lubuge Consultants Ltd. is responsible for the supervision work, by the Xi'an Municipal Water Conservancy Engineering and Construction Group is responsible for the construction of the Limited Liability Company. The construction of the project started in June, 20__, and was fully completed at the end of January, 20__, which took 19 months. Now all the works have been completed according to the approved design scheme, namely: water diversion system works, plant hub works. Shichengzi secondary power station project by Sichuan University Engineering Design and Research Institute is responsible for the design work, by the Sichuan Chengdu Kejian water conservancy and civil engineering supervision limited liability company is responsible for the supervision work, by the Xi'an City Water Conservancy Engineering and Construction Group Limited Liability Company is responsible for the construction. The construction of the project started in September, 20__, and was fully completed at the end of November, 20__, which lasted 14 months. Now in accordance with the approved design program has been completed all the works, namely: water diversion system engineering, plant hub engineering.
Second, the acceptance conditions check results
According to the relevant provisions of the state, the project has been completed according to the design requirements of all engineering and construction tasks. Reasonable use of project investment, completion information has been prepared, the quality of engineering construction has passed the Hami City District Water Resources Quality Supervision Station acceptance, the project quality is qualified, has the formal acceptance conditions.
Your unit Jia station chief and his entourage to the site in 20___ ___ month for preliminary acceptance, and the project construction project in the turbine generator set installation, electrical installation, civil engineering part as well as acceptance of the data to make valuable comments and suggestions. These suggestions on the Shichengzi one and two power station project quality of the project is very beneficial, we have been organized one by one, and urge the relevant personnel to rectify one by one, first has completed the rectification work.
Third, the project completion acceptance application
According to the completion of the project and the relevant requirements of the higher authorities, I now apply for your Shichengzi power station project, Shichengzi power station project organization acceptance; application for us to be able to start the unit on March 25, 20__, into the test run stage.
Hereby apply
Hami Ruiheng Hydropower Limited Liability Company
20__-__-__
Application for Acceptance Request Sample Essay 10 Related Articles :
★ Project Request Request Letter Report 5
★ Completion Acceptance Request Report Sample Essay 2019 Selected
★ Project application acceptance report sample
★ Engineering application acceptance report sample
★ Engineering acceptance application report sample
★ Environmental protection acceptance application template
★ Fire protection acceptance application sample
★ Simple completion acceptance application sample
★ Environmental protection acceptance application report sample selected
★ Project application report sample template