Application Report of Telecommunication Line Moving

Application Report of Telecommunication Moving Line

Part 1: Application of Moving Line

Wushan County Telecommunication Bureau:

My house is located in the fourth community of **** Village, **** Town, **** County, and I am now planning to build a house, but a cable pole of your bureau (Pole No.: Yun-Gui 058) is located in the area where my house is planned to be built. ) is located in my family planning to build a house in the area, I in January 29, 2014 telephone report to your bureau, your bureau in January 31, 2014 sent engineers and technicians to carry out on-site investigation.

Hereby apply

Applicant:

February 16, 2014

Part II: Detailed electric power relocation application report

Dear Leader:

The Huangjiang Avenue roadbed project constructed by our organization should be requested by the owner and Changsha County Government to strictly follow the node progress, but at present, there is a part of electric power within the construction red line. However, at present, there are some power lines within the red line of construction, which have affected the construction progress of our organization:

1. The high voltage poles on the right side of the existing road in the section of K14+900-K15+400 have not been moved. Needs to be solved:

a) The trees in the nursery in this section have not been moved.

b) 3 poles need to be relocated on the east side of the terminal.

2. There is a nursery at K14+200, which cannot be constructed for the time being because the owner of the nursery does not agree.

3. 6 high voltage poles at K13+850 are not moved.

Needs to be solved:

a) The place is a level crossing, high-voltage lines need to wait for the completion of the level crossing roadbed filling to be relocated to the buried crossing.

b) On the right side, the drainage ditch should be filled in after the construction of the drainage ditch is completed.

4. A number of telecom poles at K13+550 have not been relocated.

5. Left high voltage pole at K11+280 has not been moved.

Needs to be resolved:

a) The left roadbed needs to be filled and shaped before the poles can be buried in the section.

6. K8+900-K9+660 section of Changzhu Expressway small mileage direction, the left width of the pole has not been moved, need to be moved to the left side of the roadbed. However, the left width of a nursery garden staff due to land coordination issues hindering construction.

7. At K7+500, the power poles could not be moved due to the incomplete coordination of land use.

8. K6+300-K7+500 section left pole not relocated.

a) K7+120-K7+300 section of the left width of the villagers' houses and the construction area is too close to the local villagers need to do a good job communicating with them.

b) K7+100 Ta Gua Ling level crossing there are a number of houses have not been demolished, affecting the migration of poles. And the section needs to be the first level crossing roadbed construction is completed before the high voltage line buried construction.

c) The left side of K7+400 is not demolished because of the houses of the machinery factory, which need to be demolished before the relocation of poles.

In order to respond to the owner's node schedule requirements, on time to complete the roadbed road construction of Huangjiang Avenue, I hope that the poles will be relocated as soon as possible.

Part III: letter on the migration of optical fiber

China Mobile ** Branch:

Due to the change of our business, now need to ** branch of the 10M video surveillance lines and 2M business lines migrated to ** branch.

(move out) branch address: ** City ** District ** Street

(move in) branch address: ** City ** District Lin ** Road ** Contact: so-and-so 13 *******

The above application, hope that your company to study and implement as soon as possible!

** Rural Commercial Bank Co.

December 2014 ? Day

;