Shenyang city mechanical and electrical equipment bidding management regulations

Chapter I General Provisions Article 1 In order to promote and improve the reform of fixed asset investment management system, give full play to the role of the market competition mechanism, reduce the cost of the project, improve the efficiency of investment, according to the relevant provisions of the State, combined with the specific circumstances of Shenyang City, the formulation of these provisions. Article II of the provisions referred to in the electromechanical equipment, refers to the fixed asset investment projects required for electromechanical equipment.

Electromechanical equipment bidding, bidding for domestic equipment and imported equipment international bidding. Article Shenyang mechanical and electrical equipment bidding company (hereinafter referred to as the bidding company) is the city's mechanical and electrical equipment bidding management organization. Bidding company to undertake the city's mechanical and electrical equipment bidding business, and the winning economic contract implementation supervision, inspection and necessary coordination.

Where the implementation of general contracting of fixed asset investment projects, the city bidding management office and bidding company joint bidding. Municipal bidding management office is responsible for the construction project bidding, bidding company is responsible for the project required mechanical and electrical equipment bidding. Article 4 The following principles shall be implemented in the bidding and tendering work:

(a) All bidders shall have equal opportunities.

(ii) Fair treatment of the commissioned bidding party and the bidding party, safeguard the legitimate rights and interests of both parties.

(iii) Bidding and tendering work to achieve the best economic efficiency. Chapter II Bidding content and mode Article 5 The bidding content includes:

(a) complete sets of equipment bidding, refers to all the equipment or part of the equipment required for the construction project.

(ii) single equipment bidding, refers to a single species and specifications of equipment bidding.

(C) cooperative manufacturing tender, refers to the tender for the manufacture of the introduction of equipment supporting the extension or parts.

(d) equipment installation and commissioning bidding, refers to the manufactured electromechanical equipment for installation and commissioning of the tender.

(v) the introduction of equipment digestion and absorption bidding, refers to the introduced electromechanical equipment has been mapped, imitation of the bidding. Article 6 The bidding methods include:

(a) public bidding, that is, by the bidding company through the national professional newspaper bidding announcements, public bidding for the community.

(ii) Invitation to tender, that is, by the bidding company according to the special requirements of the commissioned bidding project pre-determined qualification conditions, directed to send out invitations to tender, bidding on the pending object. Article 7 The bidding and tendering work shall be carried out under the supervision of a notary public and in accordance with the prescribed procedures, and strictly observe the relevant confidentiality provisions. Chapter III Scope of Tendering Article 8 Where the city by the State, the State Council departments or local levels approved the establishment of capital construction, technological transformation, technology introduction projects (including the implementation of general contracting projects) required for domestic mechanical and electrical equipment, shall be in accordance with the provisions of the implementation of the domestic mechanical and electrical equipment bidding (hereinafter referred to as the domestic bidding). However, the following conditions are met:

(a) the total investment in equipment in 1 million yuan (excluding 1 million yuan) or less.

(ii) The equipment is a short market product.

(C) the equipment is the exclusive domestic enterprise production of products.

(d) The bidding company determined that the equipment can be produced by the construction unit itself. Article IX approved by the relevant domestic authorities to import electromechanical equipment (including the World Bank and other foreign loan projects), are required to implement the provisions of the international mechanical and electrical equipment bidding (hereinafter referred to as international bidding). However, the following conditions are met, except:

(a) the total investment in equipment in 300,000 U.S. dollars (excluding 300,000 U.S. dollars) below.

(b) the equipment for the exclusive production of foreign enterprises.

(C) the state regulations do not implement bidding.

(D) by the bidding company determined or in conjunction with the relevant departments to determine that it is not appropriate to implement the bidding. Article X where the city introduced in the past (including the introduction of domestic) equipment and maintenance parts required (except for electromechanical equipment patented in our country), regardless of its ownership, as long as other enterprises in the city need to entrust the bidding company in the city for the introduction of equipment digestion and absorption bidding, prototype units and the competent departments shall not be unreasonably rejected on any pretext. Specific measures according to "Shenyang city to promote the introduction of technology digestion and absorption of the work of the trial provisions" (Shen Zheng Fa [1986] No. 86) for.

By the Municipal Mechanical and Electrical Equipment Import Review Office approved the import of the prototype, the importing unit can not digest and absorb, shall be entrusted to the bidding company in the city to select the unit of digestion and absorption, shall not be delayed under any pretext. Article XI of one of the following cases, the financial sector, the financial sector will not issue loans or grants:

(a) the equipment demand side of their own procurement should be the implementation of the bidding of electromechanical equipment.

(B) should be determined through bidding for surveying and mapping, imitation of imported electromechanical equipment to undertake the unit but does not implement. Chapter IV bidding procedures Article XII of the required equipment in line with the scope of bidding, equipment needs (or construction units) in the competent approval authority to report the project proposal and design task book at the same time, to copy a copy to the bidding company, with a list of equipment in five copies.

If the equipment demand side in the report of the project proposal and design task can not put forward the list of equipment, can wait until the completion of the feasibility study report, the technical transformation program to put forward. Article 13 In the competent approval authority to approve the feasibility study report, technical transformation program or expansion of the initial design, the bidding company should be on the list of equipment to put forward whether to organize the bidding, the planning department as a basis for the development of the relevant annual plan.

The confirmation of the project to be tendered, after the implementation of the funds required for the project, the bidding company to organize the bidding work. Article 14 After the bidding project is determined, the equipment demand side should be submitted to the bidding company bidding commission and bidding equipment technical requirements. The bidding company shall work together with the equipment demander **** with the preparation of bidding documents, agree on the bidding price, and formulate the methods of evaluating and finalizing the bid.

Equipment demand side in the submission of the preceding paragraph at the same time, through its account bank to the bidding company issued a bidding equipment 2% of the total amount of the bidding deposit of the letter of guarantee. After the completion of the bidding work, if the equipment demand side without default, the bidding company shall return the letter of guarantee to the equipment demand side.