(a) water purification equipment installation confirmation of the required documents
① flow charts, system description and design parameters recognized by the quality department or technical department;
② water purification equipment and piping installation and commissioning records;
③ Instrumentation appraisal records;
④ equipment Operation manual and standard operation and maintenance procedures.
(B) The main content of the installation confirmation of water purification equipment
The installation confirmation of water purification equipment is mainly based on the production requirements, check whether the installation of water treatment equipment and piping system is qualified, check the calibration of the instrumentation as well as the preparation of operation and maintenance procedures.
1. The installation of water purification equipment to confirm
The installation of water purification confirmation refers to the installation of machinery and equipment, compared with the design drawings and suppliers of technical information, check whether the installation is in line with the design and specifications. Purified water at the equipment are mainly mechanical filters, activated carbon filters, pumps, (distilled water machine), etc., check the items are electrical, connecting piping, steam, instrumentation, water supply, filters, etc., installation, connection.
2. Purified water equipment piping distribution system installation confirmation
(1) Piping and valve materials
Piping selection of stainless steel (304, 316L and other models). Stainless steel materials are characterized by: ① chemically inert after passivation; ② easy to disinfect; ③ wide range of operating temperatures.
(2) pipe connection and pressure test
As mentioned earlier, the purified water transfer pipeline should be welded using thermal fusion argon arc welding, the requirements of the inner wall smooth, should check the welding quality. Generally use automatic argon arc thermal welding machine, according to the equipment manual to determine the welding control parameters, such as the current size, frequency, etc., and then in accordance with this welding parameters of a few joints, such as meeting the requirements, and later on in the installation can be controlled within these welding parameters, which can ensure that the weld seam is smooth and smooth. After the end of welding and then test pressure with deionized water, the experimental pressure is 1.5 times the working pressure, no leakage is qualified.
(3) pipe cleaning, passivation, disinfection
Stainless steel pipe processing (cleaning, passivation, disinfection) can be roughly divided into purified water cycle pre-rinse → alkaline cycle cleaning → purified water rinse → passivation → purified water rinse → discharge → pure steam disinfection and so on several steps.
① purified water cycle pre-rinse: a storage tank and a pump, and the pipeline to be passivated into a circular path, in the storage tank filled with enough deionized water at room temperature, with the pump to the cycle, 15min after opening the drain valve, while the cycle is discharged, it is best to install a flow meter.
② lye cycle cleaning: prepare NaOH chemical reagent, add hot water (temperature not less than 70 ℃) configured as 1% (volume concentration) of the lye, with a pump for the cycle, the time is not less than 30min, and then discharged.
③ Rinse: add purified water, start the pump, open the drain valve discharge until the resistivity of the water at each exit point is the same as the resistivity of the water in the tank, the discharge time of at least 30min.
④ Passivation: a. With purified water and chemically pure nitric acid formulated as an 8% acid solution, circulate at a temperature of 49 ~ 52 ℃ for 60min and then discharged. b. Or with 3% hydrofluoric acid (volumetric fraction), 20% nitric acid (v/v), 77% purified water to prepare a solution, the solution temperature at 25 ~ 35 ℃, circulating for 10 ~ 20min. and then discharged.
⑤ Initial rinse: rinse with purified water at room temperature for not less than 5min.
⑥ Final rinse: rinse again until the resistivity of the inlet and outlet purified water is the same.
⑦ Pure steam disinfection: clean steam into the entire stainless steel piping system, each point of use at least 15min rinse.
The above cleaning, passivation, disinfection process and its parameters should be recorded.
(4) integrity test
Water storage tanks installed on a variety of ventilation filters must do integrity testing.
(C) the calibration of instruments
All instruments on the water purification equipment must be regularly calibrated or recognized, so that the error is controlled within the allowable range. Water purification equipment commonly used instruments are: resistance (conductivity) meter, time controller, flow meter, temperature controller / recorder, pressure gauge and analyze the water quality with a variety of instruments. Need to emphasize is the ultraviolet lamp (UV) and other should give extra attention to the ultraviolet lamp calibration parameters are: wavelength, light intensity and display the use of time clock.
(D) operating manual
List of all equipment operating manuals and daily operation and maintenance of water purification equipment.