The sewage treatment station has been repaired, how to carry out environmental protection acceptance? Is it independent acceptance or environmental protection department acceptance?

The Regulations on Environmental Protection Management of Construction Projects (hereinafter referred to as the "Regulations") was revised on June 2 1 day and came into force on June 1 day. Article 17 of the new "Regulations" clearly stipulates that after the completion of a construction project that prepares an environmental impact report (table), the construction unit shall, in accordance with the standards and procedures stipulated by the competent administrative department of environmental protection of the State Council, conduct acceptance of supporting environmental protection facilities and prepare an acceptance report. The "Regulations" only canceled the administrative licensing items for environmental protection acceptance of construction projects, and changed them to independent acceptance by the construction unit, further strengthening the "three simultaneities" main responsibility of the construction unit for environmental protection.

Therefore, the environmental protection department will no longer accept it, and the enterprise will accept it independently in the future.

In recent years, the Ministry of Environmental Protection has issued acceptance technical specifications for pharmaceutical, polyester, viscose fiber, automobile manufacturing, cement manufacturing, medical institutions, water conservancy and hydropower, highways, ports and other industries. The independent acceptance of environmental protection after 10 is based on the acceptance specifications of these industries. The main reference documents are:

1, two high judicial interpretations

2. Regulations on Environmental Protection Management of Construction Projects

3. Technical Specification for Environmental Protection Acceptance of Construction Project Completion

4. Notice on Printing and Distributing the Key Points of On-site Inspection and Audit for Environmental Protection Acceptance of Construction Project Completion (Huanban [2065 438+05] 165 438+03)

5. Notice on Standardizing the Construction Unit's Independent Acceptance of Environmental Protection for Construction Project Completion (Draft for Comment)

6. Technical Guidelines for Environmental Protection Acceptance of Pollution Impact Category of Construction Project Completion (Draft for Comment)