1, agreement (including supplementary agreement)
2, notification of award
3, tender and its annexes
4, special contract terms
5, general contract terms
6, relevant standards, specifications and Technical Documents
7, Drawings
8, Bill of Quantities
9, Quotations and Budgets for the work, etc.
Article 2: The Contractor shall have the right to propose an additional contract price for the improvement measures. Progress improvements are reasonable requests and shall not be subject to an additional contract price.
Article 3: The construction organization design is submitted by the construction unit to the engineer for review 7 days after the drawing review and is not a confirmation.
Article 6: If the inspection fails, the contractor shall bear all the costs incurred and the construction period shall be postponed.
The work period will not be postponed.
Article 9:: (1) Damage to the work itself, third casualties and property losses due to damage to the work, and damage to materials brought to the construction site for use in the construction and to equipment to be installed shall be borne by the contractor; damage to materials brought to the construction site for use in the construction and to equipment to be installed shall not be borne by the contractor in this subparagraph.