What are the fire inspection standards for general hospitals?

General hospital fire inspection standards require the following information:

Article 21 The construction unit to apply for fire acceptance shall provide the following materials:

(a) the construction project fire acceptance declaration form;

(b) the project completion acceptance report and the project completion of the relevant fire protection facilities drawings;

(c) the quality of fire protection products qualified Proof of documents;

(d) with fire performance requirements of building components, building materials, decoration materials in line with national standards or industry standards, factory certificates of conformity;

(e) fire protection facilities testing documents;

(f) construction, project supervision, testing units of legal identification and qualification level of documents;

(VII) construction unit of business license and other legal identification documents;

(VIII) laws, administrative regulations and other materials.  

Article 22 The public security organs of the fire agency shall accept the application for fire acceptance within 20 days from the date of fire inspection and acceptance of the organization, and issue fire acceptance opinion.

Expanded Information:

Site sampling and functional testing include:

Site sampling and functional testing include:

1, on-site sampling of the appearance of the building fire prevention (extinguishing) facilities;

2, through professional instruments and equipment involving distance, height, width, length, area, thickness, and other measurable indicators of on-site sampling and measurement;

3, sampling and testing of the function of fire protection facilities;

4, sampling and testing of fire protection products, verification of their market access Proof of documents;

5, on other projects involving fire safety random checks and tests.

The public security organs of the fire protection agencies to declare fire acceptance of construction projects, should be in accordance with the construction of fire protection acceptance assessment standards for fire protection design has been reviewed and approved the content of the organization of fire protection acceptance.

The comprehensive assessment of the conclusion of the construction project, the public security organs of the fire agency shall issue fire acceptance opinion; the comprehensive assessment of the conclusion of the unqualified, shall issue fire acceptance opinion, and explain the reasons.