Supervision bystander record writing method:
(a) the basic situation
including the project name, number, date and climate, the project location, bystander supervision of parts or processes, bystander supervision start time, bystander supervision end time.
Numbering should be reasonably determined, easy to organize and find. Such as the use of 2002102802, said October 28, 2002 occurred in 02 parts or processes of a bystander supervision record, so that can be clear, not easy to confuse. The best regular (such as a month) to organize and bind the side station supervision record table, convenient for future use and management.
Climate includes cloudy, sunny, rainy, snowy and temperature changes (maximum temperature, minimum temperature), wind. Accurate weather conditions allow supervisors to determine whether the weather conditions are available at the site of the bystander supervision or to request the construction unit to take appropriate operational measures according to the weather conditions. Weather temperature on the concrete and mortar strength growth rate has a significant impact, while rain will affect the water content of sand, stone relationship to the concrete, mortar ratio, and thus affect its strength, so carefully record the weather conditions is quite an important part.
Side supervision of the parts or processes should be written in the part of the line, elevation, or a division (sub-division) project, sub-projects, test batch.
(ii) construction
Mainly record the construction process of the construction unit in the key parts or key processes, testing and inspection, the use of machinery, equipment and materials, safety and civilization of construction.
(C) Supervision
Mainly reflects the project supervisory body in the side supervision process of three control (investment, progress, quality control), two management (contract, information management), a coordination (coordination of the relationship between the parties) behavior.
(D) problems and processing
Including the discovery of problems, processing opinions, remarks three aspects. Discover the problem can be supervisory personnel, can also be construction, design, construction unit of the personnel found proposed. Handling of the problem should be analyzed and come to a conclusion (not necessarily the final conclusion, such as the project supervision body will be the analysis of the problem forwarded to the design or construction departments to deal with). Remarks is the problem and processing of tracking records, is the final conclusion of the problem after processing records, that is, the whole problem after processing "closed".
(E) construction, supervision personnel to sign the confirmation
On-time signature confirmation is one of the important aspects of the bystander supervision record, there is no construction quality inspector, bystander supervision personnel to sign the bystander supervision record is invalid. Not signed in time, is not the importance of the work of bystander supervision, irresponsible, so there must be a rigorous timeliness. It is recommended that the bystander supervision personnel in the bystander supervision within 24 hours after the end of writing, confirming the signature, and sent to the hands of the construction quality inspector; construction quality inspector in the receipt of the bystander supervision record within 24 hours to confirm the signature, and sent back to the bystander supervision personnel, if there is any doubt in the middle should also be within 24 hours of the two sides to discuss the solution.
Expanded Information:
(a) the side supervision record as a true record of the side supervision work, should be different from the "supervision log", so the two should be recorded separately, can not be merged, and the content should also be different. Such as the supervision log is a daily record, there is a continuity, while the bystander supervision record is only in the case of bystander supervision occurs to record, does not occur is not required to record.
(b) the proposed side supervision record in triplicate, supervision, construction, construction unit, but the construction unit that can be summarized by the project supervision body monthly and then handed over. This can avoid forgery, all parties have a certain understanding of the implementation of the project, but also allows the construction unit to make certain engineering decisions in a timely manner, so that the project is more smoothly implemented.
(C) side supervision records can not be vague and general, a single one-sided, not to mention the misspelled words, words do not mean. Such as "pounding concrete today", "today's batch swing", "with yesterday" and so on.
(D) side supervision records written, to be timely to the project superintendent engineer review, in order to communicate and understand in a timely manner, so as to promote the supervision work in a normal and orderly manner.