Introduction to the deep wastewater treatment project construction master schedule?

Depth sewage treatment project construction master schedule

1 construction resource allocation

1.1 construction team arrangement

1, the whole plant road, site and process installation works by the general contractor to organize their own construction.

2, four 3000m3 steel manufactured water tanks within the group company to seek internal construction unit subcontracting construction.

3, civil engineering, piling works and high and low voltage distribution instrumentation and self-control for professional subcontracting.

(1) Selection of subcontracting construction units by invitation to tender.

The civil construction of the whole plant is divided into two sections: pretreatment area, super-consideration and reverse osmosis workshop, office building, enclosure and biochemical treatment area and intermediate tanks, etc. Under the guidance of the competent authorities of the Group Company, the subcontracting construction unit will be selected by inviting tenders from the construction teams that have been licensed to enter Hong Kong for construction and have a similar track record of the technical difficulties of this project in the oilfields, which will be determined by the approval of the Project Construction Management Department.

(2) The civil construction subcontract is in the form of package contract. Among them, the construction of temporary construction by the general contractor unified construction of all concrete by the general contractor to build a mixing station unified production. Cement, steel and other major materials by the general contractor in accordance with the provisions of the Group designated material supply and marketing company supply. Bidding price is prepared in the form of package contract for commercial concrete and steel, cement and other main materials uniformly specified price of large-scale temporary requirements listed in the breakdown of separate offers. Signing the subcontract at the same time to the winning bid price minus the large temporary facilities provided by the general contractor for the cost of commercial concrete and steel, cement and other raw materials direct costs (according to uniform pricing) as the contract price.

1.2 construction equipment configuration plan

1, road, site, process installation construction equipment by the general contractor according to the need to configure the configuration plan in the preparation of the construction organization design according to the progress of the plan requirements.

2, civil engineering piling project construction equipment, machinery and tools by the subcontractor according to the need to configure the configuration plan in the preparation of the construction organization design according to the progress of the plan to determine the requirements and in the subcontracting bidding documents to put forward clear requirements.

3, lifting, transportation, earth moving construction with large equipment in principle, who construction who equipped (self-provided or rental can be). If the subcontracting unit has difficulties, the general contractor has the ability or can be rented within the oilfield to solve the problem, the general contractor will provide or help to contact within the oilfield to rent.

4, construction equipment configuration plan see annex 2: "deep sewage treatment plant construction equipment configuration plan list".

2 construction progress plan

2.1 progress plan node control

This project is a self-supporting thermal power plant supporting water supply projects to meet the owner's principle of not arranging winter construction and the project in the completion of the commissioning requirements on the basis of the construction of the total progress of the plan according to the principle of balanced construction and optimization of the construction management costs as far as possible. The total progress of the construction of the project according to the following stages of nodal control.

1, the completion of the following construction:

(1) site filling and site leveling construction road construction construction water, electricity facilities construction and construction of production, living with temporary facilities construction;

(2) foundation pile pressure pile construction and quality inspection of foundation pile construction;

(3) organization of civil construction team to enter the field and complete the preparation for the start of work.

2. In addition to the deep pit support works and ultrafiltration equipment pit does not arrange other winter construction to complete the following construction:

(1) intermediate pool, wastewater recycling tank, intermediate mixing tank, aeration filter tank, RO thick pool deep pit support works;

(2) hydrolysis tank reinforced concrete footing casting coagulation reaction precipitation tank, V-type filter tank foundation earthworks;

(3) 4 3000m3 steel manufactured water tank foundation to complete the foundation pile bearing platform;

(4) ultrafiltration and reverse osmosis workshop, office building, mechanical repair room, dosing room and other building foundation reinforced concrete structure construction to ± 0.00.

3, full access to the peak period of civil engineering construction to complete the construction of the following:

(1) complete the 4 3000m3 steel manufactured water tank fabrication, water testing and the interior of the water tank. Water tank production, water testing and internal and external corrosion protection delivery process installation.

(2) Completion of all reinforced concrete pool civil construction and water testing, inner wall anti-corrosion, outer wall heat preservation, pit backfill delivery of equipment and technology installation;

(3) Completion of all plant and other buildings to complete the main construction of civil delivery of equipment and technology installation.

(4) Completion of the plant reinforced concrete valve pools, valve wells and other structures construction delivery equipment technology installation.

4, depending on the civil works to deliver equipment technology installation time to start equipment technology installation construction July 30-October 20 for the peak of equipment technology installation construction. Completion of the following construction content:

(1) complete the 4 3000m3 steel manufactured water tank tank process and the installation of the valve group in front of the tank.

(2) Completion of all the pools and biochemical treatment device internal process installation.

(3) complete the ultrafiltration and reverse osmosis workshop equipment process installation and delivery of civil construction closing.

(4) Completion of other industrial plants and production equipment and process installation delivery of civil closing.

(5) Completion of the plant process pipe network installation.

(6) Completion of the installation of variable power distribution system.

(7) Completion of installation of instrumentation and automatic control system.

5, complete the plant earth backfill work at the same time to complete the construction of the fence.

6, complete the plant road and site construction.

7. Completion of stand-alone test run

8. Completion of joint test run of clean water media process system.

9, complete the plant greening construction. Which completed in 2007 to complete the engineering part of the completion of plant planting.

10, the project reached the pre-acceptance conditions.

11, to assist the use of units to complete the feeding test run delivery and acceptance of the project delivery.

2.2 Construction General Progress Plan

Construction General Progress Plan to the network plan for details see the "depth of the sewage treatment plant construction General Progress Plan".

More about the engineering/service/procurement category of the tender writing production, enhance the winning rate, you can click on the bottom of the official website customer service free consultation:/#/?source=bdzd