Table of Contents
I. Overview of the project
II. Basis for preparation
III. Selection of construction program
IV. Construction period, progress plan
V. Arrangement plan for the main management personnel of the project department and the laborers used
VI. Arrangement plan for the main construction machinery
VII. Material Requirement Plan
VIII. Winter and Rainy Season Construction Measures
IX. Guarantee of Schedule, Quality, Safety and Civilized Construction
Measures to Reduce Nuisance to the Public to Lower the Environmental Pollution and Noise
(I) Schedule Guarantee Measures
(II) Quality Assurance Measures
(III) Measures for Safety and Civilized Construction
(IV) Measures to Prevent Nuisance to Reduce Environmental Pollution and Noise
(IV) Measures for Prevention of Nuisance to the People to Lower the Environment and Noise
(D) measures to prevent nuisance and reduce environmental pollution and noise
Ten, the site of temporary electricity special program
Xi, material management system and conservation measures
XII, quality standards and acceptance methods
XIII, the disease and accident measures
XIV, rationalization proposals
XV, the construction site Layout Plan
Preface
According to the construction requirements and design drawings of CFG pile project of Qingdao Siyuan Petrochemical Company's solvent oil project, our company carefully organizes the technicians to be familiar with the drawings and relevant information, and carefully prepares the technical plan and construction organization design for the characteristics of this project. The project is located in Huangdao Economic Development Zone of Qingdao City. This project adopts cement fly ash rubble pile (referred to as CFG pile) composite foundation reinforcement treatment.
I. Project Overview:
(1) Project Name: Qingdao Siyuan Petrochemical Company Solvent Oil Project CFG Pile Project;
(2) Project Address: Crossing of Huangzhang Road and Huaihe Road, Qingdao Development Zone;
(3) Piling Form: Cemented Fly ash rubble piles (CFG piles) are adopted for the foundation of raw material storage tanks; the designed length of a single pile is 13.00m, pile diameter 600m, and the length of a single pile is 1.5m. 13.00m, pile diameter 600mm, pile distance 1800mm;
(4) the amount of work: CFG piles; about 1,600 (raw material storage tanks according to the calculation of 10), cumulative design and construction of 20,800.00 extension of the meter, about 7,641.58m3 grouting concrete;
(5) the site geology:
Regarding the China Petroleum Corporation (CPCC), the China Petroleum Corporation (CPC) has developed a new project, which is a new project of the China Petroleum Corporation. Ltd. Geotechnical Engineering Detailed Investigation Report provided by East China Survey and Design Institute in May 2001, the geotechnical stratigraphy within the pile length is divided as follows (see the investigation report for details):
The first layer of soil, man-made fill: it consists of two sub-layers of vegetative fill and fly ash alluvial fill with a low degree of consolidation, saturated, underconsolidation and high sensitivity. The thickness is about 4m.
The second layer of soil, powdery clay: saturated, fluid-plastic to soft-plastic state, with high compression, high sensitivity stratum. The thickness is about 6.0m.
The third layer of soil, powdery clay: saturated, plastic state, medium compression stratum. The thickness is about 2.7m.
The fourth layer of soil, granite all-weathering zone: saturated, plastic ~ hard plastic state, is a medium ~ low compression stratum. The thickness is about 3.1m.
II. Basis of Preparation
(1) Requirements for the construction of CFG pile project of solvent oil project of Qingdao Siyuan Petrochemical Company;
(2) Experience of construction of similar projects;
(3) Main specifications adopted:
(1) Code for Acceptance of Quality of Construction of Building Ground Foundation Works, GBJ50202- 2002;
(2) Code for Construction and Acceptance of Petrochemical Steel Tank Foundations and Foundations SH3528-93;
(3) Long Screw Bored and Pumped Concrete Pile Composite Foundation Technical Regulations DB13(J)31-2001;
(4) Technical Specification for Treatment of Building Foundations JGJ79-2002;
< p>(5) Standard for Concrete Strength Inspection and Evaluation GBJ107-2002;(6) Standard for Concrete Quality Control GBJ5064-2002;
Three, the selection of the main construction program
(1) Selection of the construction process:
According to the design requirements, the foundation of raw material tank area of this project adopts the Cement Fly ash rubble pile (CFG pile) composite foundation treatment, CFG pile composite foundation is different from the main characteristics of the pile foundation is: give full consideration to the play of the bearing capacity of the soil between the piles, so the construction of the soil between the piles should be minimized as far as possible to reduce the perturbation of the soil, but also according to the geological data of the site, the upper part of the ground layer of the site is mainly made up of saturated, high compressibility, high sensitivity of the pulverized clay, the construction of the influence of the impact of touching the change is relatively large. Large. Therefore, in order to ensure the quality of pile construction, minimize the disturbance of soil between piles, and ensure the smooth progress of this project, the reasonable selection of mechanical construction technology is the key to the smooth progress of this CFG pile construction project.
The original big oil refining project (1993) in the north side of the project construction tank base foundation treatment program selected D400mm dense gravel pile, immersed tube into a hole, filling and pulling, spaced skipping; because of the geology is saturated clay soil, pile quality can not be guaranteed, serious necking rate of 46%, shallow pile breakage rate of 22%. Later, the spaced cement powder spraying piles and reinforced concrete piles were adopted to reinforce the piles.
At present, there are three types of CFG piles construction methods: vibrating immersed pipe grouting, long spiral drilling and grouting, and long spiral drilling and pumping in pipe grouting, which have the characteristics of fast construction speed, high pile compactness, low environmental noise impact, low impact on the surrounding inter-pile disturbance, and especially suitable for high sensitivity stratums below the water table. Therefore, the construction process of CFG pile project is proposed to adopt the long spiral drilling-pumping concrete filling in pipe process. Underwater pumping concrete, pulling out the pipe while pressing concrete, adopting replacement reinforcement, strong penetration force, high bearing capacity of single pile, will not be affected by the second layer of saturated, rheoplastic ~ soft plastic state of powder clay. And it can reach the requirement of design bearing capacity (characteristic value of single pile bearing capacity ≥600kN, composite foundation bearing capacity ≥210KPa), and the quality of the pile is guaranteed.
CFG pile test pile
In order to ensure the quality of the project, according to the design requirements, two tanks with representative geological conditions are selected as the test pile area, and three shapes or single pile composite foundation are pressed in each test area.
Because of the construction site near the loading of heavy loads to solve, it is recommended to use anchor piles as the reaction force, in the test pile construction, the anchor piles to be placed in the reinforcing cage, the test piles are arranged as follows: (Figure in the Annex)
(ii) Construction sequence:
Combined with the characteristics of the raw material tanks CFG piles structural layout and the site geologic conditions, the project adopts: advancing from the center to the outside of the construction (circular pile distribution) This project adopts: advancing construction from the center to the outside (circular pile) or advancing construction from one side to the other (square or plum blossom grid pile), according to the specific conditions, further in order to minimize the disturbance of soil between piles, control the construction process, find out the special conditions, make specific changes, and if necessary, adopt the construction method of interval jumping.
(C) equipment selection:
Two sets of KLB-75 walk-behind long auger drilling rigs are used; two sets of QZ-60 concrete pumps are used; one set of 500-type forced mixer is used; two sets of loaders are used; one set of electric and gas welding equipment is used; one set of leveling instrument and latitude and longitude instrument are used, as well as other auxiliary equipments.
(4) Construction process:
CFG pile: positioning line→starting pile machine to align the pile position→leveling the pile machine, straightening the drill pipe→closing the valve of the drill bit to start the hammer drilling to the bottom elevation of the designed pile, and at the same time mixing the mixture→starting the concrete pump to fill in the material, and at the same time starting the winch to lift the drill pipe to the elevation of the top of the pile of the construction design→pile formation is completed→shutdown and shifting to the next pile position.
CFG pile process flow diagram: (see annex)
(E) the construction method of the main branch project:
(1), positioning: move the pile machine to the designated pile position, centering. When the ground is undulating and uneven, the outrigger or platform base should be adjusted to keep the base of pile driving machine horizontal and the drilling rod vertical. Generally the error of pile position should not be more than 2.0CM, and the deviation of verticality of drill pipe should not be more than 1.5%.
(2) Drilling: Close the valve of the drill bit, start the winch to lower the drill pipe until the drill bit touches the ground, then start the hammer head of the drilling rig and rotate the drill pipe to sink to the design elevation of the pile bottom.
(3) Mixing: Prepare the mix according to the design ratio, strictly control the size of coarse aggregate, usually 10mm-30mm or smaller, add pumping agent and other additives if necessary, the slump of the mix should be 180mm-220mm.
(4) Filling and lifting: When the drilling rig drills to the pile holding layer, start the concrete pump to fill the pile, when the pipe and the core of the drilling rod touch the ground, start the pump to fill the pile. When the conveying pipe and the core pipe of the drill pipe is full of mixed material, start the winch to lift the drill pipe at a constant speed, while filling, while lifting, until the top of the pile elevation of the construction design, the lifting speed should be controlled at 2m/min-3m/min, it is strictly prohibited to pull out the pipe and then fill the material, to grasp the difference in time between filling and lifting the drill, and try to avoid the phenomenon of waiting for the material to be lifted and filled during the process of stopping the material. In the fluid-plastic soil, the drilling speed should be controlled to ensure the quality of piling.
(5) Stop filling the pile top elevation, move the machine to the next pile position: try to control the pile top elevation to stop the gray surface of this link, under the condition of reaching the technical requirements, to do as little as possible to waste the mixture.
Four, construction period, progress plan
This project is proposed to use KLB-75 walk-type long auger drilling rig 2, the construction period since the signing of the construction contract, the construction site to meet the requirements for the start of the work: the project CFG pile construction 1600, the cumulative total design length of 20,800.00 extended meters, the plan for the 30/each per day, 30 days to complete the task. (See engineering progress plan crosswalk) (Figure see attached)
V. Arrangement plan for the main management personnel and laborers used in the project department
1, the construction organization is as follows: (Figure see attached)
2, the main management personnel and their responsibilities are as follows:
Project manager presides over the overall leadership of the piling project, and is responsible for the overall piling construction. He is fully responsible for the organization of personnel, material plan, construction arrangement and coordination of each link in the process of production, and is fully responsible for the schedule, quality and safety in the process of construction. Make full use of manpower and material resources, and effectively utilize the time, in order to ensure the quality and quantity of this pile foundation project completed on schedule.
Technology is responsible for cooperating with the project manager to do a good job, manage the production technology work, organize the production construction scientifically, lead other technicians to give full play to their technical advantages, formulate the construction technology guarantee measures in detail, ensure the quality of the project, improve the efficiency of the production and construction, and actively cooperate with the construction unit, the supervisory unit and the testing unit to carry out the acceptance of the project work.
The quality inspection supervisor is responsible for sampling raw materials, checking the pile position, checking and accepting the preparation, mixing, conveying and other processes of the mixture in a timely manner during the construction, and reflecting the inspection situation and the relevant information to the person in charge of the technology in a timely manner in order to deal with the problems in time, so as to achieve the accuracy of the construction work.
Safety inspection supervisor is responsible for checking the construction site safety of electricity, to eliminate construction machinery, fire and other aspects of the hidden dangers, regularly organizing safety education for employees, after the occurrence of accidents should be dealt with to achieve the "four do not let go": First, the cause of the accident is not clear do not let go; Second, the staff and the person responsible for the accident can not be educated to let go; Third, the hidden danger of the accident is not rectified do not let go; Third, the hidden danger of the accident is not rectified do not let go. Accident hidden danger is not rectified is not spared; Fourth, the person responsible for the accident is not dealt with is not spared.
Materials supervisor of all kinds of materials to strictly quality control, is responsible for planning a good amount of various materials to achieve timely supply, the materials supplied by the construction unit should be reported to the plan in advance, timely receipt.
Seven, the main material dosage plan
CFG pile mix composition for cement, fly ash, crushed stone plus a small amount of dopant, the project CFG pile materials to be selected 42.5R grade slag silicate cement, fly ash, small 10mm-30mm crushed stone, composite antifreeze early-strengthening agent.
CFG piles; 1600, pile design construction length of 13.00m, pile diameter 600mm, the construction of the total cumulative design length of 20800.00m; about 7641.58m3 grouting concrete (construction filling coefficient according to 1.3 considerations); the design requirements of the standard value of composite foundation bearing capacity fsp.k is not less than 210Kpa. in the selection of materials should be in line with the corresponding standard requirements, and the proportion of no test. In the case that the selected materials should meet the corresponding standard requirements, and there is no laboratory data for the ratio, now according to the construction experience and conventional ratio roughly analyze the amount of materials required as follows (according to the design requirements of CFG pile body strength ≥ C15, single pile bearing capacity characteristic value ≥ 600KN).
(Ratio: cement fly ash sand gravel water composite admixture)
(3009070010002108)
Material dosage: cement; 2293T. fly ash; 688T.
Sand; 3566m3. gravel; 4246m3.
Water; 1600m3. composite admixture. 62T. 62T.
The actual material requirement will be analyzed by the laboratory ratio data.
Eight, winter, rainy season construction measures
1, the storage of cement should be strictly protected against rain, snow, moisture, rain measures, the incoming materials should be in accordance with the provisions of the location of the stacking and protective measures to prevent freezing, moisture. Do build a high platform - under the pavement cover; mechanical and electrical equipment using rain, snow, flood prevention measures, the installation of grounding devices, mechanical electric gates, boxes of protection devices should be reliable.
2, winter construction, the mixture mixing process according to the requirements of adding the appropriate amount of anti-freezing early strength agent, construction water should be heated to prevent the freezing of the blocked pipe caused by the low progress of the project or the quality of the pile body problems.
3, winter construction to do other aspects of anti-freezing, cold measures, water pipe insulation, special machinery special parts of insulation, workers issued cold clothes.