Agreement is a social life, collaboration between the two sides or several parties, in order to protect their legitimate rights and interests, by both sides or several parties **** with the consultation to reach an agreement, signed a written material. Agreement is a contractual instrument. So how to write a good agreement?
Part I engineering labor contracting agreement model
Party A: operation team (hereinafter referred to as Party A)
Party B: ______ team (hereinafter referred to as Party B)
According to the need for Party A to undertake the task of the project, by the friendly consultation between Party A, Party B, on the basis of equality and mutual benefit, friendly cooperation In order to clarify the responsibilities and rights of the two parties, this agreement is signed for both sides **** with the implementation of compliance. Specific terms are as follows:
I. Project name: ____________ Court garage concrete project
Second, the project address:
Third, the structure type:
Fourth, the building area:
Fifth, contracting mode: package clearing, package limit of collaterals, package quality, package safety, package progress (package duration), package civilization, package construction. The structure of the acceptance.
Six, the contract content and requirements:
Concrete engineering:
1, concrete pouring before the mold of the sporadic garbage cleanup, watering and wetting, ride, demolition, move pouring within the scope of the temporary runway, ride, demolition, clean the concrete pump conveying pipe, concrete horizontal, vertical transportation, vibration, leveling, receiving surface, pumping pipe conveying after the concrete treatment and reuse, handling of the leakage of slurry. Handling and repairing of honeycomb, pockmarked surface, bursting concrete and storm pipe concrete. Pouring of concrete for railings, roofs, daughter walls, platforms, slopes, and other sporadic components, and maintenance of concrete after pouring, as well as making test blocks in cooperation with the tester. Production of prefabricated components, processing of prefabricated boxes, production of concrete pads. Repairing the edge and checking the bottom, shoring around the pit and shoring steel pipe erection, mending the eye of water-stop screw, repairing the r-line, and erecting the steel pipe handrail of the inner staircase. Including the site of all incoming and outgoing materials on and off; and to ensure that the upper and lower materials stacked to the designated location (sub-specification, type, stacked neatly and clean).
2, civilized standardization within the scope of work, cleaning and sanitation.
3, the design institute and the construction unit of the project modification changes occurring in the increase or decrease in the amount of work.
4. Safety and civilization within the scope of contracted works.
5. The erection and dismantling of productive temporary.
7. Unit price of subcontracting:
No.
Name of subitem
Unit
Unit price (yuan/floor area)
Remarks
Superiority
Safety
Progress
Civilized construction
1 Concrete pouring, concrete receiving surface, site, floor Cleaning, repairing, loading and unloading of materials (including transfer) ㎡
10.00
Construction area
Description:
1. There will not be any hourly labor within the scope of contracted construction. Failure to meet the quality standards required by the Party according to 80% settlement;
2, the unit price does not deduct taxes;
3, the unit price has included safety, progress, civilized construction, tool costs, etc.; if there is a safety incident corresponding to the quality of the unit price is reduced by 1.00 yuan / floor area; if there is a failure to meet the requirements of the progress of the corresponding quality of unit price is reduced by 1.00 yuan / floor area; if there is a civilized construction does not meet the requirements of the corresponding quality level unit price is reduced by 1.00 yuan / floor area; if there are Civilized construction can not meet the requirements of the corresponding quality level unit price reduced by 1.00 yuan / floor area.
Eight, the project quality standards: 100% good rate, according to the quality requirements of the standard, the contracting team must be in strict accordance with the quality acceptance standards and construction specifications, good construction of each process, each process after the completion of the team must do a good job of self-checking, mutual inspection, and then notify the A party, the general contracting unit and the supervisory unit acceptance. Acceptance of quality standards before the next process, less than the quality standard must be carefully in accordance with the acceptance of the proposed rectification measures and requirements for rectification until the standard is reached. If the rectification still does not meet the requirements Party B must bear double the occurrence of the general contractor's fine penalty to Party A, as compensation for Party A's credibility.
Nine, the duration of the requirements: the total duration of days (according to the general contractor's progress plan implementation). If you can not be completed within the required period of time, resulting in the general contracting party to Party A's schedule penalties, according to Party B's total contracted price in accordance with the appropriate proportion of double penalties.
Ten, safety requirements and comprehensive management:
1, the contracting group must seriously study and master the safety management regulations and operating procedures, in strict accordance with the safety regulations for construction. Such as violating the safety operating procedures unauthorized operation caused by safety accidents, by the violator of the full responsibility.
2, strictly abide by the laws and regulations and XX city, obey the general contractor and the Party and other relevant departments of the command, consciously abide by and implement the general contractor and the Party's rules and regulations. If safety accidents occur during the construction process, the costs incurred within ____________ yuan will be paid by the team, ____________ yuan --- within ____________ yuan Party A is responsible for half, ____________ yuan or more Party A is responsible for 60% of the total costs. Security accidents above ____________ yuan will be handled with the assistance of the security department. Contracting team to enter the construction site of all relevant documents must be complete and submit a copy and a roster to the Party for the record.
3, the contracting team to enter the construction site of the relevant documents must be complete and submit a copy and a roster to the Party for the record.
4, into the construction site must be the correct use and wear a variety of safety equipment, must wear a helmet and fasten the seat belt, such as found not to wear a helmet and do not fasten the seat belt to give the ______ yuan / person fines, violation of safety regulations and without the consent of the competent authorities to arbitrarily remove the safety protection of the seriousness of the situation is punished by a fine of ______ - - ______ yuan.
5, the dormitory is strictly prohibited indiscriminate wiring, it is strictly prohibited in the dormitory cooking food, once found in addition to the confiscation of cooking utensils and impose a fine of more than 200 yuan. The use of all electrical equipment is prohibited in the dormitory.
6, it is strictly prohibited to fight, gambling, if found first given to both parties to impose a fine of ______ ---- ______ yuan, and then according to the results of the investigation, the responsible party to bear all the losses of the other party, the circumstances of the serious transferred to the judiciary to deal with.
7, it is strictly prohibited in the dormitory men and women mixed, the site is strictly prohibited with family, if there is a family to give ___
____ yuan / person a fine, if there is the phenomenon of mixing to give ______ yuan / person a fine; without the consent of the competent authorities shall not stay non-shift personnel, every time to give ______ yuan / person a penalty, care of public property, shall not be damaged facilities. The company's main goal is to provide the best possible service to its customers.
8, where the construction area outside the occurrence of security incidents, are responsible for by Party B itself.
XI, Party A's responsibilities:
1, is responsible for Party B for quality, safety, progress, civilized construction, operation specifications and other technical instructions.
The construction capacity of Party B after entering the field, personnel quality, technical quality, assessment, to give Party B 30 days of probationary period, such as the probationary period Party B does not meet the quality, progress, civilized construction, comprehensive governance requirements of Party A has the right to unilaterally terminate the agreement, the construction of some of the volume of the project will not be settled as a loss of credibility of the Party's compensation. Party B will compensate for Party A's economic loss.
2, according to the site conditions, to provide party B's food, accommodation, and its own costs.
3, actively create construction conditions for Party B, and do a good job of coordination.
4, responsible for Party B's quality, safety, progress, civilized construction supervision and inspection, does not meet the requirements of the proposed rectification and measures. If Party B rectification fails to meet the requirements or not rectified, Party A has the right to send people to rectify, the cost of rectification part of the workload according to the cost of twice from the Party B labor costs.
XII, Party B's responsibilities:
1, according to the amount of contracted work to organize the appropriate construction personnel, into the field personnel must be a reasonable mix of its ideological quality, strong technical skills, no health diseases and infectious diseases 18 - 45 years old male. Each contracting team has a comrade with strong organizational ability, good technology and strong sense of responsibility as team leader to form a systematic management. At the same time the team leader shall not leave the site without the approval of Party A's on-site supervisors, and actively participate in the relevant meetings organized by Party A or the General Contractor, where unauthorized departure from the site or do not participate in the meetings that should be attended to give ______ ---- ______ yuan / times a fine.
2, familiar with the construction drawings, in strict accordance with ? Construction and Acceptance Code for Building and Installation Engineering? and design requirements, to organize construction, to ensure project quality, progress, safety, rework caused by poor management of quality standards can not be achieved, should bear the resulting loss of materials, time.
3, Party B into the field must be relatively stable, without the consent of Party A shall not change the team personnel.
4, accept Party A on quality, safety, civilized construction and other technical briefing, education and supervision, and obey the command.
5, the Party puts forward corrective comments should be immediately organized to rectify, until it reaches the standard.
6, caring for the facilities and equipment provided by Party A, shall not be damaged at will, if any damage will be given twice its value to be compensated and penalized.
13, civilization standardization, health requirements:
1, seriously improve personal, dormitory, on-site hygiene, keep civilized and clean at all times.
2, seriously in accordance with the requirements of civilization standardization, the materials within the scope of their own contracting classified and stacked neatly.
3, the completion of each process, must do a good job of site clearance, can use the material must be utilized.
4, where the above does not meet the requirements, according to its nature, scope and value of more than twice the fine, each time each minimum not less than ______ yuan.