The first part of the project construction implementation plan
In order to effectively improve the flood control and drainage capacity of Xingguo County and ensure the safety of people's lives and property, according to? One city and three districts? 、? Three rivers and six banks? Overall planning, in order to ensure the orderly progress of barrage projects on both sides of a river as planned, this implementation plan is specially formulated:
I. Overview of the Project
Damming projects on both sides of a river cover the intersection of Tongjiang estuary and the lower reaches of two rivers. The dam is about 320 meters long and consists of a flap gate. What is the general requirement of engineering construction? Strong flood discharge capacity, low investment cost and characteristics of rejuvenating the country? . The main contents of the project construction include:
1. Thoroughly inspect the land, graves and trees around the dam, and delimit the expropriation scope.
2. Complete the land requisition, grave migration, transplanting of various trees and clearing of miscellaneous trees around the dam site.
3, according to the policy and the relevant compensation standards that have been issued in the county, do a good job in land acquisition, grave relocation, tree felling and transplantation of funds compensation.
4. Do a good job in project environmental impact assessment, soil and water conservation plan report and other related work.
5. Make other preparations for the barrage project.
6. Complete the preliminary design and technical design of the project, and complete the drawing review.
7, engineering construction and engineering supervision bidding.
8, the construction team in construction.
9, project completion acceptance and operation.
Second, the working mechanism
In order to ensure the smooth implementation of the project construction as soon as possible, the office of the county party committee and the government office issued the Notice on the Establishment of a barrage construction headquarters on both sides of a river on March 8, 2008, which made it clear that the county party committee, the deputy county magistrate and the minister of agriculture, industry and agriculture were the chief commanders and were responsible for the overall work of the headquarters. The vice chairman of CPPCC is the deputy commander-in-chief, responsible for the coordination, inspection, arrangement, use and management of the daily work of the headquarters and the funds for project construction. The headquarters is composed of the following institutions:
1, office:
Moderator: Preside over the overall work of the office.
Deputy Director ():, responsible for the daily work of the office, organizing and coordinating, checking and implementing, proposing work plans and arrangements, and formulating work measures and schemes.
Deputy Director: Responsible for expense audit, material procurement, fund application and financial reimbursement, and daily office affairs.
Office staff:
Responsible for engineering quality and technical control, engineering quantity verification and engineering change approval.
Responsible for drafting documents and materials, meeting preparation, work reception, uploading and issuing, seal management, report submission and coordination.
Assist and do a good job in related affairs.
2. Land acquisition and demolition group:
Group length:
Deputy team leader:
Member units: Land and Resources Bureau, Housing Authority, Forestry Bureau, towns and industrial parks.
Responsibilities: Responsible for land requisition, grave relocation, tree transplantation and fund compensation audit.
3, working technology group:
Team leader:
Members:
Responsibilities: Responsible for monitoring and verifying the whole process of engineering construction quality, and signing and approving engineering changes.
Three. Work arrangement and implementation steps
1. The county water conservancy bureau will take the lead and the city investment company will cooperate to complete the dam site selection, survey, measurement and feasibility study report before April 20, 2008;
2. The county development and reform commission will take the lead, and the Water Conservancy Bureau and the city investment company will cooperate to complete the project feasibility study review, project establishment and other related work before May 10;
3. Take the lead by the county investment company and cooperate with the Water Conservancy Bureau to implement and determine the preliminary design unit of the project before the end of April, come up with the preliminary design plan before June 10, and complete the preliminary design review before the end of June;
4, by the county environmental protection bureau is responsible for, before May 30, 2008, complete the project site observation and monitoring and environmental impact assessment report;
5, the county soil and water conservation bureau is responsible for, before May 30, 2008, complete the compilation of soil and water conservation project report;
6. With the cooperation of the County Land and Resources Bureau and the administrative committees of towns, townships and industrial parks, the land acquisition survey and scope definition around the dam will be completed before May 10; Go through the land acquisition procedures before May 20, and pay the compensation for land acquisition funds before the end of May;
7. With the cooperation of the County Housing Management Bureau and the town, township and industrial park management committees, the investigation and verification of graves around the dam and the selection of new grave resettlement sites will be completed before May 20, 2008, and the grave owners will be informed to make preparations for relocation before June 10, pay compensation for relocation funds, and complete the relocation of all graves before July 10;
8. The County Forestry Bureau is responsible for the inspection of tree cutting and transplanting around the dam before May 15, and completing the examination and approval procedures before May 25 and the tree cutting and transplanting before June 20;
9. The county investment company will take the lead in organizing relevant departments to complete the project bidding before August 15, 2008, determine the construction unit and sign the construction contract;
10, at the end of August, 2008, the construction team entered the site and the project officially started construction (including the protective dike and its supporting ancillary works);
1 1. The headquarters is responsible for guiding the construction unit to complete the first-phase cofferdam diversion project by the end of 10, the dam foundation cleaning and the civil works of the pump house by the end of 12, and the first-phase dam construction and gate by the end of12.
12, before the end of June, do a good job in project closing, acceptance and handover;
14, the headquarters office shall, in accordance with the above-mentioned implementation steps, conscientiously do a good job in pre-planning, follow-up service, supervision and inspection in the early, middle and late stages of project construction, and increase the guidance and management of project construction.
IV. Project Budget and Fund Use
The project is constructed according to the design scheme approved by the county government, and the city investment company is responsible for preparing the project budget in consultation with relevant departments, and the city investment company is responsible for reviewing, allocating and supervising.
Verb (abbreviation of verb) Work measures and requirements
1, strengthen leadership.
It is required that the personnel transferred to the headquarters should be relatively stable, ensure that they are on the job, pay attention to people, devote their heart, time and energy, and implement all the work according to their respective responsibilities.
2. Pay close attention to the progress.
Each member unit and working group of the headquarters shall draw a work flow chart according to the requirements of the time schedule and work implementation plan, submit the work progress of the month to the headquarters in writing before the 25th of each month, and submit the work arrangement and plan for the next month.
3. Strengthen scheduling.
In principle, the headquarters will hold a work dispatch meeting once a week, and each working group will report the work carried out last week, coordinate and solve the difficulties and problems in the project progress, and study and deploy the work plan and arrangement for this week.
4. Clear responsibilities.
Countdown assessment shall be carried out for each work, with responsibilities detailed to member units and tasks implemented to individuals, with clear responsibilities, proper methods and measures, proper procedures and limited time, and the headquarters office shall be responsible for supervision and inspection.
5. Coordination and cooperation.
All member units and working groups at the headquarters should carry out their work under the unified leadership of the headquarters, establish an overall concept, support each other, cooperate closely, form a joint force and do all the work well.
6. rewards and punishments are clear.
All member units and working groups of the headquarters should take the initiative to do a good job in accordance with their respective job responsibilities, promptly handle and resolve all kinds of contradictions and disputes arising in the work, ensure the smooth progress of the project construction, and reward and punish all member units and individuals according to the completion of the work.
The second part of the project construction implementation plan
In order to implement the spirit of the State Council's Notice on Further Promoting the Construction of National Green Passage Project (Guo Fa [20xx]3 1No.) and complete the greening project of Xiyan Expressway in our city on time with good quality and quantity, this implementation plan is specially formulated according to the Master Plan for Greening Forest Belt Project of Xi Main Road.
First, the significance of engineering construction
Is the construction of the green passage project of Xiyan Expressway implemented? Western Development, Xi 'an Development? An important measure of this strategy is an important part of the green passage network project of nine main highways implemented in our city, and it is also an important way to improve the ecological environment, beautify the ancient city of Xi 'an, improve the quality of life of urban and rural residents and meet the sustainable development of social economy. The implementation of this project can not only increase the green area of our city, reduce the air pollution caused by various waste gases and dust, but also promote the adjustment of agricultural industrial structure along the line and promote the healthy development of the two civilizations.
Second, the guiding ideology and principles of engineering construction
(A) the guiding ideology
To implement Jiang? Rebuilding the beautiful northwest region? And the spirit of instructions proposed by Zhu? Mobilize the broad masses of people, plant trees and grass, and improve the ecological environment? Focusing on the protection and improvement of urban ecological environment, taking the construction of high-standard and multi-benefit ecological public welfare forest as a means, and aiming at realizing beautiful mountains and rivers and promoting urban and rural economic development, we will give full play to ecological, social and economic benefits and promote the sustainable development of Xi's economic and social undertakings.
(2) principle
1. Adhere to the principles of unified planning, unified seedling supply, and organization and implementation by districts and counties.
2. Adhere to the principle of unchanged land ownership and adjustment and settlement by counties, townships (towns) and villages.
3. Adhere to the principle of combining the right place with the right tree, giving priority to quality and combining greening with beautification.
4. Adhere to the principle of joint efforts of the state, the collective and the individual, who owns the afforestation, who benefits from the investment and who benefits from the management, and do not plant or build ownerless trees.
Three. Main construction contents
(1) Construction scope
The greening mileage of Xiyan Expressway is 42.6 kilometers (4.5 kilometers for the section under construction), including 9 kilometers for Yanliang (4.5 kilometers for greening), 0/6.5 kilometers for Gaoling/Kloc, 8.6 kilometers for Baqiao and 8.5 kilometers for Lintong. The width of the forest belt outside the barbed wire fence is10m, and the forest belt is equivalent to the total area1278mu.
(two) the construction period and tree species configuration and planting requirements
1. The engineering task shall be completed before the end of March of 20XX.
2. According to the principle of engineering construction, the tree species configuration is as follows: a row of Luan trees is planted 0.5 meters outside the barbed wire fence, with a spacing of 3 meters; Plant 4 rows of poplars 2 meters outside Luan tree, with a row spacing of 2 meters? 2 million. Poplar varieties are 107 Populus tomentosa and triploid Populus tomentosa, which need to be planted in pure forests.
3. seedling size: The height of the seedlings is more than 3.5 meters, and the ground diameter (DBH) is more than 2.5 cm, which is robust, with straight ends and no pests and diseases.
4. Planting requirements: use high-quality seedlings, dig big pits to plant large seedlings, and row spacing? Product? Font configuration. The specification of the planting pit is 60? 60? 60 centimeters. Before planting, water the bottom water, and after planting, water the foot water to ensure the survival of seedlings, and brush the trunk below 1.2 meters.
(3) Seedling requirements
This project needs seedlings 199000, including poplar 17 10000 and Luan tree 28000 (see attached table 1 for details). The districts and counties are as follows:
1. The greening mileage of yanliang district is 9 kilometers, and 42,000 seedlings are needed, including 36,000 poplars and 6,000 Luan trees.
2. The greening mileage of Gaoling County is 16.5km, and 77,000 seedlings are needed, including 66,000 poplar trees and 0/.1.0000 Luan trees.
3. Baqiao District has a greening mileage of 8.6 kilometers and needs 40,000 seedlings, including 34,300 poplars and 5,700 Luan trees.
4. The greening mileage in Lintong District is 8.5 kilometers, and 40,000 seedlings are needed, including 34,300 poplars and 5,700 Luan trees.
Four. Investment allocation scheme
This project is an important part of the beautiful mountains and rivers project, and it is also an important task of the green channel construction in our city. The project is organized and implemented by all districts and counties in accordance with the unified planning, and the municipal finance gives appropriate financial subsidies, with a subsidy of 35,000 yuan per kilometer for planting and management. In order to ensure the engineering quality, all seedlings are provided by the modern comprehensive nursery in the city.
The total investment of the project is 3 million yuan, including 1 107600 yuan (26,000 yuan per kilometer), 149 1000 yuan for planting and management subsidies, 60,000 yuan for technical guidance, 70,000 yuan for supervision, 50,000 yuan for management, and 21000.
Subsidies for districts, counties and road sections are as follows:
1. yanliang district has a green mileage of 9 kilometers and an investment of 3 1.5 million yuan.
2. The greening mileage of Gaoling County 16.5km, with an investment of 577,500 yuan.
3. The greening mileage in Baqiao District is 8.6 kilometers, and the investment is 30 1 10,000 yuan.
4. Lintong District has a green mileage of 8.5 kilometers and an investment of 297,500 yuan.
Verb (abbreviation of verb) safeguard measures
(A) to strengthen leadership and raise awareness
Relevant districts and counties should attach great importance to the construction of the green passage project of Xiyan Expressway, put this project on the important agenda, and fully understand the significance of implementing this project from the strategic height of western development. It is necessary to widely publicize and mobilize, organize all forces, invest in the construction of the green passage project of Xiyan Expressway, and achieve new and better results.
(two) to establish and improve the technology and quality assurance system.
City Forestry Bureau transferred from the city forestry station to 6? Eight professional technicians form a technical guidance and quality supervision team, which is responsible for technical guidance, seedling evaluation and quality supervision. All districts and counties should set up corresponding institutions, and earnestly grasp the project quality under the guidance of the municipal supervisor. It is necessary to observe the procedure of digging planting pits first and then scheduling planting seedlings after acceptance. It is forbidden to dig and plant seedlings after delivery. It must be the same day of seedling raising, transportation and planting. After planting, water the roots to ensure the survival of the seedlings.
(three) serious acceptance, and actively implement.
All districts and counties should make preparations for ideological mobilization and land adjustment before the end of February. In early March, the masses were mobilized to engage in planting activities to ensure that the task was completed on time. 20XX At the end of June, the municipal government will organize relevant departments to carry out inspection and acceptance, and commend and reward those who have completed it; Those who fail to complete the project will be given to informed criticism, and relevant leaders will be held accountable. After inspection and acceptance, all districts and counties must replant the sections with low survival rate in autumn, and the city will not give subsidies. No matter what form of land, it is forbidden to interplant Gao Qian crops in the forest belt to ensure the planting effect.
(four) the establishment of management responsibility, consolidate the results of afforestation.
All districts, counties and towns should formulate practical management and protection measures and implement management and protection responsibilities in light of their own reality. In the future, where the local government is responsible for the land for road greening in counties, townships and villages, farmers can voluntarily leave the land, countries will emerge, individuals will contract for afforestation and management, and the income will be returned, and the policy of whoever benefits from afforestation will be implemented. We can also solve the project land by auction, contracting and anti-leasing. It is necessary to clarify the property rights and responsible persons, mobilize the enthusiasm of all parties to participate in the project construction, and consolidate the results of afforestation.
The third part of the project construction implementation plan
In order to further strengthen the ideological and moral construction of teachers and students in our school and promote the harmonious and healthy development of all our work,
According to the county party committee and the county government's "On in-depth implementation? Four virtues? "County-wide Promotion Project of Civic Moral Construction" and the spirit of "Decision on Strengthening Civic Moral Construction" issued on 19971February 15. [20XX]43, combined with the actual education in my hometown, this implementation plan is formulated.
I. Guiding ideology
Conscientiously implement the spirit of the XX Congress and the XX Plenary Session of the Communist Party of China (CPC), adhere to the guidance of Scientific Outlook on Development, take building the socialist core value system as the foundation, and strive to enhance the sense of honesty and responsibility. In the next few years, it will be implemented throughout the school. Four virtues project? , and constantly strengthen the social morality, professional ethics, family virtues and personal moral education of teachers and students. The Code of Professional Ethics for Primary and Secondary School Teachers and the Code of Practice for Primary and Secondary School Students are infiltrated into daily study and work life, and transformed into conscious actions to guide teachers and students to develop good moral literacy and behavior habits, thus providing solid ideological guarantee and spiritual support for the healthy, harmonious and sustainable development of our school.
Second, the activity target requirements:
Think of the next three years as? Moral construction promotion year? , based on the reality of hometown, widely carried out? Assist, sincerity, filial piety and benevolence? For the main content? Four virtues project? Build and strengthen the education of social morality, professional ethics, family virtues and personal morality of teachers and students in schools. By carrying out various forms of study, education and moral practice activities, we advocate a number of advanced models, and guide teachers and students to start from themselves, start from small things around them, learn from role models around them, and put? Love your job and care about students; Study hard and be rigorous; Be brave in innovation and forge ahead; Indifferent to fame and fortune, ambitious? The basic requirements of ""permeate into daily study, work and life, and are vigorously promoted? Love one's job, be honest and trustworthy, be filial to the old and love one's relatives, take pleasure in helping others and be brave? Civilized fashion, develop good moral quality and behavior habits, and promote the harmonious development of all work in the school.
Third, improve institutions.
For in-depth, solid and effective implementation? Four virtues project? , effectively implement the activities and achieve practical results. After research, it was decided to set up an activity leading group.
Team leader: Liu Xiangjun
Deputy Team Leaders: Tang Wenfa and Sun Xinze
Members:
Feng Shouliang Hao Guangmin Liu Yupo Gao Wenshen
Cui Jinchao Liu Cangzhu Hao Jijun Fan Chuanbo Duan Chuanqiang
All primary schools should set up corresponding leading groups.
Fourth, the implementation steps
According to the unified deployment and requirements of the superior, this activity is divided into four stages, which last for three years:
(1) learning mobilization stage (20XX 10 month)
1, hold a mobilization meeting, set up a leading body, formulate a work plan and sign it? Four virtues project? Personal responsibility certificate.
2. Organize to study the spirit of the superior documents and learn the relevant series of Chinese traditional virtues of benevolence and virtue. Concentrated study time is not less than 40 hours, and personal study notes are not less than 4000 words.
3. around? Four virtues? Learning content construction, writing experience, learning communication.
4. Organize the singing of "Song of Four Virtues" among the teachers and students of the whole school; Hanging propaganda slogans on campus; Distribute proposals to all teachers and students, and concentrate on publicity and reporting.
(2) Organization and implementation stage (from 20XX 165438+ 10 to 20XX February)
1. With what? Five ones? Strengthen the activities of building teachers' morality and style.
Carry out reading experience evaluation activities with the theme of love and responsibility, test the learning results, and let them gain something from reading, gain something from reading and make a difference from reading.
Organize a meeting? How to be a happy teacher? Keynote speech activities, find happiness around you and set an example of teachers' morality around you.
Further promote a theme activity. Namely. Be a happy teacher and live a happy life? Theme practice activities, through democratic appraisal, student parents' satisfaction evaluation, post publicity, teachers' public commitment, professional ethics lectures and psychological counseling activities, stimulate the sense of responsibility and mission of teaching and educating people, and create a positive and good teacher atmosphere.
Combined with the main line of school teaching, a series of teaching activities were carried out. Actively build a platform for teachers' self-display and development, help teachers improve their education and teaching level, promote professional growth and enhance their sense of professional accomplishment.
Hold a series of cultural and sports activities for faculty and staff. Care about the physical and mental health of the teaching staff, reflect the humanistic management feelings, organize the teaching staff to actively exercise during the big class, guide the teaching staff to constantly adjust their mentality, and ensure that the teaching staff devote themselves to education and teaching with abundant energy.
2. Carry out among students? Mingde's self-cultivation and love practice? A series of theme education activities.
Determine the theme and form of each month in combination with the moral education work in hometown schools? There is a theme every month, a focus every week, and content every day? The new situation of moral education. The theme of moral education every month is:
165438+ October Civilization and Politeness Month
(1) once? Four virtues? Education theme class meeting. Each class is designed with a variety of forms, lively content, easy to understand and interesting theme class meeting suitable for age characteristics, so that students can understand the content and implementation methods of the four virtues education. Four virtues project? The meaning of the activity.
(2) participation? Love proposition? Action, organize students to claim a tree, a piece of green space or a public facility in a school or community in their own names, and use rest days and holidays for voluntary maintenance and management.
(3) hold? Lei Feng spirit accompany me? A series of practical activities: let children start from the small things around them, bring a cup of tea to their parents on Sunday and holidays, wash their feet, cook a meal and make a small Thanksgiving gift; Use weekends or spare time to do it? Walking into the nursing home to take care of the elderly, I offer my love to the old teacher? Visit condolence activities.
(4) Combined with the National Safety Education Week, it will be launched in the last week of June 165438+ 10? Is it safe to be with me? 、
? Create a safe campus? Safety education activities.
65438+ February campus blooms with flowers of civilization.
(1) development? Environmental guardian? Action. Each class organizes special blackboard newspapers, actively publicizes environmental protection knowledge, advocates energy conservation and emission reduction, and low-carbon life, educates students to consciously protect the environment, save resources, beautify their hometown, and supervises and reports environmental damage.
(2) Each class organizes students to study "Daily Work and Rest" and "Daily Code of Conduct for Pupils" seriously, hold knowledge contests, integrate moral education into competition activities, and let students know their spiritual essence.
(3) implementation? I'll do it. I'll show it, okay? Activities. Organized? A song before class? 、? Read good books, sing good songs and be a good person? 、? Reading Chinese classics? Organize and watch civilized etiquette videos and other educational practice activities, and educate students on civilized etiquette and behavior habits, so that students can develop noble ideological quality and good moral sentiments.
20XX 1 month is the most glorious to work and the happiest to study.
(1) Carry out competitions to fold clothes, tie shoelaces and sew sandbags to educate students? Effort and glory, laziness and shame? .
(2) Hold a recommendation activity for reading good books, and on the basis of encouraging students to read more books, read good books, take notes and write their own experiences, recommend the good books they have read to their classmates.
(3) hold a parent meeting. Improve the system of parents' committees, actively broaden the channels of moral education, and form an educational network of communication and cooperation among schools, families and society.
2065438+March-April 2003 Appraisal and Commendation Month.
(1) for identification? Star civilization class? And then what? Star civilized students? Activities as the carrier, in the form of students' self-evaluation, mutual evaluation and teachers' evaluation, to carry out a phased summary of moral education.
(2) Organize students to take advantage of summer vacation to carry out colorful and moral education activities.
(III) Summary and improvement stage (March 20XX to April 20XX)
Conduct a self-examination and summary of the activities, find out the shortcomings, and formulate the objectives and tasks for the next step.
(4) Long-term mechanism stage (May-20XX)
Further improve? Four virtues project? Systematic, deepening? Four virtues project? Build, build? Four virtues project? Build a long-term mechanism and form a normalization of work.
Verb (abbreviation of verb) implementation requirements
(1) Strengthen organizational leadership. The school set up an activity leading group to clarify the job responsibilities. According to the implementation plan, strengthen measures, define objectives, and select the entry point and combination point to ensure the effective development of all work.
(2) Improve the working mechanism and strengthen the assessment management. According to the actual situation of the school, further improve the evaluation mechanism of teachers' morality and strictly implement the evaluation of teachers' morality? One vote veto? Strengthen supervision and inspection and standardize teachers' teaching behavior according to law.
(3) Strengthen typical cultivation. Pay attention to cultivating and excavating moral models and advanced figures. Choice? Students like it, colleagues admire it, and leaders are satisfied? Teachers and students set an example in a series of activities, set up advanced models and create a good working atmosphere.
Guess you like:
1. Implementation plan of engineering construction project
2.20 17 key project implementation plan.
3. Format of project implementation plan
4. Model essay on construction project implementation plan
5.20 17 project construction implementation plan
6. Model essay on project implementation plan