Chapter I General Provisions
Article 1 In order to meet the needs of railway construction, standardize the construction employment behavior, ensure the construction quality and safety of the second bid section of Dunge Railway in Gansu, and realize the construction goal of "Safe Dunge, High-quality Dunge and Harmonious Dunge", according to the Guiding Opinions of the Ministry of Railways on Actively Advocating the Scaffolding Team Management Mode (Railway Construction [2008] No.51) (Railway Construction [2009] No.60)
Article 2 The scaffolder team is the grass-roots construction operation team in the construction site of railway engineering construction projects, with the management and monitoring layer of the construction enterprises' managers, technicians and production backbones, and the workers of the labor service enterprises and other social personnel (collectively referred to as workers) who have signed labor contracts with the construction enterprises as the main construction personnel.
The third shelf team management mode can make full use of social labor resources, realize the organic connection and effective operation between the project department and the operation layer, and prevent the quality and safety assurance system of the construction site from becoming a mere formality, which is of great significance to ensure the engineering quality and construction safety.
Fourth, the scaffolding team management mode is adopted to organize the construction, which is conducive to the smooth realization of the project quality, safety and time limit for a project, and is a direct and effective construction production mode; It is beneficial for the project department to strengthen the management and control of the operation layer and ensure the effective operation of the quality and safety assurance system on the construction site; Is conducive to improving the technical quality of enterprise employees. Each shelf team must fully understand the superiority and importance of organizing construction by using the management mode of shelf team.
Article 5 According to the relevant regulations and requirements of the Ministry of Railways and the construction headquarters, strengthen the organization and leadership of the shelf team management, establish and improve the shelf team management system, and actively adopt the shelf team management mode to organize the construction.
Chapter II Organizational Structure and Division of Responsibilities
Article 6 In order to strengthen the organization and leadership of shelf team supervision, strengthen process control, and implement the responsibility of shelf team supervision, a leading group of shelf team is established:
Team leader: Song Pengcheng
Deputy leaders: Zhang Limin and Zhu Youjun.
Team members: Cao, Hao Yingshun, Hou Zhongliang and Li Linrunsuo, responsible for the formation, operation and management of the shelf team, and implementing various management systems and measures of the shelf team. Responsible for the daily work of the shelf team supervision.
Seventh according to the scale of the project and construction characteristics and other factors, unified production management, unified quality supervision. The main personnel of the shelving team established by the construction project department are fully equipped according to the specified requirements and brought into unified supervision. According to the needs of construction management, on the basis of meeting the basic personnel requirements of "nine members", the number of personnel in each position is appropriately increased to ensure the effective operation of the scaffolder team. The person in charge of each shelf team is responsible for organizing the implementation of various management systems and measures of the shelf team, and organizing construction and production.
Chapter III Construction of Management System
Article 8 According to the relevant requirements of the Ministry of Railways and the Construction Headquarters, and in accordance with the five goals of "standardization of management, standardization of operation, specialization of construction, automation of teams and groups, and marketization of behaviors", our supervision department will comprehensively carry out the construction of the shelf team system, formulate the shelf team management system and methods, improve the shelf team management system, and implement the shelf team management responsibility system. Standardizing management, clarifying authority and strengthening supervision of shelf team are conducive to improving the construction and management level of shelf team.
Ninth shelf team management to establish five categories of management system.
(A) shelf team management system
Supervise and urge the formulation of shelf team management methods and assessment methods, and establish and improve the shelf team management system; Establish a management system for the post responsibilities and qualifications of the main responsible personnel; Establish a system of personnel filling vacancies, which is mainly responsible for personnel adjustment, and fill vacancies in time as required.
(2) Internal management system
Including meeting formulation, attendance assessment, health management, political study and business training, office data management, etc.
(3) post management system
1. Pre-job professional training system
Pre-job professional training should be provided to the labor service workers, and they can only take up their posts after passing the training, and the training situation should be recorded in the education and training files.
2. Production safety education and training system
Establish and improve the safety production education and training system, strengthen the safety production education and training of laborers, and laborers who have not received safety production education and training may not take up their posts.
3. The system of holding certificates
Engaged in technical jobs, must obtain relevant professional qualification certificates before taking up their posts, hold relevant certificates, and supervise and inspect employees according to regulations.
4. Special operations personnel related certificates system
Personnel engaged in underground work, aerial work, bridging work, blasting work and other special operations must receive special safety operation training in accordance with relevant state regulations and obtain the qualification certificate for special operations before taking up their posts. Special operators working at the site must hold relevant certificates.
(4) Security system
1. Safety production management system
Establish and improve the safety management system and related systems and measures, and clarify the safety responsibilities of personnel at all levels.
2. security team Activity System
Post disclosure, post inspection and post record must be carried out every day, and problems found should be solved as soon as possible to avoid accidents.
3. Safety technical disclosure system
The technical director shall make a written technical disclosure to the foreman and team leader on the operation procedures and links of the project, and the written technical disclosure materials shall be classified and filed for future reference. Before the project construction, the foreman and team leader shall make safety technical disclosure to the shift operators to ensure the construction safety.
4. Operating procedures and written notice system for dangerous posts
Safety protective articles and safety protective clothing shall be provided to the labor operators, and the operating procedures of dangerous posts and the hazards of illegal operations shall be informed in writing.
5. Safety production inspection system
The safety officer of the shelf team must adhere to the daily patrol inspection system, and the inspection should be clear in purpose, specific in content and complete in record, so as to ensure the supervision and promotion of safety production. When discovering potential safety hazards and uncivilized behaviors and construction methods that violate civilized construction regulations, we should put forward rectification measures in time, and ask the team to carry out rectification. The rectification measures should be fixed by personnel, time and time, and reviewed in time.
6. Safety assessment and accountability system
It is necessary to establish a safety assessment system, implement a system of accountability, and implement the responsibility to people at all levels.
(5) Quality system
1. Quality management system
Establish and improve the quality management system and related systems and measures, and clarify the quality management responsibilities of personnel at all levels.
2. Technical disclosure system
Before the project construction, the director should sign and confirm the technical disclosure made by the Minister of Safety and Quality Department to the site supervisors step by step; During the construction of key working procedures, the supervisor must follow the shift; On-site data are filed for future reference.
3. Process inspection system
According to the current acceptance and construction specifications of the Ministry of Railways, do a good job in the process inspection of each working procedure. For concealed works, the next procedure can only be carried out after the acceptance of the supervision engineer.
4. Quality assessment and accountability system
It is necessary to establish a system of supervision and assessment, implement a system of accountability, and implement the responsibility to people at all levels.
1, on-site material supervision
1. 1. The shelf team is required to establish storage places to meet the construction needs.
1.2. The materials shall be accepted in time after entering the site, and the raw material inspection sheet shall be filled in, and the inspection and test shall be carried out according to the prescribed procedures; Materials that fail to pass the inspection and test shall be marked, stored separately, prohibited from being distributed and used, and disposed of according to the prescribed procedures.
1.3. Materials shall be stacked neatly, orderly and reasonably, and garbled and mixed are not allowed; Material identification shall indicate the material specification, model, origin, batch, representative quantity, status identification, etc. To meet the traceability requirements of materials; The environment of the material area should be clean, tidy, free of weeds and water.
1.4, storage of common materials:
1.4. 1, the sand and gravel yard should be sheltered and protected to achieve the purpose of shading, rainproof and dustproof. At the same time, it is equipped with stone washing machine and sand screen machine, which must be used, and it is forbidden to be used as decoration.
1.4.2, metal materials should be covered and padded when stored, and rust should be removed before use if there is rust.
2.4.3 Bagged cement and admixture should be stored in the warehouse, bulk cement should be stored in the cement tank, and admixture should be stored in the dark. It is forbidden to use expired materials.
2.4.4, inventory materials shall be subject to the first-in first-out system. Materials with shelf life requirements shall be distributed and used within a time limit, and those exceeding the shelf life shall be sampled and rechecked as required. For materials that should be accompanied by technical certificates, the sending personnel should give a copy of the technical certificates to the picking personnel.
2.4.5, supervision should take measures to ensure the safety and good quality of materials in stock, and take effective maintenance measures. The storage and transportation of dangerous goods and chemicals shall comply with the relevant provisions of the public security fire department.
2.4.6. The supervisor should strengthen the dynamic management of the construction materials of the outsourcing labor service team, keep abreast of the consumption of materials on site, and prohibit the outsourcing labor service team from carrying or selling construction materials or surplus materials on site, and it is strictly forbidden to "manage them by package".
2, field equipment management
2. 1. The construction unit shall verify, set up accounts and identify the construction machinery and equipment that comes into play, and report it to the supervision unit for inspection in time, and it can only be used after approval.
2.2, construction machinery and equipment in the process of use should always keep the performance quality and safety protection facilities in good condition. Meet the requirements of environmental protection and occupational health and safety protection.
2.3, strengthen the use, repair and maintenance of construction machinery and equipment, configure the necessary spare equipment and spare parts.
2.4, the installation and use of special equipment must comply with the provisions of the relevant national laws and regulations, and obtain the acceptance "license" issued by the competent department of the local government, equipment inspection report or other documents before use.