Engineering Construction 2022 Work Summary Part 1
First, the project and file overview:
Nanfu all the way to the road and bridge reconstruction project is located in the Jiangjin District Shuangfu New District, Jiujiang Avenue, Chongqing Bypass Highway, Jinma Avenue and other high-level Highway intersection in the new area; from the Chengdu-Chongqing Expressway Jiuma exit 2km, 10 minutes drive from Chongqing Inner Ring, only 35 minutes drive from Jiangbei Airport, the site has convenient transportation.
The standard width of the road is 24 meters, with four lanes in both directions, distributed as: 4 meters (sidewalk) + 16 meters (carriageway) + 4 meters (sidewalk).
Road grade: urban secondary arterial road Ⅱ
Road surface grade: high-grade pavement (asphalt concrete pavement) standard axle load: bzz-100 design life: 12 years design traffic level: intermediate
Construction unit: Chongqing Shuangfu Construction and Development Co. Quality Supervision: construction engineering quality supervision station of Jiangjin District, Chongqing
Design unit: China Huaxi Engineering Construction Design Co., Ltd Chongqing Branch Supervision Unit: Chongqing Fukang Engineering Construction Supervision Co. Construction Unit: Chongqing Deguan Construction and Installation Engineering Co.
The leadership of our company attaches great importance to the archive work, and has formulated a perfect archive management system, and the leadership of the company has visited the site many times to check and guide the archive work. In order to ensure the successful completion of the project file, the company specially equipped with the necessary office supplies and the project department of three computers, a printer, and from the file quality to train and pay attention to. In the data management project, the archive group prepared a data management plan, formulated a realistic and operable file management implementation rules, specifically formulated the project completion data control points.
Second, the formation of information:
According to the municipal engineering completion of the technical documentation material requirements, the archives group is responsible for the number of the project department's technical documents, registration, issuance, custody, and is responsible for the completion of the collection and accumulation of information.
Completion of the original information is formed as follows:
1, the project quality assessment information is formed by the project technical director, quality inspector.
2, test information from the site manager to extract the test pieces, supervision witnessed the sampling sent to the laboratory for testing in accordance with the relevant provisions of the laboratory according to the results of the test to form the information, return to the project department two copies of the original information. The summary table and rating table is formed by the internal data officer, the person in charge of technology.
3, raw material quality assurance certificate in the material into the field by the manufacturer to provide. The material clerk received in a timely manner to the archivist for the archives, the internal technician to summarize and organize.
4, the construction of technical delivery records formed by the project constructor, to the archivist archives.
5, hidden inspection data, construction records, formed by the constructor according to the actual situation on the site, to the supervisor, quality inspection station, design institute, geology and other relevant units after signing to the archivist.
6, as-built drawings by the constructor to provide first-hand on-site information, verified by the person in charge of technology by the Department of the as-built drawings to change.
This project in the process of collecting and organizing files, adhere to the principle of synchronization with the progress of the project, before the construction of the completion of the technical briefing records, earthwork construction records, concrete pouring records, steel hidden inspection, tensioning records, as well as the collection of material to prove the collection of information, organizing work. In the construction process, timely and truthfully fill in the construction records, hidden acceptance records and inspection records, in accordance with the specification requirements of the test, and the records are timely organized, all records are timely visa, accurate data, the content of the real. In the preparation of as-built drawings, to do in each sub-part of the completion of the project, in a timely manner, based on the hidden records and technical changes in the preparation of negotiation documents, so that the as-built drawings can be seen, feel, remember clearly, the preparation of accurate, to ensure that the project as-built drawings of the intrinsic quality of the accuracy, timeliness, systematic and true and effective. When collecting, organizing, summarizing and binding archival materials, we strictly follow the "Special Acceptance Measures for Chongqing Construction Project Archives" and the relevant requirements of Chongqing Municipal Urban Construction Archives, so as to make the archival materials complete, accurate, true and complete. Chongqing Shuangfu New District Nanfu all the way road and bridge renovation project *** formation of engineering files sets, each set of this, including documents and materials of this, as-built drawings of this, photo book. Hand over the A set, *** this, including text materials, as-built drawings, photo album; hand over the archives set, *** this, including text materials, as-built drawings, photo album; construction unit self-storage set, *** this, including text materials, as-built drawings, photo album.
Third, the project file features:
1, the project file group according to the actual situation of two people were organized and collected to ensure that the information and text data, specialists are responsible for the overall check, and basically complete the file finishing requirements of the task.
2, around the production of factual work style to form information, do not engage in "memoirs", do not engage in false information.
3, the archive group formed by the information written in standardized, block letters.
4, file formation with blue and black ink to write.
Fourth, the archives group work:
Several comrades in the archives group focus on unity and collaboration on a good article, often together to study the requirements of the archives organizing, to play their respective expertise to ensure the completion of the project in a timely manner, accurate file acceptance. Do not understand the relevant issues to the archives comrades to ask for advice, indeed, is not clear, then please come to guide the work.
Emphasize the importance of archival work, in the support of the project manager, the archives group boldly on the work of management, adhere to the file management requirements for processing, recognize the facts, so that the formation of information on the current situation of information management to have a further understanding.
This project in the construction process, the project department has repeatedly accepted the inspection of the higher management, archives have been the affirmation of the leadership, we strive to work in the future, so that our project archives continue to move towards a new height.
Fifth, self-assessment:
September 5, 20xx, the company's technical department of my site file inspection, archives group staff in the company after consulting the relevant personnel on the site file for self-assessment, the project archives can be basic to "qualified
Six, experience and summary
1, dealing with the construction workers, quality inspectors, materials supervisors, test and other relevant departments of the relationship, is the key to the file work can be successfully implemented. File management process must be in accordance with the principle of "cooperation, mutual assistance" to deal with the constructor, quality inspector and other data formers between the relationship.
2, in the professional and technical to have a high level in order to make others convinced, in order to establish the prestige of file management. First of all, to improve their skills, to the relevant departments for archive training, to do everything in the archive management in mind.
3, in the project a start should be strictly in accordance with the requirements of the archives and high-quality structural standards to organize, in order to reduce the construction process of some of the undesirable factors on the impact of archival work.
4, fully aware of the archives work on the project and the project value of the use of the role played by the archives, be sure to put a good archive management work.
Seven, the future work intends to:
1, from now on, the main focus on the optimization of archive management, through careful study, digesting the archives to organize the relevant content, and the owner, the archives exchange of views to achieve the purpose of improving their own capabilities.
2, the organization of the formation of relevant information personnel to study, through careful work, pay close attention to hidden works and processes handover acceptance work, grasp the material test work to participate in the construction program and the construction of technical delivery of the work, to ensure that the information in the next step of the project can be more on the next level.
VIII. Conclusion:
This project in the process of collecting and organizing the project files, the contractor and supervisory units and the competent authorities of the upper level of support, especially the city construction archives of the leaders and teachers have visited the scene many times to guide the work, we would like to express our heartfelt thanks!
Engineering Construction 2022 Work Summary Part 2
Time flies, the years like a shuttle, turn of the eye I to the unit has been working for six months. This half a year is an important part of my life journey, during the leadership of the training and help, colleagues care and support I gradually completed from the study of professional surveying and mapping engineering to the engineering section of the work content, as well as from the University of XX Highway Construction Corporation to work in this environment and role of the double change and adaptation. At the end of the year, I meditate on this half-year working life, and I have gained a lot. I now summarize my learning and work in the past six months as follows:
First, the work:
xx July, it is a great honor to come to the xx Highway Construction Corporation to work, and was assigned to the xx roadbed project thirteen standards of the engineering section. The engineering section is the leader of the company, mainly responsible for the management of the issued plans and measurement and other work, the engineering section is very exercise at the same time can also learn a lot of things. In these six months of study and work, I learned about the names of the various parts of the bridge, highway drawings of the part of the study, and mastered the relevant content of the internal work, as well as the completion of the data organization methods and rules. During this period, I learned a lot and summarized some shortcomings, I still need to work harder to learn the relevant knowledge, to go to the scene to understand more, in the field can learn more knowledge. So in the next year, I have to be not afraid of the wind and sun, have the opportunity to go to the scene to learn more. Consciously strengthen the study, to the theory of learning, to the professional knowledge of learning, to the side of the colleagues to learn, and gradually improve their own theoretical level and business capacity, to overcome the youthful anger, to be down-to-earth, to improve the work initiative, not afraid to do more work, not afraid to do the smallest thing, in the practice of the drop in the perfect to improve their own.
Second, the ideological aspect:
First, consciously strengthen the political theory study, improve the party spirit. The company's strong political learning atmosphere y infected me, I actively participate in the company's organization of various learning activities, and focus on self-study, serious study, and further improve their own theoretical level and political quality, and strengthened self-discipline conscientiousness. And wrote an application to join the party as well as thought reports, I hope I can join the ranks of the Chinese **** production party as soon as possible, I implore the company and the party's test. In the work, I am modest to ask colleagues, encountered problems and actively ask for advice, and can be a good solution to the problem. In the future, I have to learn a lot, so be persistent.
Three, xx year's work plan:
This year, I will be the main management of the completion of this aspect of the data, although they do not know much, and humbly ask for guidance to the leadership, and strive to do this aspect of the perfect. At the same time, in the engineering section to listen to the arrangements of the leadership, seriously complete the tasks assigned by the leadership, all pace with the organization.
The company's five than the implementation of the five. Very good, continue to carry out "than the progress, create an image of the project; than the quality, create a quality project; than the project management, create a clean project; than the safety production, create peace of mind project; than civilized construction, create a harmonious project.
The above is a summary of my work over the past six months, in the future, I will be down-to-earth, in the xx Highway Construction Corporation in this fertile ground to make a difference, for the xx Highway Construction Corporation to contribute their youth.
Engineering Construction 2022 Work Summary Part 3
I went to work in the company's project management department on December 10, xx through recruitment. From engineering construction units to engineering construction units, although my work position and role has changed a lot, and the "Zhejiang Province, the construction project budget quota" is also the first contact, but in the leadership of the concern and the help of colleagues, with their own professional foundation and work experience, coupled with hard work and study, and soon adapted to the working environment, and achieved better results. Now the work situation is briefly summarized as follows:
First, personal profile
September 1996-July 1999, in Hunan Urban Construction College of Higher Education in the Department of real estate to study engineering costing; July 1999-July xx, in the Ltd. is engaged in budgeting, contract management, bidding and other work; in October, xx, participated in and passed the national cost engineer qualification examination.
Second, the main work performance and achievements
1, strictly abide by the company's rules and regulations. At the beginning of the work, I carefully studied the "Wike outline", "real estate plate staff daily code of conduct", "basic management system", "job function description" and other rules and regulations, and will be in mind, always remind themselves to strictly abide by the company's rules and regulations, and safeguard the company's image. Such as insisting on going to work early every day to the company, cleaning the office health, to create a clean working environment for colleagues.
2, seriously study the Zhejiang Province budget preparation information. Although the principle of budgeting is the same, but "Zhejiang Province, construction and installation works quota" and my previous contact with more highway and railroad project quota is very different. Therefore, I first of all on the Zhejiang Province budgeting information for serious and systematic study, and adhere to the side of the work while learning, and soon mastered the essentials, has been able to independently complete the task given by the leadership; at the same time, I also use my spare time to learn to use the "Magic Calculator software" budgeting and "Luban software" to calculate the rebar, work efficiency has been greatly improved. In the future work, I will continue to explore and study, to do a more fine and perfect work.
3, Wike Essence Group Co., Ltd. Dunhuang Branch winding workshop and temporary project finalization audit work is progressing smoothly. Although the winding workshop and the temporary project has been completed for a long time, but the completion of the information is very incomplete, which gives the final account audit work has brought great difficulties. I took over this work, on the one hand, actively request the construction unit to improve the completion information, on the other hand, using the existing information in hand to calculate the number of projects, check the data. In order to accurately grasp the project situation, to ensure the accuracy of the calculation, I also deliberately to the scene to carefully check. Through my efforts, this work has made rapid progress, most of the information required for the audit of the final account of the project has been collected, winding workshop budget has been checked with the construction unit.
4, actively embarked on Huayan Street, Lot 5, commercial and residential buildings, civil audit work. From the leadership arrangements for me to be responsible for the project after the audit of the civil budget, I seize the time to familiarize myself with the construction drawings and related information, and many times to the construction site to understand the situation, so that he mastered in the shortest possible time the static and dynamic situation of the project. In order to better safeguard the interests of the company and take the initiative when finalizing the accounts, I advanced the calculation of the project volume to the present stage. After a period of intense and orderly work, I have completed the calculation of the quantity of the basement part of the project. In addition, I also carefully completed the progress payment budget for the two months of December XX and January XX and the audit of the engineering contact sheets that occurred in the early stage, of which the budget was reduced by 461,321,000 yuan in December XX, and 163,723,000 yuan in January XX, which was affirmed by the leadership of the department.
5, other aspects: ① actively put forward to the leadership of the rationalization proposals, such as cost control, data management; ② with colleagues to actively discuss cost control, contract management, data management and other content. Through the discussion not only enhance the friendship between colleagues, but also improve their own business capacity; ③ initiative to communicate with colleagues, enthusiasm to help others; ④ actively participate in the activities organized by the company, such as participating in the party to learn, the Chinese New Year gala performance.
Third, the direction of efforts
1, make full use of the advantages of passing the National Cost Engineer Licensing Examination and previous work experience, proactive contact with a variety of related businesses, improve their practical ability to make their own contribution to the company's brand building;
2, actively participate in self-learning Undergraduate exams, study professional technology, improve business skills and professional standards;
3, play a leading role in the party's role model, and strive to be advanced.
In short, three months, although I have made a little achievement, but there is still a gap from the leadership requirements. In the future, I will further strengthen the study, solid work, give full play to personal strengths, for the company to make a good contribution.
Engineering Construction 2022 Work Summary 4
Since graduation in 20xx I have been engaged in quality control work, quality control work is also considered to have formed a certain mode of work, 20xx May 6, the new challenge is standing in front of me, life is to be full of challenges, so that life can make us in the memories of the time! Not because of nothing and regret.
Time passes really fast, in the blink of an eye three months of time has passed in the life, in the three months I learned a lot of things, but also see their own shortcomings, now the three months of work as follows:
Longyu Coal Chemical Industry is in the construction of the second phase of the construction period according to the construction requirements of the site material supply can be divided into A (Longyu Coal Chemical Industry purchased substances) and B supply (construction unit to buy substances). (The company's business is to provide the best quality products and services to its customers.)
I. The process of A-supply material.
Engineering and Technology Department, the construction unit puts forward material demand plan equipment department for approval, according to the LiKu situation, pre-bidding and construction needs for approval (A supply or construction unit purchased) inquiry to make an estimate, in the 20th of each month reported to the Henan Longyu International Trade Co. (Self-purchase or purchase) selection of manufacturers, review qualifications, answer technical questions and standardize technical requirements to sign the shortlisted supplier recommendation form (department, finance, business management, supervision and management) to determine the time and place of bidding to notify the supplier and the Ministry of Management (the Ministry of Management is responsible for bidding the selection of the jury, the jury should be an odd number of jurors) jurors and suppliers to sign to the bidding meeting site, we should be the first to describe the subject matter and to clarify technical requirements Supplier clarification of technical questions and a quotation handed over to the monitoring (indicating the delivery time and payment methods) supplier second quotation voting (and then monitoring without permission of anyone shall not look at the quotation) approval of the tender results notify the winning supplier within 7 working days after the signing of the contract signed technical agreement signed contract (the winning supplier should pay the winning bidding conference fee) to place an order for the contract tracking the arrival of the goods and acceptance (planners, Custodian, engineers and technicians, inspectors and suppliers should be on site) invoices accounted for (the content of the invoices issued by the supplier should be consistent with the content of the contract signed) payment.
Notes:
1, the supplier's name must be written clearly and correctly;
2, technical issues should be harmonized before the tender;
3, before the tender must ask the supplier whether there is any unclear matters and whether it is possible to participate in a timely manner;
4, in the signing of the contract to check the substance of the project and the price, divided into the specifications to prevent delays in follow-up work. specifications to prevent delays in follow-up work.
2. B supply substances.
Construction unit according to the construction requirements of the self-purchase of substances is known as B supply, in order to control the quality of the project and the budget must be B supply material quality and price recognition. Recognition of quality and price need to construction units to provide the appropriate contract, invoices, price application form and material declaration form. Recognize the quality and price work should be divided into recognize the quality and price of the two parts, recognize the quality is the quality of the project inspection, recognize the price is the price of the materials used to verify the construction unit to see whether the amount declared in line with the actual market price, and whether in the budget range. Recognize the quality and price of work and self-procurement work link consistent, in the inquiry process to pay attention to avoid some suppliers to report blindly price impact recognition work.
Three, joint bidding.
Joint bidding is a construction unit organization owners to participate in a bidding mode, both sides can recommend suppliers, only bidding mode can slow down the owner's financial problems, but also reduce the construction unit and the owner of some unnecessary friction between the joint bidding contract signed by the supplier and the construction unit, but the owner is obliged to be responsible for the guarantee of funds in place, the joint tender is also a form of price recognition. Bidding is a form of price recognition, so the need for permanent coal company development planning department of minister Zhang to participate. The form of joint bidding is basically the same as their own bidding, and then joint bidding there is a point to note is that the owner of the jury must be more than the construction unit.
This is three months to do the main work, in the three months found themselves still lack of organization and coordination skills, which is the next key learning aspects. Supply work regardless of just buy things on the completion of the work, to learn how to buy to the material at a good price is the fundamental supply work. Supply work also need to keep abreast of the market price, keep abreast of the market dynamics, in their own hearts into a price system, a variety of material suppliers to form a unified system.
Supply work is the source of a company, but also relates to the company's ability to run a safe long cycle, so the supply work must avoid selfishness, have a fair and just heart.
Supply work is faced with suppliers every day, which is another indispensable part of the supply work. If the supply work is missing suppliers, supply work is equivalent to the lack of walking legs.
Engineering Construction 2022 Work Summary Part 5
The project is located in Fengxian Road, Affirmation Dam, which is a frame structure, with the function of an underground garage (83 parking spaces) in normal times, and the function of a second-class personnel shelter in wartime. The main body of the proposed project is one layer underground, and there is a mezzanine (dressing room) under the local square stage. Layer height 4, 5m, floor area 4137, 88. engineering grade for the second level, the design service life of the structure for 50 years, the structure of the safety level for the ii level, seismic defense for 6 degrees, garage fire classification for Ⅲ, fire resistance level for the first level, the main body of waterproofing level for the second level, the waterproofing level of the power station for the first level.
The project since the start of construction, the company's leaders attach great importance to archive work, the development of a perfect archive system, the archive data subdivided in place, comprehensive organization, to ensure that the archives and construction synchronization, true. In order to ensure the quality requirements of the archived materials, the company has specially configured computers, printers, copy and scan machines, paper cutters, binding machines, page numbering machines, digital photo / (camera) machine and other equipment and office supplies, so that the quality of the archives more standardized.
Project files in the collection and finishing process in strict accordance with national Chongqing local standards, in Wanzhou District, Chongqing City Construction Archives leadership of the project's strong support and help, in the owners, supervisors and construction leaders attach importance to this work, the construction process, material quality assurance information and test data integrity, all kinds of hidden information, construction records and a variety of functional test data is complete, and are in the construction of the project, the construction of the project, the construction of the project and the construction of the project. Complete information, and are in the owner, supervisor supervision with the progress of the project to fill out the signature formalities are complete, handwriting, content is complete, true. To synchronize the information and engineering, the formation of the project archived information has reached the provisions of file management and acceptance criteria requirements.
From the start of the project, the project's full-time data clerk in strict accordance with the acceptance criteria and archive requirements for the collection of engineering data. Finishing work, and strive to achieve data archiving standardization. After collecting and organizing, the information is reported as follows:
The project is now line into the archives *** sets. Transfer to the owner of the set of *** this, including textual materials, as-built drawings, *** Zhang, photo album, *** Zhang.
From the start of the project to completion, the formation of archival materials, collection and improvement. All have been the strong support of the higher authorities, without the guidance of the leadership, care and coordination, the difficulty of the archives work can be imagined, the organization of the files of this project has benefited us a lot, for the next project's archives have accumulated valuable experience wealth, which to the teachers and leaders to express the most sincere gratitude!
Engineering Construction 2022 Work Summary Part 6
Since I joined the work in xx in 20xx, I have participated in the construction of xx port development zone development zone through the eight road project, xx project, xx road project, xx west road project, xx east road project, xx project and other projects. Now in xx is responsible for the port area bt project construction data organization work, served as a trainee, data clerk, contract administrator and political workers and other positions.
During the tenure of construction technology section data clerk, I work meticulously and conscientiously. The main work is:
1, with the professional engineers to make a good strict check of engineering data. Because the engineering data is a true reflection of the results of the construction of the project, the data is formed in the process of engineering construction of various forms of information records, only with other professional engineers to complete and do a good job of this work.
2, responsible for the governance of construction data, and construction data collection, organization and archiving. Construction data is a true record of the construction process, is a systematic project. It involves supervision units, construction units, construction units, design units and other engineering units involved in the construction of substantive work, is the construction of scientific work, standardization, legalization of the signs.
3, the preparation of minutes.
4, in accordance with the data protocol will be included in the scope of the city's construction archives to receive the construction data moved xx construction archives. Only the early stages of each link are done, can be successfully transferred to the archives.
Our construction of the South Ring Road project is not only excellent quality, in appearance, more port area added a bright landscape; in the construction of the XX Road project, I actively cooperate with the leadership and technical staff, and construction units and supervision units to form a good working relationship to ensure that the data signature, transfer without error.
20xx x month in response to the xx city planning and construction bureau "to create a safe site activities" I was as "safe site leading group", and become one of the activities of the main person in charge, I am responsible for the establishment of the "creation of a safe site account", the project department and the company's leadership by the unanimous support for the creation of a safe site. By the project department and the company's leadership of unanimous praise, and in the acceptance of the higher inspection of a one-time pass, for the company has gained a positive impact, and since then is also responsible for the "one law, three cards" activities and "create a civilized construction site" activities such as work, in the work of the responsible, able to complete the tasks assigned by the leadership in a timely manner. In the work of conscientious and responsible, able to complete the tasks assigned by the leadership in a timely manner. In my participation or responsible for the construction data and completion data of the four projects, are timely, serious, high-quality completion, for the completion of the project on schedule, the final account laid a good foundation. For this reason, I have been repeatedly praised by the leadership of the project department and the leadership of the construction technology section.
In addition, in the process of construction, I am also responsible for the contract management of the project, the unit has a large number of labor contracts need to be re-signed, as well as the centralized management of migrant workers, so that I have learned a lot of knowledge. During the work period I continue to learn to improve their professional skills and practical experience, I hope I can do better in the future work.