Chishui City, 2008 village health room construction project to implement the implementation of the program to implement steps

(A) the preliminary preparatory work: March 21, 2008 - July 31

1, determine the construction plan: May 6, 2008 in conjunction with the actual report of the village health room construction plan.

2, site selection: June 30, 2008, led by the Municipal Health Bureau, the project is located in the township party committees, governments, township health centers and other relevant departments and village committees *** with the determination of the village health room site, the village health room must be built in the rural population is relatively centralized, easy access to the residential area, to facilitate the public close to the clinic. The land for construction is allocated by the local government without compensation, and the relevant formalities are completed in accordance with the regulations. Exemption from various construction fees for the construction of village health centers.

3, drawing design: the use of provincial unified design of standardized drawings, according to Chishui City, combined with Qianbei residential style, from which to choose a set of design options.

4, bidding: July 1, 2008 - July 31, civil engineering projects to implement the county (city) as a unit by regional section of the bidding bundle. Equipment projects will be purchased through unified bidding by Zunyi City.

5, the project legal person: the legal representative of the Municipal Health Bureau, and is the first person responsible for the implementation of the project.

(2) construction phase: August 1, 2008 - November 30 for the construction phase, the people's governments of the townships are responsible for the coordination of the construction project of the village health room in the township. Construction unit in accordance with the approved design documents and related documents, timely organization of survey, design, construction, supervision, and monthly on time to report the progress of the project. 2008 before November 30 must be completed pending acceptance.

(3) acceptance stage: December 1, 2008 - January 30, 2009 for the acceptance stage. After the completion of the civil engineering project, the construction unit by the completion of the acceptance report, by the engineering quality supervision department acceptance for the record. Municipal Health Bureau, Municipal Development and Reform Bureau, Municipal Finance Bureau to organize the relevant departments and experts to carry out a comprehensive acceptance of completion, and reported to the Zunyi Municipal Health Bureau, Development and Reform Commission, Finance Bureau for the record. After the completion and acceptance, the timely transfer of fixed assets and related information.

Equipment by Zunyi City bidding procurement, the City Health Bureau unified reception, acceptance, distribution to the project use unit. Township health centers unified establishment of asset files.