At present, the construction of various infrastructures and the introduction of projects in Dengshahe Lingang Industrial Zone are progressing smoothly.
Infrastructure construction:
1. Water purification plant
Accommodating an area of 100,000 square meters, with a total investment of 340 million yuan, the total daily water supply capacity of 150,000 tons. One of the project daily water supply of 50,000 tons, has been in December 15, 2007 started, is currently undergoing site formation and water supply and distribution pipeline line construction, to the end of March to complete the above project, the end of 2008 all completed and put into use.
2. The substation
occupies an area of 22,000 square meters, at present, is under construction design and expert review, by the end of March to complete the above work, by the end of 2008 all completed and put into use.
3. The main roads
are Jiangda Line, Hongji Road, Longgang Road and Special Steel Road, with a total mileage of about 25 kilometers, all of which will be completed and put into use by the end of the year.
4. Railway line
Railway line is the Northeast Special Steel Group relocation and renovation project supporting projects. Total length of about 20 kilometers, a total investment of 350 million yuan, at present, the project study has been completed, the Shenyang Railway Bureau has been approved, the preliminary design has been completed, the State Ministry of Railways permit has been issued, is being reviewed by experts and the line of retesting, construction will begin within the year.
5. Port
Port planning berths 13, a total investment of 1.6 billion yuan. One of the planning 5000 tons of berths 2, an investment of 520 million yuan. As of now, the project, planning has been completed, the expert review has passed, is carrying out port planning, preliminary research, environmental assessment of the use of sea areas and other work. During the year will invest 520 million yuan, started construction of the trestle and two 5,000-ton berths.
6. Centralized heat supply (steam)
Recently invested 80 million yuan to build two 75-ton peaking boiler, has now signed a letter of intent with Dalian Huixin Venture Capital Co., Ltd., the site selection has been completed, is under design, the construction of the year to start; the long-range preparations for the construction of thermoelectric power plant.
7. River governance
The governance project involves embankment engineering level for the I level, flood control standard of 100 years, a total planned investment of 138 million yuan. East and West Bank construction construction, the west bank project has begun, completed before the flood season this year, the east bank from June, to the end of 2008, the project was fully completed.
The progress of the two projects:
1. construction projects have begun:
(1) Northeast Special Steel Dalian environmental protection base relocation and renovation: covers an area of 3 square kilometers, with a total investment of 7.3 billion yuan. 29 March 2007 to start, in October 2008, part of the production line was completed and put into use, all completed and put into operation in 2009, is expected to reach production can be achieved output value of about 10 billion yuan, profit tax 1.4 billion yuan. It is expected to realize output value of about 10 billion yuan and profit tax of 1.4 billion yuan after reaching production.
(2) Air Liquide (Dalian) Co., Ltd: invested by one of the world's top 500 French Air Liquide Co., Ltd, covers an area of 22,000 square meters, with a total investment of 29.5 million U.S. dollars, registered capital of 12 million U.S. dollars, the processing scale of 82,000 cubic meters/hour. 18 October 2007, the construction began, and was completed and put into operation in October 2008, and it is estimated that the production can be It is expected to realize annual sales revenue of 100 million yuan and tax revenue of 10 million yuan.
2. Construction projects to be started:
(1) Dalian Daxiang Casting Co., Ltd: covers an area of 100,000 square meters, with a total investment of 250 million yuan, and is doing all the preparatory work before the start of construction.
(2) Dalian Xianzheng Pipe Industry Co., Ltd: covers an area of 240,000 square meters, with a total investment of 600 million yuan, is doing all the preparatory work before the start.
(3) Dalian Eco-life City: by the British Oscar Investment Management Company to invest in the construction of a total investment of about 1 billion euros, covering a total area of 3.14 square kilometers, mainly for hospitals, rehabilitation centers, training schools, homes for the elderly, tourism, vacation, leisure and recreation, etc., the preliminary site has been determined, is carrying out the feasibility study, preliminary design, and other preparatory work in preparation for the signing of the agreement, and then enter into specific work implementation.
(4) sewage treatment plant: the project adopts the BOT method for social operation, by the Dalian Dongda Environmental Group for actual operation. The overall scale of sewage treatment for 120,000 tons / day, a treatment scale of 20,000 tons / day, an investment of 0.36 billion yuan, covers an area of 30 acres. Are doing all the preparatory work before the start of construction.
3. In the talks about the project
(1) Lopuzi refractory materials company China factory: Lopuzi refractory materials company is registered in Poland, a listed company in Europe, intends to build a China factory in Dengshahe Lingang Industrial Zone, plans to invest a total of 25 million U.S. dollars, covers an area of 40,000 square meters.
(2) large diameter LSAW pipe production base: the project is invested by Tianjin Seamless Steel Pipe Factory to build a production base in Dengshahe Lingang Industrial Zone, with a planned area of 200,000 square meters and a planned investment of 800 million yuan.
(3) Heilongjiang Hengqiang Special Steel Co., Ltd. to build high-strength low relaxation ribbed tendon production project: the planning covers an area of 400,000 square meters, building area of 240,000 square meters, the project total investment of 1.161 billion yuan. After the project reaches production, the annual sales revenue of 2.0565 billion yuan, the total annual profit and tax 351.9 million yuan. One of the annual sales revenue of 688.5 million yuan, total profits and taxes of 137 million yuan.
(4) Steel Structure Project: Dalian Steel Structure Co., Ltd. specializes in large-scale complete sets of steel structure production equipment manufacturing enterprises. It is proposed to build a steel structure production base project with an annual output of 1.3 million tons in Dalian Dengshahe Lingang Industrial Zone, covering an area of 267,000 square meters and a building area of 180,000 square meters.
Three Economic Scale Situations:
The construction of the Lingang Industrial Zone started in 2005, and the infrastructure is initially equipped with the ability to undertake industrial projects to move in, and the industrial projects are in the construction period.