1, where the fall height of the reference plane 2 meters (including 2 meters), there is a possibility of falling from the height of the operation, known as work at height.
2, before working at height, must be carried out to analyze the danger point, the development of preventive measures. 3, before working at height, carefully check the safety protection facilities.
Such as checking the lifting gear is not safe and reliable, lifting machinery, braking, insurance and protection devices are not safe and reliable, found that the problem should be dealt with in a timely manner. 4, work at height should be set up safety fences and signs to stop the pedestrians, vehicles, to avoid falling objects.
5, when working at height, should always wear the helmet on the head, shall not be taken off. 6, when working at height, must use the safety belt, safety belt hooks or or rope should be hung on the strong and solid components or specialize in safety belts with the steel wire rope.
Stop hanging on the moving or unsound objects.
2. Working at height to pay attention to what safety matters
1, the hook or rope of the safety belt should be hung on a strong and solid components or wire rope designed for hanging the safety belt.
Prohibit hanging on the moving or unsound objects. 2, high work should always use the tool bag.
Larger tools should be tied to the rope in a solid component, not allowed to put, in order to prevent accidents from falling from a height. 3, in the work at height, in addition to the relevant personnel, do not allow others in the workplace below the line or stay, the workplace should be fenced or installed below other protective devices to prevent falling objects hurt.
If you work on the grille-type platform, in order to prevent the tools and equipment fall, should be paved with wooden planks. 4, tools and materials are not allowed to be thrown up and down, to be tied to the rope down or up to send, so as not to injure the staff below or destroy the scaffolding.
5, the upper and lower levels of work at the same time, the middle must be set up tight and solid protective partition, canopy or other isolation facilities, the staff must wear helmets.
3. What are the basic provisions of the safety measures for work at height
The basic provisions of the safety measures for work at height are as follows: (1) safety and technical measures for work at height and the required materials and equipment must be included in the project's construction design.
(2) unit project construction should be responsible for the project's safety and technology of work at height and the establishment of a corresponding responsibility system. Before the construction, should be carried out level by level safety technology education and briefing, the implementation of all safety technology measures and personal protective equipment, without the implementation of the construction shall not be carried out.
(3) safety signs, tools, instruments, electrical facilities and various equipment in the work at height must be checked before construction to confirm their integrity before being put into use. (4) Climbing and hanging work at height personnel and build safety facilities for work at height, must be qualified for professional technical training and professional examination, licensed to work, and must be .
Regular physical examination. (5) the construction of safety facilities for work at height, found defects and hidden danger, must be resolved in a timely manner; jeopardize personal safety, you must stop the operation.
(6) construction workplace objects that may fall, should be removed or fixed. The materials used in the high work should be stacked smoothly, so as not to hinder the passage and loading and unloading.
Tools should be put into the tool bag; work in the aisle, access panels and climbing gear, should be cleaned up at any time; dismantled objects and residual materials and waste should be cleaned up in a timely manner and transported away, and shall not be arbitrarily placed or thrown down. Passing objects are prohibited to throw.
(7) rainy days and snowy days for high work, must take reliable anti-skid, cold and frost measures. Where water, ice, frost, snow should be removed in a timely manner.
The towering buildings for high work, should be set up in advance to avoid lightning facilities. In the event of six or less strong winds, fog and other inclement weather, shall not be open-air climbing and overhead work.
After snowstorms and typhoons, the safety facilities for work at height should be checked one by one, and should be repaired and improved immediately if they are found to be loose, deformed, damaged or detached. (8) due to operational necessity, temporary removal or change of safety protection facilities, must be agreed by the construction manager, and take appropriate and reliable measures, the operation should be immediately restored.
(9) protective shed construction and demolition, should set up a warning area, and should be sent to specialists to monitor. It is strictly prohibited to dismantle the upper and lower at the same time.
(10) the main force of the safety facilities of work at height rod, mechanical calculations in accordance with the general structural mechanics formula, strength and deflection calculations in accordance with the current relevant norms, but the strength of the steel bending member of the calculation does not take into account the impact of plasticity, the structure should be in line with the current requirements of the corresponding norms.
4.
4. Communications engineering work at height, the main prevention of which safety
First, the prevention of personal injury, fall prevention, anti-skidding accidents, a winter construction, to strengthen labor protection, construction workers with gloves, wear rubber-soled shoes, increase anti-skidding measures, it is strictly prohibited to wear hard-soled shoes.
Second, into the construction site must wear a helmet, cold hat can not replace the helmet; third, open-air work to match the cold supplies, construction on the shelf to be careful to prevent "probe board" stepping on the air, high-altitude work to suspend the safety belt, at a height of more than one.5 meters on the bench, to be operated by a person to guardianship; fourth, the height of the operating personnel must wear slip-resistant shoes, protective gloves, and increase slip measures, strictly prohibit wearing hard-soled shoes. Must wear non-slip shoes, protective gloves and other anti-slip, anti-freezing measures, must fasten the safety belt; 5, four or more gusts of wind prohibit the tower crane installation, jacking operations, land level gusts of wind prohibit lifting operations and work at height; land, in the negative temperature of binding, lifting steel components with steel cables and components in direct contact, should be set up non-slip spacer pads. Check the lifting wire rope has no damage, U-type card is locked, hook insurance is effective; paint, because of the winter material brittle, easy to slip, so lifting heavy tonnage of goods tools should be left with a greater safety factor to fully ensure safety; bar, encountered in the rain and snow and other inclement weather, we must promptly remove the construction site of the water, snow, rain and snow and gusty weather is strictly prohibited to force the organization of the construction.
Second, fire prevention, anti-poisoning accidents a, to prevent fire, fire facilities and equipment should be complete, intact and can be used, the engine room (base station) shall not be stacked flammable and explosive substances; second, the safety officer should be regularly on the construction site of the power supply, fire prevention inspections, to prevent communications, fire accidents and theft of the matter; third, it is strictly prohibited to move the open fire in the site to warm up, especially in the construction site, once found, will be heavily fined; fourth, in the lower people under the people's power, the fire will be the first time, the construction site, the fire will be the second time, the fire will be the second time. Heavy penalties; Fourth, in the manhole operation should be done before "a pass, a check": (a) in the manhole operation should be before and after the manhole operation area manhole cover open, the first to do the ventilation process. (B) check the manhole for poisonous and harmful gases, to ensure the safety of the well.
5, in the manhole operation must do "a wear, a look, two are not allowed, three prohibited": (a) the operator should wear a good helmet, wear waterproof pants and rubber boots. (B) outside the well (on) should be guarded.
(3) are not allowed to start the blowtorch in the well; not allowed to smoke in the well. (D) prohibit non-operators surrounded; prohibited in the manhole with flammable substances; strictly prohibit flammable substances to clean the cable (gasoline, alcohol, toluene, etc.).
Third, the prevention of China's network security accidents First, the construction of the engine room is strictly prohibited the use of high heat lamps (such as sun lamps, etc.) to do temporary lighting, is strictly prohibited the use of electric water heaters, electric stoves and other non-construction electric heating appliances; Second, the winter construction of the temperature is low, the construction of joints of construction workers are not flexible, more clothing, inconvenient to move, installing equipment, arming the cables, you should pay attention to the equipment and the current China's security to put an end to the construction caused by the current China's Business interruption accidents; 5, optical (electric) cable cutting, relocation or dismantling of the old before, must develop a detailed cutting, relocation or dismantling of the old program, step by step, a thorough analysis, a careful survey of the site resources and approved cutting, relocation or dismantling of the old information, cutting, relocation or dismantling of the old program in the cutting, relocation or dismantling of the old program, step by step and the way (including personnel, production of instrumentation, cold-proofing, frost protection, wind and other auxiliary tools) to determine and approve, in the various Participating units of technicians (administrators and above) to re-verify the site, by the maintenance of supervisory technicians stationed at the site under the command of the implementation of the field, in order to avoid cutting and connecting errors, interruptions in the business or mistakenly dismantled and other communication accidents; land, in the city, the town for the pipeline fiber optic (electric) cable construction requires that each wellhead should be placed on the safety sign, and need to leave someone to keep guard, pay attention to the vehicles coming and going, a single disk of fiber optic (electric) cable Longer length, manual application requires more workers, in the construction of the complex road surface must be strictly organized, close cooperation, equipped with good communication tools (such as wireless walkie-talkies, speakers, etc.) so that the construction workers move in unison to protect personal safety and optical (electric) cable safety; paint, in the highway side of the construction, as much as possible to set up more safety signage and slogans, will be signage with reflective tape strung together, the urban areas Night construction also need to set up anti-fog lights to show the police, and arrange personnel to cooperate with the traffic department to divert traffic; bar, steel pipe welding should be carried out before the test welding, test welding qualified before formal welding, butt welding steel pipe, in order to prevent the temperature difference is too large, affecting the quality of welding, welded joints should be taken to protect the joints, snow should be covered with the appropriate items, welded joints not cooled is strictly prohibited from touching the snow and ice; 9, to strengthen the quality of construction monitoring, the joints shall not be transverse cracks. Joints shall not have transverse cracks, when there is a joint does not meet the requirements, the batch of joints should be inspected, out of substandard products, rewelded, and then the second acceptance, welding in the wind-blocking structure within the construction, when the temperature is lower than -20 degrees Celsius, no longer continue to construction. Fourth, the prevention of traffic safety accidents a, strengthen the maintenance of the project with the vehicle maintenance, maintenance, to prevent accidents due to vehicle failure; second, strictly prohibit drunk driving, driving without a license, fatigue driving; third, in case of severe snow and ice, the vehicle should be kept in the distance, to prevent the occurrence of tailgate accidents.
V. Winter heating and fire prevention I. Winter construction dormitory heating using coal should prevent accommodation construction personnel carbon monoxide poisoning, the dormitory should ensure adequate ventilation; each dormitory according to the size of the room to set the ventilation funnel, ventilation funnel size: length not less than 50cm, the width of the lower mouth is not less than three 0cm, the width of the upper mouth is not less than five centimeters, set up the ventilation funnel at least not less than three per room. II. Daily lights out before setting up a person to seal the fire, coal-fired heating facilities are strictly prohibited open mouth, the stove plate, stove cover should be fastened tightly; such as the stove plate, stove cover can not be completely fastened to cover tightly, it should be clay mud will be wiped tightly to prevent gas leakage.
Third. Heating facilities smoke pipe installation, each section of the pipeline should be installed in the direction of the medium flow, the interface and sealed with tape; smoke pipe outlet tan out the eaves of the house shall not be less than 50cm, the riser shall not be less than two.0m, the horizontal pipe from the roof of the house shall not be less than 50cm, and its direction shall not be towards the northeast of the winter monsoon blowing. iv. Smoke exhaust pipe shall not be drying clothes and other flammable items above, heating facilities shall not be stacked near the flammable, explosive, volatile toxic substances.
5. Seal the fire when clearing out the burning coal is not burned out should be cleaned out of the outdoors, and with water will be unburned burning coal extinguished. Lu. Safety education to put an end to scalding, gas poisoning and other events, and the occurrence of emergencies medical rescue, tight China processing education.
Lac. Dormitories, offices, warehouses are strictly prohibited to connect and pull electric blankets, electric stoves and other heating facilities; moreover, tungsten iodine lamps are not permitted to be used indoors, on-site heating.
5. How to use mobile ladders for high work
should be: ① should be inspected before use, usually a person responsible for the care, maintenance and repair.
② ladder before use, must be placed firmly, and the ground angle of 60 ° ~ 70 ° degrees appropriate, the top of the ladder should be with the building, building secure. (iii) When the ladder is used on a wooden floor, the corners of the ladder should be equipped with metal anti-slip devices. When the ladder is used on a concrete floor, the corners of the ladder should be equipped with rubber-coated fiber anti-slip pads, and the ladder should be supported by a person if necessary.
④ It is strictly prohibited for two persons to stand on the same ladder at the same time to carry out work. The operator shall not stand at the top of the ladder, and shall not be less than four steps away from the top of the ladder for leaning ladder, and shall not be less than two steps away from the top of the ladder for herringbone ladder. The leaning ladder and the ladder should be fixed by ropes, and the fixed connection ropes should be inspected and qualified before working, and should not be replaced by other objects such as wires.
⑤ It is forbidden to move the ladder when there are people on it. (6) When the ladder is used in the vicinity of the rotating machine, temporary protective isolation facilities should be installed between the ladder and the rotating part of the machine.
6. What are the contents of safety education for workers working at height
(1) Workers working at height must be qualified after physical examination before construction work;
(2) Work at height must wear a safety belt, non-slip shoes, hanging hooks, and safety barriers and safety nets, and other protective facilities;
(3) Avoid single-handed operation when the conditions of work at height are poor;
(4) Avoid the use of a single-handed operation when the conditions are poor;
(5) Avoid the use of a single-handed operation when the conditions are poor. Single person operating alone;
(4) When working at height, construction tools and materials should be protected to avoid falling, and it is strictly prohibited to throw waste down below
(5) When erecting the electric cradle, it is necessary to unify the direction and coordination of the operation, and it is strictly prohibited to use the fittings that do not meet the requirements of the material, specifications and defects;
(6) When dismantling the scaffolding, the scaffolding should be dismantled according to the reverse order of erection Demolition;
(7) It is strictly prohibited for operators to use ropes and cranes as ladders up and down, and it is strictly prohibited to work on unfixed scaffolding;
(8) When carrying out work at height at night, adequate lighting equipment is provided, and there are collapsed and hollow areas to be equipped with obvious signs;