Personnel: Currently, there are packaging technicians **** 9 people, 5 people on the day shift, 4 people on the night shift for the distribution of personnel there are two people on the day shift to arrange for the state of the new equipment to be verified
Plan: Packaging plans to open 14 lines, the equipment has been debugged basically, and is waiting for the printer to be ready. Equipment can be handed over to the online completion. Follow-up for the Changan sent to Chongqing, the state of the equipment to confirm, build the production line spare pull line
Verification process:
1 state to confirm the structure of the equipment: whether the appearance of the damage, the moving parts of the electrical machinery is missing, can be normally energized
Spare parts: to confirm that the perishable spare parts are in stock, the safety of the stock status. Missing emergency report
Suppliers to confirm: who is the equipment manufacturer, personnel are in place, whether the ability to be reliable
Whether applicable: whether the equipment and the product being produced to match, can not be used in a timely manner upward feedback
2. Run to confirm the
equipment operating parameters: equipment parameters can be adjusted to the production line to normal down the machine, can not be, to confirm that the equipment Mechanical limitations or software does not work, timely feedback to change
Performance confirmation: whether the equipment can run stably after debugging, collection of abnormalities in the process of running, analyze the reasons for the anomaly, put forward a solution, a time to do the maintenance of the maintenance: on-line before the maintenance of the equipment, the operating mechanism, the screw guide movement mechanism, the cylinder to add lubricating grease lubricating oil, terminal row of equipment, internal cleaning and dust.
3. Installation confirmation
Confirmation of the on-line location, tracking the status of the on-line, collect the data of the test run, correct the equipment.
4. Reporting and registration
Check the asset code of the registered equipment, whether it is missing, and report on line in time