Ministry of Electrical and Mechanical Services capital projects (engineering) completion inspection and acceptance of the implementation rules

Chapter I General Provisions Article 1 for the completion of capital projects (engineering) acceptance, so that it is in accordance with the procedures, plans, steps, according to the State Planning Commission, "construction projects (engineering) acceptance of the completion of the construction of construction [1990] No. 1215, combined with the specific circumstances of the electromechanical industry, especially the development of capital projects (engineering) acceptance of the completion of the implementation of the rules (hereinafter referred to as the rules). Article II of the capital construction project (project) completed according to the design requirements, with the commissioning, use conditions, for the completion of the acceptance, is the construction project into production or use of the logo. Acceptance is a comprehensive assessment of the results of the capital construction, test the design and quality of the project, to promote the timely commissioning of the construction project, to play the benefits of investment, summing up the construction experience have an important role. Article III acceptance of the completion of the scope. Where the new construction, expansion, alteration, relocation of the capital construction project (project), according to the approved design documents provided by the content of the completion, with the conditions for production or use, in line with the acceptance criteria, must be organized in a timely manner acceptance, delivery of production or use of the department, while handling the transfer of fixed assets. Article 4 Basis of Completion and Acceptance

(1) Feasibility study report, preliminary design or implementation plan approved by the higher competent department (company);

(2) Relevant documents such as change of design, adjustment of budget estimates, etc. approved by the higher competent department (company) on successive occasions;

(3) Construction drawings, technical specifications of the equipments and relevant technical documents;

(4) (d) construction technical acceptance specifications, regulations, quality standards and relevant regulations on environmental protection, occupational safety and health, fire protection, energy conservation, earthquake resistance, etc. issued by the state and the central competent authorities of various industries;

(e) projects that introduce technology or imported equipment from abroad, as well as Sino-foreign joint-venture construction projects, should also be accepted in accordance with the signed contract and design documents and other information provided by the foreign country. Article V Completion and Acceptance Standards

Completion and acceptance of a capital project (project) for production or use shall meet the following standards:

(1) the main project and its corresponding auxiliary utilities, which are required by the design documents of the capital project (project) to form the production capacity or to realize the benefits of its full use, have been built in accordance with the design requirements to satisfy the production;

(2) the main works within the design shall be completed in accordance with the design requirements of the capital project (project) to meet the requirements of the capital project (project). p>(b) the design of environmental protection, occupational safety and health, fire safety facilities, etc., have been completed at the same time as the main project according to the design requirements;

(c) the main process equipment and supporting facilities, qualified by the linkage of the load test, the formation of production capacity, and normal production of qualified products stipulated in the design documents;

(d) the production of preparations for the initial commissioning or the hospitals, institutions, schools, scientific research, teaching needs;

(d) production preparations can adapt to the initial commissioning or hospitals, institutions, schools, etc., and can meet the needs of production. Scientific research, teaching needs;

(e) the necessary living facilities have been built according to the design requirements. Article 6 Some construction projects meet the requirements of the completion and acceptance criteria, but only a few non-major equipment or engineering according to the design of the content has not been fully built, but does not affect the normal use of the initial production, should also be organized for acceptance. The remaining problems should be approved according to the provisions of the design, within the planned scale of investment, acceptance of a finalization of the tailing content, quantity, investment (including sources of funding), by the investment unit in charge of arranging for the annual closing project plan, deadline for completion.

For the production of preparatory work temporarily difficult to solve the problem, such as the production of special raw materials, energy or production of liquidity, etc., acceptance of the commissioning of the higher authorities continue to assist in unblocking the channels as soon as possible to implement. Article VII of the construction process, the construction unit to grasp the single project put into operation and part of the construction project put into operation. Where the design content of a single project, with independent production or play the benefits of the project, in line with the completion and acceptance criteria, we must handle the acceptance of a single project, delivery of production or use, the transfer of fixed assets; for the construction of a phased construction, phased benefit of the conditions of the construction project, part of the completion of its completion, as long as the corresponding auxiliary facilities are in line with the production of qualified products with the conditions, can be normal production, the enterprise's Capital construction departments and production departments should be organized in stages and batches of intermediate acceptance, delivery of production, transfer of fixed assets. The new production capacity shall be calculated according to the regulations in planning and statistics. Article 8 Some construction projects and individual projects, which have already formed part of the production capacity or have actually been used in production, and cannot be renewed according to the original design scale in the near future, can be scaled down and reported to the competent department (company) for approval, and then the completed projects and equipments shall be inspected and accepted, and delivered for use and handed over to the fixed assets. Article IX by the infrastructure, technical transformation of the two parts of the investment in construction projects, based on the acceptance criteria can be an overall acceptance, the preparation of acceptance of the summary report, its schedule according to the infrastructure, technical transformation of the different requirements to fill out or infrastructure, technical transformation of the organization of acceptance, according to their respective requirements. Article 10 large and medium-sized capital projects, in the formal acceptance before the need for pre-acceptance, verification of construction projects with acceptance conditions and problems, especially the completion of the relevant "three simultaneous" facilities and their effects, do not have the conditions for acceptance of the project and the existence of problems, after a period of time for rectification, so that the problem is basically resolved, and then For formal acceptance procedures.

Pre-acceptance work shall be carried out by the local competent department (company) organizing the relevant units, and the pre-acceptance report signed by the representatives of the relevant parties shall be formed after the pre-acceptance. Article XI of the organization of the completion and acceptance. According to the provisions of the State Planning Commission Planning and Construction [1990] No. 1215, large and medium-sized capital construction projects (works), by the State Planning Commission or the State Planning Commission entrusted the project authorities, the local authorities to organize acceptance. Small capital construction projects (works), by the project (works) competent departments or local authorities to organize acceptance.

The local planning (economic) commission, urban construction and planning, banking, environmental protection, occupational safety and health, fire and other relevant departments to participate in the acceptance committee (group). Construction units, takeover units, construction units, survey and design units to participate in the acceptance work.

Small capital projects with relatively simple content, the acceptance of the work procedures, can be simplified.