Conference report materials
Part I: Report materials of the first on-site meeting of S324 South Ring Bridge Project on Lianyungang trunk highway.
Reporting materials
(First on-site meeting)
Nanjing Dongfang Road and Bridge Engineering Co., Ltd. South Ring Bridge Project Manager Department of Provincial Highway 324 20 12 1 1 month 22nd
Report materials of the first site meeting
Our department entered the market in early July. Through the efforts of the project department and the concern of leaders at all levels, our department has basically completed the construction of the project department. Now, the work of the South Ring Bridge Project of Provincial Highway 324 will be reported to the headquarters and the director's office as follows.
I. Overview of the Project
Project name: South Ring Bridge Project of Provincial Highway 324. Project cost:1207,500 yuan.
Project scale: total length 1.3km (K57+000-K58+300), in which the bridge is 826.48m long and the construction period is 18 months, from July 20 12 to July 20 13.
The superstructure of the main bridge is a (55+90+55)m prestressed concrete continuous box girder with variable height, with a single box and two rooms. The bottom width of the box is12.5m, the cantilever on both sides is 3.0m long, and the total width is18.5m. ..
(2) substructure
The main pier of the main bridge is a solid wall pier, with a wall thickness of 2.5m, a width of 12.5m and a height of 7.563m The size of the cap is 14.6×9.6×3m, and the chamfer is 3×2m to avoid encroaching on the navigation clearance. 3 rows10 Ф1.6m bored pile group.
2. Upper structure of approach bridge
The approach bridge is 20m partially prestressed hollow slab beam, simply supported structure and continuous bridge deck. 3. Approach bridge substructure
Four-column pier, Ф1.1m pier, Ф1.3m bored pile foundation. I-shaped abutment adopts Ф1.3m bored pile.
Second, the construction deployment
For the convenience of management, according to the actual situation, construction period and engineering quantity of this contract section, * * * arranges six construction teams, namely, two pile foundation construction teams, 1 old bridge demolition team, 1 approach bridge construction team, 1 main bridge construction team and 1 road construction team, and each construction team is fully equipped according to the professional type of work. Implement dynamic management, establish the system of survival of the fittest and incentive mechanism, so that the construction team will always maintain high quality and strong combat effectiveness, and ensure the efficient and high-quality completion of contract projects. Organization chart of project management department
Third, the overall progress
The whole project is divided into three stages. The first stage is the construction preparation stage:
Main operation contents: advance equipment entry; Land requisition and demolition; Leveling the construction site; Erection of temporary electricity; Construction of production, office and living facilities; Building a central laboratory; Preparations for purchasing, inspecting and testing the first batch of raw materials; Complete technical preparation and site retest.
The second stage of the main project construction stage:
Main work contents: bridge foundation, pier and abutment fabrication and installation, precast beam and slab, system transformation and bridge deck system construction; Subgrade, retaining wall, waterproof and drainage construction, culvert construction, etc.
The third stage completion acceptance stage:
Main work contents: Complete the self-inspection, repair and inspection of subgrade, bridge, culvert, retaining wall and drainage works.
Fourth, the overall goal
On the basis of fully understanding the requirements of bidding documents, construction contents and construction environment, and according to the construction management ability of our company, the overall construction objectives of this project are determined as follows:
1, construction period target
Part II: Report on the regular meeting of construction projects: the new construction of Changfeng Pump Gate in Yinzhou District, Ningbo City.
(water conservancy)
Remittance information
Preparation: review: approval:
Ningbo Yinzhou District Changfeng Pump Sluice New Project (Water Conservancy) Projects Department
Zhejiang Weihai Construction Group Zhoushan Co., Ltd. 20 15 years1February 29
catalogue
I. Overview of the project. Overview of hydrometeorology
Three. This month, the visualization progress (crossing chart) of the main quantities is completed. Four. The schedule for next month.
Verb (abbreviation of verb) is the input of main equipment, personnel and materials. Summary of engineering quality inspection. Safe and civilized construction
I. Overview of the Project
This project is a new project of Changfeng water pump gate in Yinzhou District, Ningbo City. The design gate has a total clear width of 4m, * *1hole, and the pump house has ***2 holes, with a single clear width of 3.5m and a pump station flow of 6.6m/s; The total construction area of pump lock room, installation room, duty room, power distribution room and control room is 498 square meters. The newly-built planned river course upstream is160m long and 20m wide, and the greening bandwidth on both sides is 20m. Located between Zhangbei Road (Planning Road) and Guangde Hubei Road, it dredges the river under Guangde Hubei Road Bridge. The design grade of Changfeng pump gate is Grade II, and the design grade of upstream channel is Grade IV.
Term of the contract: start date, year, month, and year. Construction unit, survey unit, design unit, supervision unit, construction unit, quality supervision unit and project management objectives:
Quality management goal: civilized construction goal: civilized project.
Safety management goal: put an end to major safety accidents and minor injuries.
Second, complete the image progress of major quantities
Third, the schedule for next month
3. Strive for the completion acceptance before April 1, 20 16.
Four. Input of major equipment, personnel and materials
1, investment in machinery and equipment
Article 3: Report materials for handover acceptance of the fourth bid section of Fuzhou Expressway pavement.
I. Overview of the Project
Fuyang-Expressway starts from Liu, Lixin County, Bozhou City, passes through Yingquan District, yingdong district, Yingzhou District, Funan District and Yingshang County of Fuyang City, and ends at G 105, Fengjing Town, Huoqiu County, Lu 'an City.
Our company won the bid to build the fourth contract section, with the starting and ending pile numbers of K62+3 14 ~ K83+570, including Zhou Ji Interchange (K82+460 ~ K83+570), with a total length of 2 1.256 km. There are different degrees of lime improving soil, drainage, protection and structures along the subgrade. The main structural forms of pavement are as follows: the subbase adopts 20cm thick low-dose cement stabilized macadam; The base adopts 38 cm thick cement stabilized macadam; The asphalt surface course adopts SBS modified AC- 13+6cm thick SBS modified AC-20+8cm thick AC-25. The main projects include: subgrade earthwork construction, low-dose cement stabilized macadam subbase, cement stabilized macadam subbase and interlayer spreading cement slurry, common emulsified asphalt seal coat construction, common asphalt concrete lower layer, (SBS) modified asphalt concrete middle and upper layer, and modified asphalt spreading interlayer bonding oil; And related ancillary works: median, shoulder hardening, slope protection, drainage, defect maintenance, road reconstruction and ditch reconstruction, fence construction, etc.
Second, the completion of the tender contract
(a) the main quantities completed
Subgrade filling earthwork is 267202m3, precast C20 trapezoidal longitudinal drainage ditch is 2 1450m, M7.5 mortar rubble is 2094 1 m3, precast C20 concrete is 96 1 m3, 20cm low-dose water-stabilized macadam subbase is 295,332m2, 18cm cement stabilized. 19cm cement stabilized macadam base course is 533536m2, prime coat is 344375m2, seal coat is 345725m2, bonding coat is 876386m2, coarse-grained asphalt concrete base course with 8 cm thickness is 335659m2, modified asphalt concrete intermediate course with 6 cm is 541209m2, and modified asphalt concrete surface course with c25,4cm is 546,550.
Shoulder C20 concrete 298 1m3, C30 concrete cast-in-place structural slab 1746m3 steel handrail 9799m, reworked steel handrail 6099m. (ii) Completion of the contract
The commencement date of our bidding is April 2009 1 day, the completion date stipulated in the contract is May 3, 20651day, and the contract duration is 14 months. The actual completion date of this project is March1year in May, and the actual construction period is 14 months.
In the process of construction, the project department carefully organizes the decomposition according to the overall plan, formulates the annual plan and decomposes it into quarters, months, ten days, weeks and days. At the same time, according to the actual construction situation, the plan was adjusted, with safety and quality as the core and progress as the goal, and the construction climax began in September 2009. Especially under the guidance and strong support of the project office, the director office, the supervision team and the leaders at all levels of the local government, various problems and local interference were overcome and the construction task was completed on schedule.
(iii) Execution of the contract
According to the contract requirements, part of the project will be put into mechanical equipment, equipped with test instruments, and the construction progress plan and material procurement plan will be formulated, and the construction will be carried out after a series of construction organizations are completed. We have always strictly implemented the terms of the contract with the owner. In the process of construction, the general and special terms of the contract are strictly followed, and a perfect quality assurance system is established. The project acceptance results meet the requirements of the contract technical specifications. In accordance with the requirements of the contract, strengthen the quality awareness management and safety education of employees, and formulate corresponding quality management systems and safety management systems. There are no quality accidents and safety accidents on the construction site.
Third, the construction organization and management
(a) Project organization and staffing
In order to ensure the normal work of the project, the project department consists of seven functional departments: engineering department, laboratory, operation department, machinery department, ministry of materials and equipment, finance department and comprehensive office.
The management department and laboratory are located on the right side of K82+600 route, about 1 km away from the subgrade, and rented in Fengjing Town. The centralized mixing station is located on the right side of K82+000 route.
200 meters; The prefabrication yard is located on the left side of K78+200 subgrade. In order to ensure the smooth progress of the construction task, 1 water-stabilized asphalt mixing station, 1 asphalt mixing station, 30 transport vehicles, 5 auxiliary engineering construction teams, 3 earthwork teams and 1 water-stabilized asphalt construction teams are set up, and the project department will organize, coordinate and direct the construction of the whole line.
(2) Material organization
The limestone for the water-stabilized base in my bid section is crushed stone produced by Nantong Road and Bridge and Anhui Hefei Shi Lei Stone Co., Ltd., and the limestone for the asphalt surface is produced by Anhui Hefei Shi Lei Stone Co., Ltd., and the stone factory processes 6,000 tons of crushed limestone every day, which can meet the construction needs. The basalt used in the upper layer is crushed stone produced by Shucheng Tongda quarry, and its adhesion to asphalt reaches Grade 5. All kinds of materials are stored in different grades and categories, and the raw materials are not confused, which ensures that the raw materials do not vary.
Machine-made sand: Limestone aggregate produced by Anhui Hefei Shi Lei Stone Co., Ltd. is used for the limestone machine-made sand for asphalt pavement. The particle size of the crushed stone used for processing the machine-made sand is fixed from beginning to end, and the mud content of the crushed stone is not more than 65,438 0%, which eliminates the quality hidden danger caused by the machine-made sand and can meet the production needs.
Mineral powder: Asphalt surface filler is mineral powder ground from strongly alkaline limestone. Gravel used for processing mineral powder has a silt content of less than 65,438+0%, a fixed particle size and is stored indoors in the rain. The treated ore powder is dry, clean and stable in particle size range, and can freely flow out of the ore powder bin. Limestone powder produced by Hefei Shi Lei Stone Co., Ltd. is selected.
Anti-peeling agent: calcium hydroxide powder (hydrated lime) is used, and hydrated lime produced by Anhui Chizhou Hengsheng is selected. The test results of raw materials meet the requirements.
Cement: Conch brand compound silicate P. C 32.5 retarded cement produced by Changfeng Conch Co., Ltd. is adopted. The initial setting time of cement exceeds 4 hours, and the final setting time exceeds 6 hours.
Asphalt: The lower layer adopts Grade A 70# heavy traffic petroleum asphalt provided by Zhongwu Zhenhua Trading Co., Ltd. designated by the owner, the middle layer adopts SBS I-D modified asphalt produced by Anhui Highway Asphalt Co., Ltd. and Hefei Baoying Materials Co., Ltd., and the upper layer adopts Hefei Bao.
In order to eliminate all hidden dangers, SBS I-D modified asphalt produced by Surplus Materials Co., Ltd. is responsible to the owner. According to relevant laws and regulations, our contract section samples and tests each car asphalt, and keeps samples for inspection.
(3) Mechanical equipment
In order to ensure the smooth progress of the project, our company invested a set of WCZ-600 water-stable mixing equipment with an output of 600 tons/hour in this contract. A set of Estek -4000 asphalt mixture mixing equipment with an output of 400 tons/hour is used to centrally mix the mixture. The equipment can be automatically controlled in the whole process, and has an accurate disk-by-disk data acquisition and printing system. The excellent performance and function of mixing machinery provide a strong guarantee for the smooth completion of our contract section.
Chapter IV: Report materials for regular meetings of construction projects: Report materials for the 2009 conference on attracting investment.
I. Work Progress and Completion in 2009
In 2009, China Merchants Bureau of * * District, centering on the central work of the district party committee and the district government, thoroughly implemented Scientific Outlook on Development, constantly innovated the concept of investment promotion, improved the mode of investment promotion, broadened the field of investment promotion, and worked with the Municipal Investment Promotion Office and various departments at all levels to continuously improve and optimize the investment environment, providing high-quality and efficient services for foreign-invested enterprises and individuals, and made new achievements in the investment promotion work of the whole district.
In order to achieve the goal of "planning no less than 30 high-quality packaging projects and no less than 20 imported projects throughout the year, and striving to introduce 800 million yuan" put forward in the work report of the district government in 2009, we mainly make efforts in three directions in promoting the construction of projects: First, we will work with all levels and departments to speed up the investment and construction of existing approved projects through supervision, coordination and service; Second, in conjunction with various departments at all levels, through supervision, coordination and service, we will promote the improvement of procedures and formalities for signed projects and implement them as soon as possible. Third, through project planning and packaging, increase the publicity of the project and further introduce new projects. Introducing new projects is the goal and direction of our work. In 2009, we strengthened the establishment and publicity of the project library. After careful screening, key planning and packaging, the original projects reported by towns, offices and departments were made into DVD discs, which were taken to Guangzhou, Shenzhen, Hangzhou, Wenzhou and other places with cities and counties to carry out extensive promotion activities. In Lijiang, we also constantly promote it through the website. Compared with overseas investment, Lijiang, a place with special tourism environment advantages, has more advantages than other places. Many entrepreneurs will take the initiative to come to Lijiang, or travel, or play golf. In addition to publicity through the website, we will also introduce various projects to Lijiang entrepreneurs through chambers of commerce, entrepreneurs' associations and other organizations, and we think this is a good way, because going abroad to attract investment not only costs money, but sometimes it doesn't have to be done at once. And through the association to organize entrepreneurs' project promotion meeting, it should be said that it can also achieve certain results in publicity. However, under the influence of the financial crisis to a certain extent, the investment of foreign capital has obviously weakened compared with last year. In 2009, the jurisdiction implemented 22 foreign-funded projects, namely Oman Hotel; Dino Cafe Lijiang; Shuhe's Bar Street, Shuhe Shopping Mall, Xiyu Valley Hotel and Shuhe Hongshan Development Project; "Tianyu Sunshine Characteristic Dwellings" Construction Project and "Theme Pavilion" Project. Jinmao Group World Heritage Reconstruction and Expansion Hotel Project; Shui Mu Tsinghua Garden Project; Banyan Tree Hotel Phase II Construction Project; Snow Mountain Century Garden, Xinhua Cultural Square, etc. The investment promotion project actually reached 490 million yuan. It accounts for 6 1% of the annual target task of 800 million.
In 2009, the newly signed investment projects in the jurisdiction include: in February, an intention agreement for the development of wind energy resources was signed with the preparation office of Yangmeishan project in Luliang, Yunnan, Longyuan Electric Power Group Corporation; In March, Oman Hotel Lijiang signed a cooperative operation agreement, and in April, Hainan West Coast Country Manor Club Co., Ltd. signed an intention agreement for Lijiang Provence Holiday Project; In May, he signed an agreement with Mr. Xiang Bing, cheung kong graduate school of business, on the project of Hongshan Jian Yong Academy in Shuhe, Lijiang River; 1 1 June, 2008, signed the project agreement of Lijiang high-tech software R&D base with Shenzhen sangxia technology co., ltd.
Two. 20 10 work plan
First, establish key investment projects, increase investment promotion efforts, strengthen project reserves, screen a number of major projects related to the economic development of the whole region, especially non-land acquisition projects such as agriculture, forestry, animal husbandry and water, and increase investment attraction, especially in the 5 square kilometers planning area of the new group, focusing on introducing large enterprises and groups with core competitiveness, combining the best quality resources with the most powerful enterprises, and striving to achieve new breakthroughs in the total amount, scale and grade of investment attraction.
The second is to strengthen the follow-up service of attracting investment, further improve the target responsibility management system of attracting investment around the economic development strategy determined by the district party Committee and government, and do a good job in the landing of the proposed investment projects. Further strengthen the tracking and coordination of major investment projects. Solve the difficulties and problems in the project progress in time.
Third, vigorously promote new ways of attracting investment such as national investment, resource investment, intermediary investment, cultural investment, window investment and media investment, truly form a new pattern of all-round investment promotion, and strive to complete the task of attracting investment.
Three. Specific project plan of report 20 10:
At present, the projects under construction in Ye Ding include: Shuhe Celebrity Bar Street Construction Project, Shuhe No.10 Courtyard Construction Project, Xiyu Ancient Hotel Construction Project and Tianyu Sunshine Construction Project.
I. Shuhe Celebrity Bar Street Project
1. Start date: April 2007
2. Total planned investment: 1.20 million yuan.
3. Accumulated investment since construction started: 94 million yuan.
4.20 10 is planned to be completed in March, with a total planned investment of1200,000 yuan.
Second, Shuhe Tenth Hospital Construction Project
1. Start date: April 2009
2. Total planned investment: 50 million yuan.
3. Accumulated investment since construction started: 3 million yuan.
4.20 10 June 30th.
Chapter V Report Materials of Regular Meeting of Construction Projects: Since this year, Mianyang Municipal Bureau of Statistics has actively promoted the theme activity of "Deepening the Year of Statistical Quality Service" in accordance with the work requirements of the municipal party committee and the municipal government and the overall requirements of statistical work in the province, providing statistical guarantee for promoting the "two accelerations".
In the first half of the year, the city's economy showed a trend of recovery and accelerated development. The agricultural economy achieved recovery growth, industrial production stopped falling and rebounded, investment growth was strong, the consumer goods market was gradually active, the growth rate of fiscal and tax revenue rebounded, the credit growth rate was relatively high, the income of urban and rural residents maintained rapid growth, and market prices continued to fall.
The city's GDP reached 38.86 billion yuan, an increase of 13.7%, ranking 15 in the whole province, up two places from the first quarter and three places from last year. Among them, the primary industry realized an added value of 6.69 billion yuan, an increase of 4.6%; The added value of the secondary industry reached18.46 billion yuan, an increase of18.2%; The added value of the tertiary industry was 137. 1 100 million yuan, an increase of 12.5%, ranking second in the province. The industrial structure ratio of the primary, secondary and tertiary industries is 17.2: 47.5: 35.3, and the industrial added value accounts for 4 1.7% of gdp.
First, focus on the center, highlight key points and vigorously promote various statistical monitoring work.
Focusing on the "three accelerations", the Municipal Bureau of Statistics has overcome difficulties, reformed and tapped potential, adjusted working ideas, added working measures and strengthened special monitoring. First, further establish and improve the statistical rapid response mechanism, focusing on monthly monitoring and statistical analysis of post-disaster reconstruction, expanding domestic demand, strengthening the city through industry, "planning project investment breakthrough year", transportation hub construction and economic target completion, and making early warning and forecast. By holding regular data review and evaluation meetings and "joint departmental statistics meetings", a joint evaluation mechanism will be established to improve the quality of key monitoring data. Second, around the central work of the Party committee and government and the hot and difficult issues in society, we will carry out in-depth surveys on people's livelihood, such as investment in fixed assets, energy saving and consumption reduction of industrial enterprises, pig prices and production, which are concerned by leaders and society, and strive to form a number of in-depth and influential statistical special survey reports to provide scientific basis for the decision-making of the Party committee and government. The third is to further strengthen the management of matrix system and enhance its execution. Divide tasks into leaders, responsible departments and responsible persons, strictly meet the requirements of progress and time limit, form a good situation of grasping the first level and being responsible at different levels, and ensure the smooth completion of various objectives and tasks. In addition, according to the requirements of the Provincial Bureau of Statistics and the needs of the Municipal Party Committee and the Municipal Government to speed up post-disaster reconstruction and economic development, the post-disaster recovery and reconstruction, energy saving and consumption reduction and statistical monitoring of the service industry have been fully completed.
1-In June, the Municipal Bureau of Statistics compiled and distributed 25 statistical analysis and special investigation reports, 3 statistical briefings and 72 pieces of statistical government information, which were adopted by the general office of the provincial government, 5 by the National Bureau of Statistics and 46 by the Provincial Bureau of Statistics. Innovatively compiled and printed special products such as Mianyang Economic Development and Prospect, Mianyang Economic and Social Development for 60 Years, and Mianyang Statistical Analysis 20 10. Completed high-quality social, people's feelings and feelings investigation reports, such as Investigation Report on the Impact of the Global Financial Crisis on the Production and Operation of Mianyang Industrial Enterprises, Quarterly Price Survey of Agricultural Products and Agricultural Means of Production, Special Investigation Report on Mianyang Automobile Market, and Investigation Report on the First Anniversary of Reconstruction after the "5. 12" Earthquake in Mianyang, and the important index data were delivered to the main leaders of the municipal party committee and relevant departments at the first time.
Two, in-depth study and practice of Scientific Outlook on Development, to further deepen the work of statistical quality service.
The study and practice activities of the Municipal Bureau of Statistics have achieved a large number of prescribed actions, and the self-selected actions strive for innovation. The satisfaction rate of the analysis and inspection report of the leading group of the Bureau of Statistics reached 100%. By carrying out the 20 10 "Deepening the Year of Statistical Quality Service", we should take the statistical demand as the guide and adhere to the concept of "deepening statistical service with learning practice as the carrier"; Focus on improving service products and improving the level of statistical services; Pay attention to strengthening investigation and study and give full play to the role of statisticians; Innovating service mechanism and optimizing statistical service function; With matrix management as the guarantee, strengthen the responsibility of statistical service, realize the change of service concept to compound, service focus to multi-field and service function to diversification, strive to build an open statistical pattern, and strive to realize the change of Mianyang statistics from popularization to word of mouth.
First, based on the "scientific development" of statistical services, the concept of "great service" integrating statistics and scientific development is established. The second is around "grasping service demand, optimizing service products, innovating service mechanism and broadening service fields". The key point is to expand the statistical service that mainly provides economic statistical products to provide statistical service products including social statistics, people's livelihood statistics, resources and environment statistics, etc. The third is to increase the information content of statistical service products. In addition to the main macro information, the focus is shifted to statistical products including micro information, factor guarantee and progress information, so as to improve the reference value and practicability of statistical data. Fourth, grasp the development theme, keep up with social hotspots, actively carry out various special surveys and popular surveys, improve the quality of special survey reports, and improve the overall level and quality of Mianyang statistics.
The third is to attach importance to the investigation of major national conditions and national strength, and the economic census has achieved phased results.
Conscientiously implement the "Regulations on National Economic Census", closely focus on the requirements of the "Implementation Plan for the Second Economic Census of Sichuan Province", and complete various technical work such as unit inventory, household registration, data audit, data processing and reporting of more than 0.8 million units and more than 270,000 self-employed households in the city. Make full use of census data, establish a basic unit directory database application system with unified standards, timely updates and * * * resources, start the second basic unit geographic information system construction, and build a socio-economic geographic information system with intuitive reading and convenient query. The economic census has achieved remarkable results, successfully passed the provincial inspection and acceptance, and won unanimous praise in the cross-examination of the whole province.
Fourth, strict statistical work norms have improved the overall data quality.
The Municipal Bureau of Statistics always insists on improving the quality of statistical data as the center, conscientiously implements standardized management measures for statistical work, and strictly controls the quality of statistical data. The first is to improve the statistical data quality grading system. The establishment of city, county, township (street offices) three linkage data quality responsibility system, responsible for layers, strict data collection, summary and audit. The second is to strengthen the coordination between majors, strengthen communication and convergence with relevant departments and higher-level statistical departments, master first-hand information, and ensure that statistical survey data are well-founded. The third is to improve the evaluation mechanism. Further improve the quality evaluation mechanism of major statistical data, actively explore the establishment of a third-party evaluation mechanism of statistical data, and ensure that the main indicators of the city are accurate, and all economic indicators objectively reflect the economic operation of the city. Five, grassroots infrastructure construction has been continuously strengthened, and actively build a "big statistics" work system.
First, actively promote the "statistical agency system" and strengthen the statistical work of "three-to-one" enterprises. The work of "statistical agency system" explored by Mianyang was reported on the front page of China Information Daily, which was highly valued by the National Bureau of Statistics and the Provincial Bureau of Statistics, and has been extended to the whole province this year. Second, new breakthroughs have been made in the reform of statistical methods and systems. This year, a new monitoring index system for post-disaster reconstruction was established, a statistical system for the service industry was established and improved, and statistical investigation methods were further improved. Third, the level of software and hardware construction of grassroots statistics has been continuously improved. In the first half of the year, 276 towns and villages in the city were equipped with "special computers and printers for statistics", and business training for grass-roots newspaper units was increased, further improving the statistical ability of grass-roots units. Fourth, new progress has been made in the construction of statistical informatization. This year, we will invest 300,000 yuan to transform the local area network, build a new video conference room, and configure video conference facilities and equipment to build a unified and compatible statistical data platform for the whole city. Fifth, conscientiously implement the spirit of the instructions of Director Ma Jiantang of the National Bureau of Statistics, actively promote the construction of the "fifth-level statistical organization" (township statistical station) in jiangyou city, and strive to lay a solid foundation for township statistics.
In the second half of 20 10, we will mainly focus on the following aspects:
First, innovative measures should be taken to establish a statistical monitoring index system of "one master, three modernizations and three upgrades", unify thoughts with the development path of "one master, three modernizations and three upgrades" and the leading strategy of "strengthening the city through industry", and strengthen special statistical monitoring.
The second is to strengthen statistical law enforcement. Intensify the publicity and implementation of the newly revised Statistics Law and the newly promulgated Provisions on Punishment of Statistical Violations and Disciplinary Actions, and strengthen the awareness of statistical laws and regulations of all subjects. At the same time, do a good job in the special law enforcement inspection of statistical qualifications.
The third is to speed up the statistical reform and deepen the statistical quality service. Further expand the scope of statistical services, strengthen statistical monitoring and analysis, forecast and early warning, and provide a basis for decision makers from a long-term development strategy. Carry out a series of special surveys such as Mianyang Industrial Park (industrial concentrated development zone) survey and Mianyang 12 energy consumption survey of key energy-consuming enterprises.
Fourth, comprehensively promote the "statistical agency system", further strengthen the park's statistical work, strengthen the "fifth-level statistical institutions" pilot, explore the establishment of "township accounting centers", and improve the quality of statistical source data.
Fifth, actively prepare for the sixth national census.