Mortar runway construction program?

Zhongda Consulting brings about the introduction of mortar runway construction program for your reference.

1. Preparation of the basis

1.1. Design information hydraulic protection engineering site design: gas-B01024 hydraulic protection engineering site design general construction drawings:

Line;1792 line;1794 line;1795 line;1796

1.2. Standards, norms GBJ202-83 "foundation and foundation engineering construction and Acceptance Specification" GB50203-98 "masonry construction and acceptance specification" GB50026-93 "Engineering Measurement Specification" GBJ206-83 "Timber Structure Engineering Construction and Acceptance Specification" JGJ46-88 "Temporary Electricity at Construction Sites Safety Technical Regulations"

2.2. Project Overview and Main Quantity of Work

2.1.Project OverviewThe Section Line from the west, east junction, line starting point measurement pile number BI001 (horizontal coordinate y = 17651070.38, longitudinal coordinate x = 4306681.26), the end of the measurement pile number BJ001 (horizontal coordinate y = 17720225.57, longitudinal coordinate x = 4258240.82), after the line adjustments, the final length of the line 89.4008km.The section Most of the line along the plains, mainly including alluvial plains and alluvial inclined plains, low hills and hilly areas are mainly concentrated between BI018#pile ~ BI022#pile, mainly to the high mountains. Hydraulic protection mainly protects slopes and banks for river and gully crossing, and makes retaining walls and drainage ditches for steeper hills. For earth canals and steep slopes, retaining walls are set up; for riverbanks with unstable soil and serious scouring by the main river, measures of retaining walls are taken; for riverbanks or beaches with smooth water flow and very little scouring, slurry masonry schist berms can be used. For the clay soil bank, take layered tamping backfill measures (tamping coefficient is generally 0.90); pipeline climbing embankment laying, the water-side (or both sides), the river bank using slurry masonry schist berms, for the original on the masonry of the river or cement masonry, take the same way with the original masonry to restore the original appearance; for the angle of the slope is greater than 15 ° of the mountain slopes every 10m to do retaining walls and drainage ditches.

2.2.The current main amount of water protection structures name of the total amount of work units Figure No. slurry masonry slope 180.5m3 line-1795 concrete continuous cover 52m line-1795 retaining can 82 line-1795 drainage ditch 37 line-1795 slurry masonry schist over the water surface 1196.4m3 Note: The table is listed as the current design of the amount of work 3.1.Construction process and main Construction method 3.1. construction process

3.2. construction method water protection project monolithic project volume is small, at the same time, in order to avoid damage to the pipe body, the construction of manual excavation pit slot, the rock section, take the method of artificial rock drilling wall embedded groove. Submersible pumps are used for pit descending, generators are used for on-site power generation, slurry masonry is used for artificial masonry, and mortar is used for on-site mold support.

4. construction technology measures

4.1. material selection and technical requirements of hydraulic protection is the line project protection facilities, the pipeline use process protection is of great significance, so the technical requirements of the materials used for hydraulic protection is very strict, must be strictly selected and accepted. Material procurement adhere to the local conditions, quality assurance, cost reduction principles, incoming materials must have material certificates, certificates of conformity and related certificates, prohibit unqualified products, unlicensed products into the construction site.

4.1.1. Masonry stone masonry stone (mainly blocks) selection of uniform texture, hard, no cracks, not easy to weather the stone, stone surface without weathering debris, mud, dirt, the stone to be used in the compression test, the ultimate compressive strength should be more than 25Mpa, try to choose a larger stone masonry, blocks should be roughly square, no front flute convex angle, the top surface and the ground should be more Flat, its thickness should not be less than 20cm, width and length are not less than its thickness. Slabs should have two roughly parallel surfaces, its thickness should not be less than 15cm, one of the side length of not less than 30cm. West-East Gas Pipeline water protection stone to block stone-based, construction section of the stone area is mostly weathered stone, does not meet the technical requirements of the water protection masonry, so the construction of the stone to be purchased mainly to buy the location selected in Shandan County quarry, the distance between the nearest 26Km, the furthest distance of 82 kilometers, the use of dumper trucks Transportation.

4.1.2. Masonry mortar? First of all, according to the design requirements of the selection of qualified sand and cement, mortar mixing to use tap water, with 5T tanker trucks from Shandan County to buy and send to the site, the average transportation distance of 38Km, is strictly prohibited anywhere in the ditch to take the sewage. Cement with R425 ordinary silicate cement, purchased in Shandan Cement Factory, the cement must have factory certificate, test report, re-inspection report, its stability, setting time, strength and other indicators must be in line with the standard provisions of the average transportation distance of 39Km.? Sand adopts washed medium (fine) sand, purchased by Sandan sand field, the mechanical properties of sand and gravel and other indicators in line with the standard provisions before being put into use, the average transportation distance of 29Km. Construction site using cement stacked neatly, bagged cement stacking height is generally no more than 10 packages, stacking width to 5-10 bags as a limit, temporary open-air stacking should be covered with a rainproof tarpaulin.? The storage time of cement is generally not more than 3 months, when there is doubt and uncertainty about the quality of cement, review the test before use and use it according to the test results. The sand and cement used on site are stacked separately and neatly, and are not allowed to be mixed, and the sand is kept clean, and is strictly prohibited to be mixed with soil. Slurry masonry mortar must have when the fluidity and good compatibility, to ensure that the masonry mortar joints are fully filled and compacted. Simple on-site inspection method is to pinch the hand into a small group, to seal the finger without pulp, after letting go of the hand is not loose as qualified. Different construction parts, structural form of masonry mortar standard strictly in accordance with the design requirements for control, slurry masonry wall masonry is strictly prohibited the use of mixed mortar. Masonry mortar should be quantitative batch strength test, up to 100m3 masonry to do a group of evaluation of mortar strength specimens. When the cement varieties, standard or with changes in the ratio, should be another group of specimens, and as a measure of the quality of mortar based.

4.1.3. planks? Planking choice by place, the principle is that it must be hardwood, we choose a better texture of pine, wood from Zhangye City timber market. Cut-off wall vertical plate and wall plate connection using just nail.? Plank lagoon hole drilling using electric drill, drilling position and plank connection joints should be staggered, spacing 200mm.

4.1.4. masonry mortar? West-East gas pipeline water engineering gray cut-off wall gray soil using 3:7 gray soil, gray soil mixing before, shall be on the lime, soil, mixing water strict inspection, sampling and testing, laboratory tests can only be carried out after the gray soil preparation. Gray soil mixing using mechanical mixing, mixing to be uniform, each batch of gray soil should be in proportion to the sample check to ensure that the moisture content of the optimal moisture content, the scene to "hold the hand into a ball, the ground blossom" test as a standard. Layers should be used to compact, 30cm layer is appropriate, compaction factor ≥ 0.94.? This section of the water protection is mostly in the Gobi deserted beach and rocky lot, gray soil mixing with fine soil on-site soil extraction is difficult, must be bought from the local soil, according to the combination of the local government, choose the Shandan brickyard soil pit as a land, using dump trucks for pulling the soil, the average transportation distance of 32km. Mixing water using potable water, water tanker trucks from Shandan County to buy and send to the site, the average transportation distance of 38Km.

4.2. structure measurement and positioning? Instrument selection general measurement and positioning instrument selection of latitude and longitude, through large gullies and steep slopes on the structure positioning measurement selection of total station, latitude and longitude, total station shall be recalibrated and qualified to use, before the start of work on the instrument inspection, to have calibration certificates. Reference point selection of building measurement and positioning project coordinates and elevation from the pipeline blueprint design stake point coordinates. Laying the line using latitude and longitude measurement of the position of the corner points of the structure, and buried control piles as the basis for the construction position and the basis for the transfer of the pile later, and the site sketches for the record.

4.3 Excavation and protection of pit trench

4.3.1 Excavation of pit trench according to the position of measuring and positioning piles of the structure and the size of the structure, put out the edge line of the pit with white ash, and then carry out excavation of the pit. In order to avoid damaging the pipe anti-corrosion layer or even the pipe body during the excavation, the pit trench is always excavated manually. This section of the water protection location part of the rocky mountain and valley area, rocky section of the pit slot widening, embedded slot excavation is carried out by manual rock drilling.

4.3.2 pit precipitation protection mountainous areas adjacent to the Qijia store reservoir, part of the pit excavation will have groundwater pooling, so the pit slot excavation should always take precipitation measures, precipitation using submersible pumps to lower the pit water discharged into the pre-digged ditch, ditch cross-section by the ditch discharged.

4.4. slurry masonry

4.4.1 masonry technical requirements? Slurry masonry stone wall using staggered group masonry method, according to the shape of the stone hanging double line sub-skin laying, the first layer of stone blocks face down flat side down, the upper and lower stone blocks staggered each other, inside and outside of the lap, laying stable, sub-skin stacking. Slurry masonry should be laid in slurry method, the mortar joints should be full, and inserted and pounded, the mortar joints are generally 20-30mm, the thickness of the slurry is about 40-60mm, the larger gaps should be embedded in the mortar with crushed stone blocks, and it is not permitted to fill with crushed stone in the mortar first. Slurry block stone shall not form horizontal or longitudinal through joints, shall not have knot rubbing. When filling the belly with blocks, the width of horizontal mortar joints shall not be more than 3cm, vertical mortar joints shall not be more than 4cm, and the mortar joints of filling the belly shall be staggered with each other.? When there is no special requirement for the hooking of masonry surface, a 2cm deep gap should be left in the masonry, and the gap should be hooked up with cement mortar immediately; otherwise, the gap should be cleaned and hooked up again after the masonry mortar is solidified. The masonry surface is hooked with flat joints, and the mortar used for hooking the joints is not lower than the masonry mortar. Masonry masonry one-time masonry, not allowed to leave construction joints.

4.4.2 Monolithic masonry measures? Cistern before mixing gray soil in advance in the construction site dug cistern for construction water, cistern size according to the construction point of the amount of gray soil size, should fully meet the amount of water, cistern lined with two layers of plastic sheeting, the size of the plastic sheeting to be able to cover the top of the pool in order to waterproof evaporation and debris fall into the pool. Slurry masonry slope? West-East gas pipeline water protection pipeline through the river or gully to take the form of slurry masonry slope, slope masonry using blocks.? Berm trench manual excavation, base soil compacted, compact coefficient of 0.9.? Slurry masonry blocks shall not form horizontal or longitudinal through joints, shall not have knotted rubbing, mortar full.? When there is no special requirement for the hooking of masonry surface, a 2cm-deep gap should be left in the masonry, and the gap should be hooked up with cement mortar immediately; otherwise, the gap should be cleaned and hooked up again after the masonry mortar is solidified. Masonry surface hooking using flat joints, hooking mortar used for mortar grade is not lower than the masonry mortar grade.

4.5. Handover acceptance

4.5.1 Before pre-acceptance of the project, the contractor organizes the relevant personnel in accordance with the requirements of the design and construction drawings and construction standards of its construction works to carry out a comprehensive inspection, such as discrepancies in the immediate rectification.

4.5.2 When all the works are completed and in accordance with the contract, the contractor shall apply to the owner or supervisor for handover acceptance.

4.5.3 The Contractor shall rectify the problems raised by the Owner or the Supervisor in the pre-acceptance organized by the Owner or the Supervisor within the time limit specified by the Owner or the Supervisor, and then apply for handing over the work again.

4.5.4 Handover data shall be accepted by the owner or the supervisory organization, and the handover procedures shall be carried out for the handover data after the acceptance.

5. Rainy season construction technical measures

5.1 For the construction works carried out during the rainy season, the rainy season construction technical measures should be prepared carefully and the specific methods of implementation at all levels and the system of regular checking should be formulated according to the actual situation of the construction so as to facilitate the implementation of the rainy season construction technical measures.

5.2 According to the actual situation of site layout, do the construction site drainage work in time.

5.3 Protection of temporary facilities and on-site construction equipment:

The temporary facilities at the construction site should be refurbished and strengthened before the rainy season to ensure that there is no leakage, no collapse, no fall, and no accumulation of water around. Construction site mechanical and electrical equipment (switchboards, gate boxes, welding machines, pumps, etc.), there should be reliable rain protection measures (such as setting up a rain canopy or set up a simple mechanical and electrical room, etc.). At the same time, the power cord for electrical equipment should be hung and fixed, not dragged on the ground, the site of electrical equipment rain leakage grounding protection device should be sensitive and effective, and a person responsible for checking at any time. Before the arrival of the rainy season should check the lighting and power lines have no mixed lines, leakage, poles have no corrosion, buried whether secure, etc., to ensure that the rainy season can be normal power supply.

5.4 afraid of rain, afraid of moisture, avoid corrosion, raw materials, components and equipment, etc., should be placed indoors, or set up a solid foundation stacked at a higher place, or the use of tarpaulin cover tightly and other measures to deal with separately.

5.5 masonry:

Rainy day construction of masonry works, should prevent the base trench flooding and rainwater washing mortar, the consistency of mortar should be reduced appropriately, masonry should not be left construction joints. The surface of masonry should be covered when closing. Masonry mortar should be mixed with the use, such as the construction period, the maximum temperature exceeds 30 ℃, must be mixed into 2h and 3h after the use of the end.

5.6 mortar project:

The construction of mortar project in rainy days may cause the moisture content of construction raw materials (sand, cement, etc.) to increase due to rainfall, therefore, the proportion of mortar should be adjusted according to the rainfall; mortar construction after rainy days, the moisture content of raw materials should be re-adjusted after the determination of the proportion of mortar. Mortar transportation and masonry process, such as excessive rainfall, transportation equipment and pouring locations should be rainproof measures to avoid mortar transportation and pouring due to rainfall and change the mortar fluidity and compatibility.

6. On-site quality management system

6.1 The quality officer observes, supervises and inspects the quality-related activities carried out on site. Check that construction work on site is carried out in accordance with approved procedures.

6.2 On-site inspection activities are random and, in principle, are carried out daily without any special reason. A record is made of deficiencies or defects observed and the responsible party is notified of the deficiencies or defects in writing or verbally, depending on the importance of the deficiencies or defects.

6.3 At the end of each week, the Technical Department shall summarize the inspection, make comments and notifications to ensure that key projects and important processes are not missed.

6.4 The project site is held once a month by the departments and project managers to participate in the quality summary meeting. Technical Department at the meeting to report on the operation of the month's quality system, identify problems in a timely manner, and urge the problematic departments to actively take corrective measures and urgent rectification.

6.5 All quality problems found on site, its corrective action should be recorded in accordance with the format specified in the program documents, and with the progress of the project, and gradually to the next stage of transfer, as the completion of the state of proof of the quality of the record documents to meet the requirements.

6.6 The project site should report to the company in time when there is any conflict with the quality management documents in the operation of the quality system or when the quality management documents can not be implemented, in order to seek a timely solution to the problem.

7. On-site HSE management

7.1. Construction site

7.1.1 The layout of the construction site is in line with the relevant safety and health regulations, the machinery and equipment are placed in a neat and orderly manner, and all kinds of signs and markings are correct and eye-catching, so that it meets the standard of civilized construction.

7.1.2 If there is a danger that endangers or may injure people, all related work shall be stopped until the dangerous state is eliminated.

7.1.3 Any equipment and tools that exhibit unsafe conditions shall be immediately removed from use until they are in a safe condition or removed or replaced from the construction area.

7.1.4 If an accident occurs on site, emergency measures shall be taken immediately and a written report shall be submitted to the Owner at the first time, and the investigation and handling of the accident shall be carried out in accordance with the relevant regulations of the Owner and the Supervisor as well as the Accident Handling Procedures of the Company.

7.1.5 The main road of the construction site shall meet the standard requirements, and the special condition shall be equipped with cover and safety guardrail.

7.1.6 The construction site shall be equipped with fire-fighting facilities and apparatus according to the fire-fighting requirements, and the fire-fighting channels shall be kept unobstructed.

7.1.8 During the night construction, after approved by the supervisor, the project department will provide the equipment with sufficient lighting intensity to ensure the safety production.

7.1.9 Control box electrical switches, gate knives, etc. shall be placed in the rain shelter or rain cover, set leakage protector to prevent leakage of electricity.

7.1.10 The work site should be frequently cleaned and kept clean, the garbage should be centralized and timely cleanup, transported to the designated location.

7.2 Construction Personnel

7.2.1 Familiarize themselves with the legal responsibilities and duties relating to safety and health and with the details of the Project Department's comprehensive and integrated safety and health program.

7.2.2 Appropriate punitive action will be taken against persons involved in violations of safety procedures in accordance with relevant Project Department regulations. Persons who violate safety rules and endanger life and property will be removed from the construction workforce.

7.2.3 Before working, construction personnel shall wear protective gears appropriate to the work as required, check the integrity of the work site, construction tools and equipment, and record the date of each inspection, problems found, and remedial measures taken.

7.2.4 Construction personnel shall comply with job safety and technical operation regulations during work, and do civilized construction.

7.2.5 Construction workers shall not consume alcoholic beverages before and during work, and shall not smoke in places where fireworks are prohibited.

7.2.6 In the construction area should take the designated passage, should not cross the danger zone, should not climb on and off the moving motor vehicles and climbing crane hooks and lifting objects.

7.2.7 Attention should be paid to all kinds of safety signs, and should not casually remove or occupy all kinds of lighting, signaling, lightning and other safety protection devices, safety signs and testing instruments.

7.2.8 Accidents should be timely rescue personnel and property, protect the scene and report to the relevant personnel. Execute the shift handover system.

7.3 Electricity Safety

7.3.1 Electrical work on the construction site is operated by a full-time electrician according to specifications. And is responsible for the operation area of a variety of electrically charged equipment and wires leakage check, found that the problem is immediately rectified.

7.3.2 Electrical equipment operators, must wear qualified labor insurance clothing, wear standard insulated gloves, and must leakage test of electrical equipment before use.

7.3.3 Rain, snow or wet weather, generally do not use electrical equipment in the open air, if necessary, to take appropriate measures for the safety of electricity.

7.3.4 Construction site electrical facilities should be set at the first end of the equipment load line leakage protection device. The leakage protector shall be installed in the switch box.

7.3.5 The distribution room of the construction site shall be well ventilated, and measures shall be taken to prevent rain, snow and animals from entering the room.

7.3.6 The metal casing of electrical equipment (except for safety voltage) shall be protected by protective earthing or protective zeroing. Wet or particularly harsh conditions of the construction site of the electrical equipment should be used to protect the zero.

7.3.7 Distribution screen (panel) on the various distribution lines should be numbered and labeled use. Distribution line maintenance should be hung "prohibit closing, someone operating" warning signs. Stopping and sending power must have a person in charge.

7.4 Other safety measures

7.4.1 When carrying stones, we should pay attention to cooperation, coordinated pace, mutual force uniformity, to ensure safety.

7.4.2 Pay attention to safety when making gabions, and pay attention not to slip skin and hook clothes when tying wire.

7.4.3 Construction road should be built to ensure sufficient width and strength to ensure transportation safety.

7.4.5 When manually excavating the base trench, be careful not to slip and hurt the pipe corrosion protection layer, and when manually drilling rock, prevent the rock from crashing and injuring the operator.

7.4.6 When constructing cofferdam to divert the flow, the cofferdam should be strong enough to prevent being washed out by water.

7.4.7 Slurry masonry slope should be cleaned up to prevent stones from slipping and hurting people.

7.4.8 mixer operation should comply with the operating procedures, strictly prohibit non-job personnel unauthorized operation.

7.5 Soil and water protection measures

7.5.1 Feed right-of-way, stockpile yard as far as possible to use the construction work belt or existing country gravel road, etc., no vegetation gravel yard and vegetation has been destroyed site.

7.5.2 Take appropriate measures during construction to ensure that site roads, slopes and other obstacles to the ground will not form obstacles that cause flooding and damage to vegetation.

7.5.3 Trees inadvertently cut down outside the work zone are to be remedied immediately, and as far as safety and constructability permit, the crews leveling the site shall try not to damage the surface of the site or touch the original root system, and the plants may be cut off from the ground to create conditions for later re-sprouting and growth.

7.5.4 Excavation of pipe trenches shall be carried out by stockpiling the topsoil separately from the subsoil, by installing suitable trenches for drainage and by maintaining safe access across the trench, and by pumping excess water from the trench to adjoining areas in a manner that does not interfere with other land uses.

7.5.5 When backfilling pipe trenches, every effort shall be made to restore the original shape of the surface so that the surface will drain properly.

7.5.6 The subsoil and topsoil backfill shall be matched to the soils on both sides of the pipe trench, and preserved topsoil shall not be filled into the pipe trench before the subsoil is backfilled.

7.5.7 When backfilling stockpiles of excavated soil, the surface turf or topsoil must not be removed.

7.5.8 Compact backfill in pipe trenches to a degree roughly equivalent to the pre-construction condition to minimize subsidence. Take care when compacting the fill at the intersection of pipe trenches and watercourses and on the banks of interrupted drains, and take appropriate measures, if necessary, to ensure safe construction.

7.5.9 Large excavated pipe trenches need to be inspected visually before backfilling, and if any animals are found, they should be got out, and for larger animals a slope may be dug into the wall of the reach to enable it to climb out.

7.5.10 The reclaim site maintains a minimum vegetated buffer zone from any waters.

7.5.11 Topsoil layers removed during the expansion of the reclaim site must be properly stockpiled, measures must be taken to prevent erosion, erosion must be confined to the limits of the reclaim site, and no unauthorized expansion of the working surface is permitted.

7.5.12 Except for the designated reclaiming yard, no pebbles, sand and waste can be dumped or dredged from the riverbed or bank during construction without permission from the local authorities.

7.5.13 Destroying, relocating or clearing trees and vegetation shall not exceed the extent required for the construction of the project, and there shall be no indiscriminate felling.

The road temporarily widened and reinforced during construction shall be restored to its original form after construction is completed, taking into account the local actual situation, and those affecting the environment shall be restored to their original form.

7.5.14 For environmental damage caused by violation of environmental protection rules and regulations, it shall be immediately reported to the Project Supervisor, who shall be responsible for cleaning up, recycling and/or taking restoration measures according to the instructions of the Project Supervisor. Surface runoff toward the aggregation, the upper part of the washout ditch to set up a circular throttle drain, side slopes at the masonry along the pipe ditch cut-off wall.

7.5.15 Poorly stabilized washout slopes, soft land base using slurry masonry strips (blocks) stone slope protection.

7.5.16 In the process of riverbed excavation, according to the specification requirements, under the premise of ensuring the operational construction surface, minimize the damage to the riverbed ecological environment. After the riverbed excavation is completed, the debris that obstructs flooding will be removed.

7.6 Waste and Domestic Waste Disposal

7.6.1 Keep the area of the operation zone free from construction-generated garbage and debris.

7.6.2 Food waste on the job site shall be clearly removed daily.

7.6.3 Trash shall be properly disposed of at an appropriate waste disposal site outside the construction site.

7.6.4 Garbage shall not be disposed of in ditches, on topsoil or on mounds.

7.6.5 Cleanup crews will pack up trash, debris, cut limbs, and construction preliminaries for disposal. Collect solid waste and trash (non-biodegradable debris) for disposal at an off-site location.

7.6.6 Collect solid waste and trash (non-dust biodegradable trash) for disposal at an off-site location.

7.6.7 All kinds of oil should be stored in containers, waste oil should be recycled in time and stored centrally, dumping on the spot is strictly prohibited, and measures should be taken to clean up the oil when it pollutes the ground.

7.6.8 Trees cut off during cleanup may be transported out of the operating zone area or sliced, shredded, or piled in an accessible area that can be utilized by the public.

7.7 Emergency First Aid Before the commencement of work (or construction operation) for water protection, through the analysis of risks and hazards as well as the investigation of local common diseases, infectious diseases and hospital conditions, based on the risk factors such as venomous snake infested environments, the use of machinery and equipment, and drainage of generators, prepare the emergency plan and emergency procedures, set up an emergency response team, and prepare the emergency materials, and ensure that every employee is familiar with the emergency plan and emergency actions. plan and emergency action in case of emergency.

7.7.1 Electric shock rescue? If the power switch in the vicinity, should quickly turn off the power, otherwise use insulated objects to pick open the wire or separation of electrical appliances, so that the patient from the power supply;? Respiratory arrest, artificial respiration immediately;? For cardiac arrest, perform chest compressions;? Send to hospital for first aid treatment.

7.7.2 Mechanical injuries rescue treatment of injuries is the principle of the first to save the life of the casualty, breathing, cardiac arrest of the casualty, should be immediately resuscitation on the spot.? Treatment of asphyxia. In case of serious blood loss or open chest injury, stop bleeding or close the chest wound as soon as possible;? Treat shock and fracture immobilization. Transportation of casualties with fractured limbs must be immobilized with splints on the injured limbs, and vertebral fractures must be placed on a hard board bed;? If arterial bleeding, put on tourniquet, relax every hour, 1-2 minutes each time, and keep the airway open during transit;? Send to the hospital, prevent infection, correct electrolyte metabolic imbalance, tetanus antitoxin injection.

7.7.3 Acute poisoning rescue? Immediately terminate the contact with poison, poison by the respiratory tract or skin invasion, immediately evacuate the patient from the scene of poisoning, move to a place of fresh air, contaminated clothes must be immediately removed, wash the skin of the contact area;? Take methods such as inducing vomiting, gastric lavage and catheterization to remove the poison that has not yet been absorbed in the body;? Remove poison from the skin, remove contaminated clothing, and wash the skin and hair with plenty of warm water;? Remove poison from eyes, wash thoroughly with water;? Remove poison from wounds; ? Apply antidote and transport to hospital.

8. personnel organization

9. labor volume dosage plan

10. construction plan plan

Opened on August 1, 2003 to enable to carry out the construction of hydraulic protection, according to the speed of construction of the main pipeline, in a timely manner to complete the work of hydraulic protection of each section.

11.Main materials, machinery and equipment required for the amount of plan

More about engineering/service/procurement category of tender writing production, enhance the rate of winning the bid, you can click on the bottom of the official website of customer service free advice:/#/?source=bdzd