2. Measure the tap water pressure, suitable range: 0.15-0.6Mpa. Pressure gauge to measure the tap water pressure, lower or higher than the prescribed pressure is required to install a booster pump or pressure-reducing valves, to ensure the normal operation of the equipment.
3. Detect the hardness of the raw water, using TDS pen to measure the ppm value of the raw water, or through other ways to monitor the hardness of the water.
4. Overflow pipe, drain pipe installation
Overflow, drain pipe mouth should be in the sewage downpipe or floor drain above the gap of 10cm, do not overflow, drain pipe directly into the downpipe or floor drain to produce a siphon phenomenon of sewage is sucked into the water softener internal damage.
5. Piping installation
First, the gasket will be installed into the two bellows interface; bellows were tightened in the water pipeline bypass system inlet and outlet, adjust the other two ends of the bellows and water softener bypass valve inlet and outlet connection height position. Load the gasket, corresponding to the connection to the water softener bypass valve inlet and outlet tighten and connect the bypass valve.
6. Move the water softener to a suitable position, fixed equipment, connect the power supply.
7. Parameter setting (display panel interface)
Water softener products using the control valve using the front and back stage mode setup: the front stage mode applies to the user, set the current time, the regeneration of the trigger time (the default value of 2:00), the raw water hardness value input (hardness value measured in step 3) and display the operation of water supply and other parameters. The background mode setting does not need to be set by the user.
8. Water softener commissioning, empty the resin tank air, rinse resin to no black water, yellow water out until.
9. To the salt tank to add regeneration salt, prohibit the use of salts containing additives or large particles of crystalline coarse salt. Salt surface should reach the salt box height of more than 2/3 position (do not exceed the height of the overflow port), and add a required amount of saturated salt water.
Reference: