Popularize the knowledge of disaster prevention and mitigation to protect people's lives. In order to minimize the losses that may be caused by disasters, we need to develop an emergency disposal plan. Writing an emergency plan we can start from what? Here, you may want to read the power outage emergency plan disposal process program, you are welcome to read and collect, and share with friends around you!
Power outage emergency plan disposal process program article 1A formulated purpose
In response to the hospital sudden large-scale power outage, rapid and orderly organization and restoration of power supply, to ensure the safety of patients' lives and reduce property losses, to ensure that the hospital electricity smooth, to promote the institutionalization of the accident emergency response work and standardization, based on the relevant state laws and regulations, combined with the actual situation of our hospital, the development of this plan.
Second scope of application
This plan refers to the "sudden large-area power accident" (hereinafter referred to as "large-area blackout") refers to the hospital as a result of a serious natural disaster, damage to the important facilities or damage caused by the sudden hospital-wide Large area of power system security defenses fail, the power grid in a large area of disintegration or collapse of the accident.
Three principles of emergency
Large-scale power outages to deal with the implementation of the "prevention-oriented, unremitting" approach, follow the "unified leadership, improve the mechanism, clear responsibility, strengthen cooperation, rapid response, measures decisive" principle. The principle.
Fourth organization
The hospital set up a large power outage emergency leading group, under the emergency repair team.
1 hospital large-area power outage emergency leading group
Leader: General Manager
Deputy Leader: President
Members: Personnel and Administration Manager
Logistics Supervisor
Electric maintenance workers
Responsibilities:
(1) Do a good job of daily safety power supply and maintenance technicians, the implementation of safety production responsibility system to prevent large-scale power outages.
(2) in the event of a large-scale power outage, do a good job in a timely manner in the event of power outage emergency work, as soon as possible to restore power supply.
(3) According to the severity of large-scale power outages, the decision to start and terminate the emergency plan.
(4) timely report to the higher levels of the accident and to the community.
(5) If necessary, request external support.
(6) The leader of the leading group is the first person responsible for the fulfillment of the provisions of this plan. Members of the unit should be under the unified command of the leading group, each in its own way, each responsible for its own responsibility, full cooperation, and do a good job of large-scale power outage accident when the 'social integrated emergency work.
2 emergency repair team
Captain: logistics supervisor
Members: electric repairman
Responsibilities: in the event of an accident, the organization of personnel to carry out rescue operations; to the command team to report on the accident, if necessary, to the power supply department to send a request for assistance, and summarize after the event should be circuits or low-voltage circuits. If the high-voltage circuit failure, the hospital power maintenance technician immediately import standby power supply, should be promptly contacted with the power supply department repair class, as soon as possible to restore, to ensure that electricity; if the hospital mortgage circuit failure, should quickly identify the cause, in accordance with the operating regulations to restore the circuit.
(B) hospital departments emergency procedures
1 each department received a power outage notice, should be allowed to bar all of its power supply cut off, to be put back into use after the circuit is restored to normal.
2 received a power outage notice, immediately do a good job in preparation for the power outage. If there is a patient rescue use the backup power.
3 after a sudden power outage, immediately look for ways to rescue patients and their operation of the power to maintain the rescue work, and open the emergency lights lighting, etc.. And should promptly notify the power maintenance technician or general duty.
4 critical patients in surgery using a ventilator patients usually should have a simple respirator next to the machine, in the event of a sudden power outage, health care workers immediately disengage the ventilator, the use of simple respirator to maintain breathing. The use of electric nitrogen suction patients, with a 50ml syringe connected to the nitrogen suction tube suction nitrogen.
5 such as double line are suddenly power supply failure, hospital generator power supply, medical staff should first ensure that the patient resuscitation; nurses should be calm and collected, on the ventilator on the hand holding the ball method, on the monitor on the use of manual measurement of blood pressure and pulse, electric nitrogen inhalation is used to use a 50 ml syringe connected to the nitrogen inhalation tube suction, such as close observation and please change, the rest of the staff immediately notify the power by phone to maintenance The rest of the staff will immediately notify the power maintenance technician by phone, the Department of Personnel and Administration, and use emergency lights for lighting.
6 strengthened ward visits, appease the patients, while paying attention to fire and theft.
7 elevator encountered a sudden power outage, logistics staff to do a good job of passenger ideological work, call to the outside, with artificial methods to put all the passengers out.
Safeguards
1 Electricity maintenance technicians should do a good job of generator maintenance on a daily basis to ensure that the generator is always in use.
2 Electricity maintenance technicians should usually master the knowledge of power supply and operation norms, pay attention to operation safety.
3 clinical departments routinely equipped with emergency lights, torches and other lighting, regular checks, to maintain a perfect state.
4 logistics department to organize emergency power outage drills, 1-2 times a year, through drills, so that everyone is familiar with the emergency procedures for emergency disposal of sudden power outages, to ensure patient safety.
Circuit or low voltage circuit. If the high-voltage circuit failure, the hospital power maintenance technician immediately import backup power, should promptly contact the power supply department repair class, as soon as possible to restore, to ensure that electricity; if the hospital mortgage circuit failure, should quickly identify the cause, in accordance with the operating regulations to restore the circuit.
Power outage emergency plan disposal process program part 2For sudden fire, lightning, wind, flood and municipal pipe network maintenance and other causes of power outages, and according to the power supply of our hospital, in order to ensure the smooth progress of medical work, to protect the lives of patients and health and safety, and to reduce the hospital's property losses, in the spirit of the ideological importance of the system is complete, clear responsibilities and measures in place the principle of the development of the power outage emergency response plan. The first step in the process is to make an emergency response to a power outage.
A blackout emergency response team and responsibilities
Group leader: Tan Hui
Group members: Kong Xiangde, Zhang Jun, Zhang Xiaorui, Jiang Guolin, Wang Jianjun.
Responsibilities: Responsible for emergency response to power outages and related equipment repair and maintenance work.
Second, the report:
(a), the planned blackout
24-hour duty personnel received the notice of the hospital office blackout, immediately report the blackout emergency team to make the appropriate emergency preparations. At the same time, the hospital office will notify the details of the power outage to the clinical departments and the relevant departments of electricity, so that they can do a good job in advance of the power outage work arrangements and preparations.
(2), the case of sudden power outages
(1) the clinical departments or related departments suddenly power outages
the clinical departments or related departments suddenly power outages, immediately report to the 24-hour duty officer, the 24-hour duty officer to find out the situation immediately deal with the situation can not be dealt with to report the head of the emergency response team of the incident of the blackout, the emergency response team can not be dealt with to report to the Emergency Office, by the Emergency Office to report to the Emergency Response Office, the emergency response team to report to the Emergency Office. Emergency Response Office, by the Emergency Response Office report to the emergency leadership group.
(2) hospital-wide sudden power outage
hospital-wide sudden power outage, the clinical departments timely report 24-hour duty personnel, 24-hour duty personnel immediately reported to the person in charge of the emergency response team of the power outage. At the same time by the hospital office will notify the details of the power outage of the clinical departments and related electricity departments.
Three, blackout emergency measures
(a), the circuit protection system
1, dual power supply, blackout two power supply mutual switching time of 5 seconds, to ensure that the whole hospital power supply.
2, emergency power supply (EPS) power supply, EPS starts immediately after a power outage, can ensure that the important departments (operating room, intensive care unit, blood dialysis room, ward rescue room), important equipment (respiratory machines, monitors, etc.) power for 30 minutes.
3, generator power supply, 5 minutes after the blackout (generator warm-up takes 1 minute) to send power to the key departments (operating room, surgical ICU, intensive care unit, blood dialysis room, ward rescue room).
(B), the emergency response team to take emergency measures
1, planned blackout situation
(1), received a notice of blackout, blackout emergency team personnel should immediately check the work of the backup circuit to ensure that at any time to switch the power supply line. At the same time check the working status of the standby generator set, the standby generator set should be tested to ensure that the standby generator set can be started at any time to generate electricity.
(2), when the power outage, start the dual power supply, the two power sources to switch each other within 5 seconds, to ensure that the whole hospital power supply. Scheduled power outage time 5 minutes before the arrival of the generator to warm up, in the dual power supply can not be powered, start the generator power supply, the duty officer immediately switch the power supply line in strict accordance with the operating procedures to ensure that the electricity will be sent to the important departments within 5 minutes (operating room, ICU, intensive care medicine, hemodialysis, wards, resuscitation room).
2, sudden power outages
(1), the hospital power outage: start dual power supply, can ensure that the hospital power supply. In the dual power supply can not be powered, electrician maintenance duty personnel immediately enable generator power supply. Ensure that the electricity will be sent to the important departments (operating room, ICU, intensive care medicine, hemodialysis, ward resuscitation room) within 5 minutes.
(2), individual sections or departments to report a sudden power outage: 24-hour duty personnel immediately identify the situation, timely processing, restore power. Can not be dealt with immediately reported to the person in charge of the power outage emergency response team, the organization of the relevant personnel repair until the restoration of power supply.
3, in the blackout period, 24-hour duty personnel must monitor the monitoring cabinet on a variety of meters on the index is normal, if there is a double power supply and generator sets can not supply power, immediately report to the person in charge of the emergency response team, the person in charge of the emergency response office, by the emergency response office to report to the emergency leadership team, and immediately contact with the power company to request a mobile power generator support. At the same time by the hospital office to send a notice to the hospital departments, do the corresponding emergency work. Power outage emergency team members and related personnel of the dual power supply and hair 24-hour duty personnel to check and repair, to ensure that the power supply can be restored in a timely manner.
4, by the 24-hour duty personnel safe delivery of electricity, 24-hour duty personnel on some key departments (operating room, ICU, intensive care medicine, blood dialysis, ward rescue room) to follow up by phone, to ensure that the power needs of key departments.
(C), the sections and departments to take emergency measures
During the power outage, dual power supply suddenly failed, EPS power supply is not available, in the hospital generator power supply before the specific emergency measures:
1, clinical, medical and technical departments
(1), the sections and departments responsible for the receipt of power outage notice, and immediately notify the duty officer and related staff. At the same time, do a good job during the power outage related emergency preparations, including the preparation of materials and equipment (flashlights, emergency lights, etc.); a variety of instruments and equipment spare charging, and so on.
(2), sudden power outages, the person in charge of the department or the duty officer to check the region of the emergency lighting is normally open, in order to provide the necessary lighting in a timely manner. If there is a backup power supply, the department will immediately activate the backup power supply.
(3), the person in charge of the department or the duty officer to inform the patients and their families, do not walk around during the power outage, pay attention to safety, to prevent falls.
(4), the key departments (operating room, hemodialysis, ICU, intensive care medicine, etc.) to take the initiative to contact the electrician maintenance class, to further understand the situation of the power outage, in order to properly arrange the work during the power outage.
(5), sudden power outages, the departments of medical staff are carrying out related work such as surgery, invasive operations, patient rescue, patients are receiving instrumentation and equipment to monitor the treatment of the situation, contact with the electrician maintenance class in a timely manner and inform the relevant information.
(6), in the power outage may have damage to the instruments and equipment or drugs are damaged, the head of the department or the duty officer should be the first time to the scene, and take timely and effective countermeasures to ensure that the instruments and equipment and medicines are intact.
(7), due to power outages caused by the computer can not run, the departments and departments, especially clinical departments, charging room, pharmacy, etc. should immediately start the network failure contingency plan, and at the same time to the patient to do a good job of explaining the work.
2, safety and security
(1), the person in charge of safety and security received a notice of power outage (especially at night), security personnel should be reasonably arranged to the key departments, key equipment to strengthen the safety and security work to prevent theft and other accidents.
(2), a sudden power outage (especially at night), the person in charge of safety and security or duty personnel, should immediately send additional security personnel to the clinical departments, emergency departments, to maintain the normal working order of the department, to ensure that the normal progress of medical care.
3, logistical support:
(1), the general storehouse personnel received a notice of power outage, emergency immediately check the power outage emergency materials (such as emergency lights, torches, etc.) the number and quality to ensure that the needs of the clinical departments.
(2), in the holidays, night sudden power outage, when received by the department on duty staff call, the need for emergency receipt of relevant substances, must immediately to the hospital, to complete the distribution of substances.
Four, late work
The General Affairs Section of the power outage incident to analyze and summarize.
V. Appendix
(a), the plan development and revision
The plan is regularly reviewed, according to the implementation of the blackout accident handling problems found in the implementation process in a timely manner
to update, revise and supplement.
(B), the plan explained
This plan by the General Affairs Section is responsible for interpretation.
(C), the implementation of the plan
Since the date of publication of the plan.
General Affairs Section
20xx.1.5
Power outage emergency plan disposal process program article 3First, the purpose and significance of the exercise
1. Through the exercise, to improve the hospital's logistical support and disposal of emergency public **** events, to protect the patient's life and the safety of the hospital's property, and to maintain the hospital's safety and medical order stability, to promote the medical care of our hospital. Medical order stability, promote our hospital medical work comprehensive coordination, sustainable development.
2. Through the drill, to enhance the staff's sense of worry and emergency awareness, social responsibility and self-help, self-help ability to improve the hospital's ability to deal with power supply emergencies rapid response.
3. Through the drill, test and examine the rationality and effectiveness of the hospital's power supply emergency response mechanism, and put forward measures and methods of improvement, and further revise and improve the emergency response plan for various accidents.
4. Through the drill, exercise logistics support emergency management and electrician group emergency rescue team, and constantly improve the mastery of the accident emergency treatment essentials, for once a large area of blackout events can be quickly and effectively disposed of and minimize the incident loss and accumulate experience.
5. test "xx city people's hospital emergency plan for large-scale power outages" operability.
Second, the basic requirements and principles of the exercise
1. Must follow the principle of safety first, well-organized, effective measures to ensure the safety of the exercise;
2. Must be from the actual combat, to be targeted, representative of the key departments, to ensure that the effect of the exercise;
3. Adoption of unified leadership, unified arrangement, graded responsibility method.
4. This drill specific exercises organized by the General Affairs Section, the hospital office to coordinate, the hospital's functional departments with the relevant sections of the team actively involved in the way.
Third, the exercise time:
xx November 10, 7:00 am to 12:00 noon.
Fourth, the drill organization and responsibilities
1. Emergency leadership group leader responsibilities: in accordance with the requirements of this exercise program, unified leadership command hospital large-area blackout emergency response exercise work; organization to set up the corresponding emergency drill organization; responsible for the exercise of the overall program of the validation; coordination of the relevant departments of exercise Coordinate the relationship between the relevant departments of the exercise; announce the start and termination of the emergency plan; issue emergency instructions for the exercise. The exercise is evaluated and summarized.
2. Exercise office responsibilities: responsible for the organization of the development of exercise plans and overall program; responsible for the coordination of the coordination of the section, organization and command; the implementation of the specific work of the section exercise.
3. Emergency repair team responsibilities: in the event of an accident, the organization of personnel to implement rescue operations; to the command team to report the accident, if necessary, to the power supply department to send a request for assistance, and afterwards summarize the lessons learned from emergency rescue work.
4. Each section team responsibilities:
1) responsible for section blackout material preparation.
2) Responsible for the emergency treatment of severe patients with power outage, to ensure that the patient ventilation, cardiac monitoring, treatment, etc., to ensure the safety of the patient
V. Exercise content
(a) Emergency start-up and event reporting
1, due to the 110kV Yingcheng substation station equipment accident caused by the loss of the whole station, resulting in a large area of blackout in Wencheng City, the city. City north of a large area of power outages.
2, the Southern Power Grid xx City Company Wencheng power supply office to the hospital electrician group report the accident situation notice. The head of the electrician group reported to the head of the large-area power outage emergency leading group and recommended measures.
3, the hospital emergency leadership team decided to start the "xx City People's Hospital large-area power outage emergency plan" according to the incident.
4, the exercise office will be blackout events and start "xx City People's Hospital large area blackout emergency plan" decision to notify the departments and teams.
(B) emergency response
1, emergency repair team
① Immediately start the first set of generator backup power to ensure the supply of medical power.
② If the first set of generator backup power failure, start the second set of generator backup power to ensure that the operating room, emergency department and other key departments of the power supply.
③ Check the elevator, if there is a locked passenger, immediately put all the passengers out by manual methods, at the same time to do a good job of passenger thinking. Restore the normal operation of the elevator.
2, the clinical departments, especially the emergency ICU, operating room, neonatal ward.
① Immediately look for ways to rescue the patient's power to maintain the rescue work, and open the emergency lights lighting.
② Critical patients, patients using the ventilator in surgery should be equipped with a simple respirator next to the machine, in case of a sudden power outage, health care workers immediately disengaged the ventilator, the use of simple respirator to maintain breathing. Patients using electric sputum suction, with a 50ml syringe connected to the suction tube sputum.
③ before the hospital generator power supply, medical staff should first ensure that the patient's rescue; nurses should be calm and sedate, on the ventilator using the hand-held ball method, on the monitor using manual measurement of blood pressure, pulse, electric sputum suction using a 50 ml syringe connected to the sputum suction tube suction, etc., and closely observe changes in the condition, and the use of emergency lights for illumination.
④ Strengthen the ward patrol, appease the patient, and pay attention to fire, theft.
⑤ Discontinue the use of boiling water and heating and other energy-consuming equipment.
3, medical department
① Check the operation of the uninterruptible power supply.
② equipment equipped with uninterruptible power supply in the hospital generator backup power supply before the resumption of power, to complete the ongoing checks after the shutdown standby.
③ The hospital generator backup power supply to restore power, start the normal project inspection. But must pay attention to observe the operation of the equipment. If the motor back-up power supply voltage instability caused by the hospital equipment operation is not normal must stop standby.
Six, the end of the emergency (emergency lifting and aftermath)
1. Setting the time of the exercise in four hours, the accident processing work into the end.
2. Municipal power grid resumed power delivery, the electrician group to the exercise office to report on the restoration of the grid, requesting the lifting of the state of the large-scale blackout event.
3. The emergency repair team is ready to switch the municipal power supply, notify the valuable equipment departments (such as radiology, ultrasound room, laboratory, etc.) to be ready to switch.
4. The head of the emergency leadership team decided to lift the state of the large-scale power outage.
5. The drill office sends a notice to each section shift announcing the lifting of the large-scale power outage emergency warning.
6. The large-scale power outage emergency leading group announced the end of the exercise.
7. Each section team to the exercise office to report on the exercise.
Seven, the exercise assessment summary
1. In order to make the exercise to achieve the expected purpose, to ensure the smooth progress of the exercise, the exercise program review.
2. Summarize the end of the exercise, the exercise process evaluation, summarize the experience and shortcomings, the formation of the exercise evaluation report, the future work to provide reference and guidance.
Eight, the drill security measures and notes
1. Advance publicity should be carried out to eliminate the workers and patients on the drill doubts.
2. Before the start of the drill, each section of the team should do a good job of the relevant safety measures, strengthen the organization and leadership to ensure that the drill is safe and smooth.
3. In accordance with the emergency procedures, unified command, listen to scheduling, strictly according to the program.
4. During the exercise, hidden dangers or accidents were found, and the exercise was stopped in time and reported to the office of the emergency leading group.
5. In case of emergencies during the drill, the drill will be temporarily terminated.
Power outage emergency plan disposal process program part 4I. Usually should do the work:
① softened water tank water level should be more than three molecules of two, the high water tank should be full of water level.
② boiler should maintain a normal water level.
③ Emergency lights should be in good condition, and a strong flashlight, ready for use at any time.
④ Strict equipment inspection system to ensure that the equipment has emergency capacity.
II. Emergency measures in the event of a power failure:
① need to remain calm and make a judgment on the accident.
② need to be judged as a sudden plant-wide power outage, immediately open the emergency flue gas discharge valve, so that the flue gas is discharged from the emergency discharge channel to prevent deflagration.
③ All the equipment in the control room cabinet power to the "stop" position, to prevent the sudden start of the wrong call.
④ In the water distribution tank, open the high water tank to the water distribution tank contact valve, check whether there is water overflow in the water jacket next to the feeder. ⑤ Check whether the water outlet valve of the high water tank is always open, observe the water level in the high water tank, and estimate how long the amount of water stored in the high water tank can be maintained.
⑥ Close and gradually close the split cylinder outlet valve to reduce boiler water consumption.
⑦ shut down the furnace jacket cooling water replenishment valve, the lower material water jacket cooling water valve, two combustion chamber roof cooling water valve, flue cooling water valve, check who overflow can be.
⑧ check the high water tank water consumption and water level decline, the high water tank water to maintain the time once again estimated. ⑨ check the silo situation, the silo material level situation, the silo iron rod insertion stick, to prevent the silo burn through. ⑩ Contact the power plant, ask about power outages, determine the time to restore power.
Need to report to the leadership, the site situation, emergency measures to deal with the situation, the power plant power outage feedback, there are still problems to the leadership report.
Need to boiler water level, the water jacket water whether overflow, high water tank water storage, sub-cylinder pressure, steam packet pressure, site conditions, power outage situation for the moment monitoring.
III. Measures after the incoming call:
① A comprehensive inspection of the plant equipment, to determine the absence of major damage, ready to resume system operation. ② will be in the control room cabinet equipment power to "automatic" position, start the induced draft fan, the production line flue blowing, so that the flue to return to negative pressure operating conditions. Close the emergency flue gas discharge valve.
③ Start the circulating water pump to replenish the high level water tank, when the high level water tank is full of water, close the water distribution tank to the high level water tank contact valve, restore the water distribution tank to the water jacket valve opening and closing degrees to ensure that there is enough cooling water to cool the water jacket.
④Start the boiler feed pump to feed water to the boiler.
⑤ When everything is normal, restore the normal combustion of the incinerator and the second combustion chamber, restore the normal operation of the medical waste incineration system.
Second, the organization
The project set up emergency rescue command group, responsible for command and coordination.
2. Responsible for on-site protection, set up a cordon, maintain order, evacuate people.
3. Responsible for notifying the equipment unit to organize rescue, call the rescue personnel, timely and safe removal of dangerous situations.
Fourth, emergency rescue procedures
When the tower crane crane in normal operation suddenly encountered a power failure (for a long time), so that the lifting object hanging in the air. And for a long time, the following emergency measures should be taken:
1. All controllers should be dialed to the "0" position, disconnect the total power supply.
2. By professional maintenance personnel intermittently open the hoisting winch brake or open the pull handle by hand, so that the lifting object down, each time down a short distance, the descending speed shall not exceed the rated speed, and finally make the lifting object down to the ground.
3. If there are obstacles and houses below the crane, the following measures should be taken:
(1) according to the contents of article 2 will be lowered to a safe distance from the object or house above, and then take the slewing device brake or pull the wind rope measures, do not allow it to rotate under the action of the wind;
a. The tower crane jib slewing turn to the open place, or slewing to the building Safe parts, or temporary resting on the steel platform that can carry the tonnage of the crane and monitor, and brake slewing, set up a cordon, and then according to the operation of Article 2;
(2) set up a cordon area under the crane, and have a special person to monitor, do not allow people to walk or work under the crane;
(3) below the crane is an office area, then below the office of the crane people must temporarily (3) If there is an office area under the hoist, the personnel in the office under the hoist must leave temporarily and take measures according to the method in (2);
(4) If there is a residence under the hoist, the personnel in the house under the hoist will be persuaded and guided by the project department to take temporary evacuation measures;
(5) After the power supply is restored to be connected, a comprehensive inspection should be carried out, and then the hoist will be turned to the designated place for descending.
4. Immediately organize safety self-correction, eliminate hidden dangers, to ensure construction safety; immediately organize the construction of all construction workers to cite the safety re-education, improve the safety awareness, to comply with the rules and regulations, to prevent the occurrence of similar accidents.
5. In the rescue process, fall from height accident, immediately implement the fall from height accident emergency treatment and rescue plan.
Constructor:
Safety Officer:
Material and Equipment Officer:
Attachment Nearby hospital address:
Workplace accidents are the directory of featured hospitals (please select according to the actual project)
Power Outage Emergency Response Disposal Procedure Program Part 61, water outage:
1) First identify the cause of the water outage, to determine whether it is the external network water outage or the hotel water supply equipment problems;
2) such as the external network water outage should be immediately notified to the store manager, the company's engineering department, the deputy general manager in charge and the general manager;
3) timely contact with the relevant units, to determine the time of the suspension of the water, water supply time, so as to facilitate the leadership of the company to make the appropriate decisions;
4) Maintenance personnel on duty Water pump room, pay close attention to the water level of the water tank and the operation of the equipment; do a good job of explaining the guests and temporary water supply arrangements;
5) notify the store manager, the company's engineering department and equipment supply, maintenance unit to get in touch with the reason for the failure of the equipment and parts of the damaged parts, the degree, etc.;
6) organize personnel and materials in advance, received instructions from the higher level, and immediately take appropriate measures to safeguard the normal operation of the hotel.
2, blackout:
1) such as the external network blackout, immediately get in touch with the power supply department, to confirm the nature of the blackout;
2) should be immediately reported to the hotel's general manager, the company's Ministry of Engineering;
3) the maintenance staff should arrive at the front desk in a timely manner, with the walkie-talkie and elevator to get in touch with the elevator to confirm the elevator is closed. Off people, such as off people in accordance with the elevator malfunction release work procedures;
4) maintenance personnel with good communication tools, maintenance tools, emergency lighting, inspection of the boiler room, pump room, elevator machine room, power distribution room, lobby and other key parts, and at any time to notify the front desk of their location, to ensure that the communication is open;
5) cut off the switch of each branch of the switching cabinet, to prevent the sudden call cause Equipment and personal injury; hotel internal power distribution failure caused by power outages, identify the fault location, cause, disconnect the faulty equipment power supply, restore the power supply of non-faulty parts, reduce the impact of the area;
6) to protect the scene, the appropriate measures to deal with the timely reporting and contact with the off unit;
7) after the failure to deal with the verification of the equipment is no abnormality before the resumption of the supply of phase power and to strengthen patrols Equipment operation;
8) prohibit unauthorized operation, the important equipment must be handled by professionals;
The occurrence of the above must be a good record of equipment accidents, to facilitate the investigation of the cause of the accident and the improvement of work procedures