1, equipment procurement
(1) steel plate, thermal insulation and anti-corrosion materials, fillers, pipes, valves, etc. The supplied equipment shall be selected from qualified domestic manufacturers. List the part number, name, quantity, material, size, approximate weight and capacity, motor power and manufacturer of each equipment, list the name, quantity, model specification and manufacturer of each instrument, and list the name, quantity, model specification and manufacturer of power distribution equipment.
(2) Moving equipment should be purchased from well-known domestic manufacturers. List the purchasing manufacturers of submersible sewage pumps and centrifugal blowers (not less than three). Shanghai Motor Factory and Jiamusi Motor Factory are recommended for motors, ST50M series for motor protection and PD 1008 series for instruments.
(3) Electrical equipment and components should be purchased from well-known domestic manufacturers. The model of low-voltage switchgear should be MNS, and the frequency converter should be Danfoss. Other equipment and components should adopt famous brand products of large domestic enterprises, such as YSA2, YSM 1, CW 1 and CM 1 series.
2, civil construction organization measures
2. 1 construction preparation
(4) Do a good job of "three links and one leveling" according to the construction plane, bury construction electricity, send pipelines with water lines, and arrange water and electricity meters.
(5) According to the site general layout, set up temporary facilities according to the red line and site dividing line specified by the construction unit, and the supervisor shall coordinate with the site appearance and construction plan.
(6) According to the construction plan, organize all types of construction personnel to enter the site on schedule to meet the needs of the labor force, achieve reasonable difficulty and efficiency, and allow construction machinery to enter the site on demand.
(7) According to the construction plan, organize advocate materials and main materials below 0.00 to enter the site.
2.2 technical preparation
(1) Organize the team leader and all kinds of workers to carefully read the construction drawings of civil engineering and installation, thoroughly understand the intentions and requirements of the structure, architectural decoration and use function of the design drawings, list the opinions and requirements that need to be answered during technical disclosure, and then invite the design, construction unit and supervision unit to make technical disclosure.
(2) Before the partial construction of the project, organize technical business backbones above the team leader of each type of work to carry out technical disclosure, quality disclosure and safety disclosure, and assign all construction personnel to carry out safety construction one by one.
(3) According to the general construction plan, put away the axis, control the elevation with the assumed permanent coordinates, control the buried axis, etc., and then ask the representative of Party A or the supervision department to accept the visa.
(4) The prepared steel bars and templates shall be rechecked by the on-site technicians, and handed over to the relevant teams for production, processing and molding after the technical director rechecks them correctly.
(5) Prepare a comprehensive budget and analyze all kinds of materials and man-days as the basis for labor deployment of all kinds of materials.