How to write the project acceptance program

Question 1: How to write the "project acceptance criteria and acceptance methods" inside the bidding program Inside the bidding documents, copy it and see what is missing, or the standards used by your company are higher, you can add up

Question 2: How to write the acceptance application (construction project completion of the environmental protection acceptance of the application model)

On the application for the completion of the environmental protection acceptance of the construction project of × × × × letter

The Environmental Protection Bureau:

According to your bureau's approval

× × × × construction project The main project of Project ×× (name of the project) has been completed, and the main contents include:

......

(state whether it is consistent with the EIA document and its approval), and the supporting pollution control facilities of the project have been completed, and the pollution control and ecological protection measures have been implemented.

The project has been completed, and the main content of the project has been completed. The pollution control and ecological protection measures of the project have been implemented.

(and

agreed by your bureau to carry out trial production operation).

}

Report

{

Table

}

)

or fill out the construction completion of environmental protection acceptance application registration card. It is hereby submitted to your bureau for approval

of the environmental protection acceptance of the completion of the construction project.

Annexes

:

1

, construction project completion of environmental protection acceptance monitoring (investigation) report (form);

2

, construction project completion of environmental protection acceptance application report (form, registration card);

Question 3: What are the assessment indicators of project completion acceptance Project completion of the radical examination Acceptance is mainly against the target tasks in the project book. Since the application under this project, there must be a feasibility study report, an implementation program, a project contract. The target task is based on the contract, that is, the assessment of the indicators. The main project tasks to complete the situation (the technical results achieved, published papers, patents, awards, etc.), benefit analysis, the use of funds, and attached to the application of proof of benefits.

Question 4: What are the criteria for acceptance of science and technology projects? Hello! The acceptance criteria for science and technology projects in different provinces and cities are different. Different science and technology projects are also different. It is recommended that you go to the website of the Department of Science and Technology to download the relevant information to understand. (

Take Changsha City as an example:

The main contents of the project acceptance include: 1, the content of the project contract and the completion of the technical, economic and social development indicators; 2, the project contract to determine the total funding, the municipal science and technology administrative departments allocated funds, matching funds and self-financing in place, the actual expenditure and the rational use of the project funds. The actual expenditure and the use of reasonable and standardized; 3, the project obtained independent intellectual property rights; 4, the organization and management of project implementation.

Article 6 Project acceptance is divided into meeting (on-site) acceptance, final acceptance of two. Meeting (on-site) acceptance refers to the project unit after the completion of the project by the self-examination of the application by the members of the acceptance group in the form of a meeting to listen to the project implementation of the introduction, questioning and other procedures, if necessary, on-site inspection, discussion and the formation of acceptance opinions. Acceptance refers to the project undertaking unit after the completion of the project, under the organization of the recommended unit in accordance with the contract self-examination, the formation of the completion report. Article VII major special projects, key projects should be used in the form of meeting (on-site) acceptance of acceptance, major special projects, must be carried out on-site inspection; general acceptance of the project to take the final acceptance.

Article VIII awards, investment and financing projects and post-subsidy funding projects, as well as project research and development directly resulting from the results of scientific and technological achievements identified by the provincial level and other unnecessary acceptance of the project is no longer organized acceptance.

Chapter III Project Acceptance Organization

Article IX Changsha City, the administrative department of science and technology commissioned by the relevant scientific and technological intermediaries to organize the acceptance of municipal science and technology plan projects and performance assessment work. By the municipal science and technology administrative department of the integrated planning office under the guidance of the Supervision Office throughout the participation in the supervision. 1, the acceptance of major special projects, key projects (including mid-term evaluation) organized by the relevant science and technology intermediary institutions, to take the meeting (on-site) acceptance of the way. 2, general project acceptance, in addition to universities and research institutes project by the recommended qualifications of universities and research institutes Science and Technology Division according to the closing acceptance of their own organization acceptance, the other according to the principle of territoriality, by the district, county (city) science and technology administrative departments or parks science and technology management department according to the closing acceptance of the acceptance of their own organization acceptance, acceptance by the recommended unit of the line with self-examination of the closure of the project report reported to the Changsha City, the administrative department in charge of the project, the comprehensive science and technology management department, and the project management department. After acceptance, the recommended unit shall submit a document with a self-examination report to Changsha City Science and Technology Administration Department in charge of the project, Comprehensive Planning Department and the entrusted science and technology intermediary organization for record, and the acceptance certificate shall be issued. The commissioned scientific and technological intermediary organization may carry out random check and audit if necessary.

Article 10 In addition to the general program projects, project acceptance should be set up to accept the expert group. Acceptance of the expert group by not less than five people in the relevant fields of experts (technology, economic fields) and science and technology management personnel, including experts in the field of technology not less than two thirds of the total number of experts, experts in the relevant fields in the municipal science and technology administrative departments of the expert talent pool randomly selected.

Article XI of the project acceptance experts on the acceptance of the technical content of the project has the responsibility of confidentiality, the technical information being examined, shall not be used without authorization or open to the public. The project undertaking unit of the research content of the confidentiality requirements, can be applied to the organization of the acceptance of the department, after review, necessary, the organization of the acceptance of the department should be with the acceptance of the expert members of the signing of the confidentiality agreement, the confidentiality of the period and content.

Article XII of the project acceptance of the implementation of the avoidance system. Project completion personnel and collaborators can not participate in the acceptance as a member of the acceptance group. Chapter IV Application for Project Acceptance

Article 13 The project undertaking unit must submit an application for acceptance or closing acceptance within three months after the completion date specified in the Contract.

Article 14 The application for acceptance of major special projects, key projects, need to submit the following information: 1, application for acceptance of the project; 2, program documents and program project contract; 3, project implementation of technical reports and work summary; which should include the technical research process, the relevant test and inspection, the results obtained, patents and related products (or prototype) data, the use of funds, economic and social benefits, user reports, etc.

Article 14 The project must be accepted within three months of the completion date stipulated in the contract. Social benefits, user reports, etc. 4, the final project funding statement; 5, further research or industrialization of the organization and recommendations. General project self-examination report should contain a summary of the implementation of the project, the formation of technical results produced by the social and economic benefits, financial accounts, especially the use of funding.

Article 15 The application for acceptance of major special projects and key projects shall be submitted to the office in charge of the project of the municipal administrative department of science and technology, and the office in charge of the project shall review the acceptance information based on the project contract, and sign the opinion and submit it to Changsha after meeting the conditions for acceptance. ...... >>

Question 5: How to write the project acceptance review opinion A few provisions on "science and technology project acceptance (review) opinion letter"

Statute Level: National Regulations; Statute Category: Scientific and Technological Achievement Management; Promulgation Time: 1996-08-20;

Promulgation Unit: Xiamen Science and Technology Bureau

Xiamen Science and Technology Bureau [ 1996] No. 20

The relevant ministries, commissions, offices, bureaus, counties and districts Science and Technology Commission:

In order to adapt to the "scientific and technological achievements appraisal methods" outside the scope of the appraisal, to be declared Science and Technology Progress Award project, is now in accordance with the spirit of the Fujian Science and Technology into the [1995] No. 18, the development of the "scientific and technological project acceptance (review) Opinion", as one of the effective documents to request the award project technology, economic and other comprehensive evaluation of proof and registration of achievements. Acceptance of scientific and technological projects (review) a few points as follows:

First, the acceptance of scientific and technological projects (review) applies to "scientific and technological achievements appraisal methods" outside the scope of appraisal, to be reported to the Scientific and Technological Progress Prize for the project. Including: (1) the application of new scientific and technological achievements in the construction of socialist modernization; (2) the promotion and application of existing scientific and technological achievements; (3) in the construction of major projects, the development of major equipment and technological transformation of enterprises, the use of new technologies; (3) the introduction, digestion, absorption, development, and application of foreign advanced technology; (4) soft science research results; (5) for the public welfare of the technological infrastructure services (standards, measurement, scientific and technological information, etc.); (6) theoretical research results that have been publicly published for more than one year. As one of the effective documents to request the award project in technology, economic and other aspects of the comprehensive evaluation of proof and registration of results.

Second, the scientific and technological project acceptance (evaluation) of the procedures described in the regulations can be combined with the relevant units of technical validation, acceptance or professional academic activities. Acceptance (review) should be 5-7 people above the intermediate title of peer experts (including Sichuan scientific research, teaching, production and individual science and technology management personnel), of which, the main and deputy reviewer should be a senior title.

Third, the acceptance of scientific and technological projects (review) by the project task of the department or the management of scientific and technological achievements at all levels of the Science and Technology Commission (the above departments are called the organization of acceptance (review) unit to accept the application and responsible for the organization.

(1) *** department at all levels of the project issued by the task department to accept applications for review, and then reported to the Municipal Science and Technology Commission results management department for approval and organization.

(2) unit of self-selected or horizontally linked projects, according to the completion of the project unit's administrative affiliation, by the municipal authorities or county, district science and technology commission to accept the application for review, and then reported to the Municipal Science and Technology Commission results of the management department for approval and organization.

(3) such as the combination of technical validation, acceptance or other professional academic activities for review, the project completion unit should first obtain the consent of the host unit of the above activities, before the organization of the review unit to apply.

(4) After accepting the application, the organization acceptance (evaluation) unit shall promptly review and notify the applicant whether it agrees to organize the evaluation. The organization acceptance (assessment) unit can host or entrust the relevant units (including validation, acceptance or professional, academic activities of the host unit, the implementation of the project, etc.) to host the work.

Question 6: Briefly explain the conditions, scope and criteria for acceptance of project completion? Acceptance of completion should generally have the following conditions: 1, the project has been completed according to the approved design of all the content; 2, the unit project can operate normally; 3, the problems identified in the previous acceptance has been basically dealt with; 4, archived data in line with the relevant provisions of the project file data management; 5, the project has been basically dealt with the construction of land acquisition, compensation and resettlement of immigrants, and so on, within the scope of the project's main building safety protection The relocation of the main buildings of the project within the scope of safety protection and land acquisition for project management has been completed; 6, the investment in the project has been fully in place; 7, the final account of completion has been completed and passed the completion audit. But the following cases can also enter the completion of acceptance: 1, individual units of engineering has not been completed, but does not affect the normal operation of the main project and the benefits of play, acceptance should be given to the unit of engineering to leave enough investment, and make arrangements for the completion of the construction; 2, a small number of tailing can not be completed due to special reasons, but does not affect the normal and safe operation of the project. Acceptance of the tail work should be reviewed, and instructed the relevant units to complete the deadline.

Scope: 1, check whether the project is completed in accordance with the approved design; 2, check the quality of the project, assess the level of the project, the project defects in the processing requirements; 3, on the acceptance of the remaining issues to deal with the requirements of the 4, in accordance with the requirements of the contract, the construction unit to the project sponsor to hand over the project.

Criteria: 1, according to the approved design documents; 2, the national quality standards for each construction project and acceptance specifications, regulations.

Question 7: how to write a model construction unit completion acceptance? Housing construction project completion acceptance and quality assessment report issued by the Ministry of Construction Construction [2000] No. 142, "Housing Construction and Municipal Infrastructure Project Completion Acceptance Interim Provisions" (hereinafter referred to as "Interim Provisions") and the Ministry of Construction Decree No. 78, "Interim Measures for the Record Management of the Completion Acceptance of the Construction of Buildings and Municipal Infrastructure Projects" (hereinafter referred to as "Interim Measures") has been promulgated and implemented for one year! The construction project completion inspection and acceptance by the verification system reform for the record system, used for many years by the construction quality supervision agency for the completion of the project acceptance of the quality level approval to be changed by the construction unit to organize the construction unit and the relevant experts to form an acceptance group for the completion of the project inspection and acceptance, through the record for the record procedures to be confirmed. However, in the actual completion and acceptance process, some supervision engineers still do not understand the procedures and content of completion and acceptance, not familiar with the "Interim Provisions" and "Provisional Measures", not clear about the work to be done by the supervision unit as well as the requirements of the supervision unit to provide the content of the quality assessment report. Therefore, this paper summarizes and concludes the procedure and content of completion acceptance, the work to be done by supervision engineers at the stage of completion acceptance and the content of quality assessment report. Peer reference.  1, the completion and acceptance stage of the supervision unit's work 1.1 review the engineering technical information submitted by the contractor, and the quality of the project for the completion of the pre-acceptance.  1.2 Evaluate the quality of the project and put forward the project quality assessment report. And sign the supervisory opinion on the project completion report and the project completion report submitted by the contractor.  1.3 Participate in the completion acceptance organized by the construction unit.  1.4 Report on the performance of the supervision contract and the quality of the project at the acceptance meeting.  1.5 Accept the review of supervision file information by relevant parties.  1.6 in the acceptance of all parties *** with the signature of the completion of the acceptance report and completion of the acceptance of the record form signed.  2、Assist the construction unit in the stage of completion and acceptance 2.1 Advise and consult the construction unit on the procedure and content of completion and acceptance, assist the construction unit to formulate the completion and acceptance program, determine the list of members of the acceptance team and the completion and acceptance procedures.  2.2 Assist in obtaining approval documents or permitted documents from the departments of urban and rural planning, public security and fire protection, environmental protection, etc.  2.3 Assist in notifying the local construction project quality supervision organization.  2.4 Assist in organizing completion acceptance.  2.5 Record and summarize the summary materials on the performance of engineering contracts and the implementation of laws, regulations and standards by all parties involved in construction, investigation, design, construction and supervision.  2.6 Assist in reviewing the engineering files and materials of the above participating parties.  2.7 Assist in organizing field engineering quality inspection.  2.8 Assist the construction unit to make a comprehensive evaluation of the engineering survey, design, construction, equipment installation quality and management links, coordinate the opinions of all parties, and draft opinions on the completion and acceptance.  2.9 to assist the construction unit to the local construction administrative departments to submit the completion of the acceptance of the documents for the record.  3、Completion Acceptance Procedure 3.1 Pre-completion Acceptance 3.1.1 When the unit project reaches the condition of completion acceptance, the contractor shall fill in the project completion report after the completion of self-examination, self-inspection and self-assessment and submit all the completion acceptance data (quality assurance data, evaluation data, construction technology data, construction management data and as-built drawings) to the Project Supervision Department to apply for completion acceptance.  3.1.2 The superintendent supervising engineer organizes all professional supervising engineers to carry out a comprehensive inspection of the completion data and the quality of each professional project, and should urge the contractor to rectify the problems in time.  3.1.3 After acceptance, the superintendent supervising engineer shall sign the project completion report and submit quality assessment report to the construction unit.  3.2 Completion and acceptance The supervisory unit participates in the completion and acceptance organized by the construction unit.  3.2.1 Construction unit, survey unit, design unit, construction unit, supervision unit respectively report in writing on the quality of the construction project, the performance of the engineering contract and the implementation of national laws, regulations and mandatory standards for engineering construction.  3.2.2 Check the completion information provided by all parties involved in engineering construction.  3.2.3 Check the quality of engineering entities. According to the specific conditions of the project, carry out random inspection and examination of the use function of the construction project.  3.2.4 Summarize and discuss the situation of completion acceptance, form the opinion of completion acceptance, and fill in the "Construction Project Completion Acceptance Filing Form" and "Construction Project Completion Acceptance Report".  3.3 Completion Acceptance Record After the completion and acceptance of the construction project is completed, the construction unit is responsible for, within 15 days for the record department for the record of completion and acceptance.  4, the main content of the quality assessment report work ...... >>

Question 8: how to write the monitoring project acceptance copy shameful for reference only

Security Monitoring Project Completion Acceptance Report

Intelligent Monitoring System Project Acceptance Form

The system (project) name: Road Intelligent Traffic Monitoring Project

The system (project) level:

The construction (using) Unit: xx Traffic Patrol Brigade

Design, construction unit: Shenzhen Tiger General Technology Co.

2 system has an alarm part of the alarm test once a day. No alarm leakage, in the corresponding space to play "√", there is a leakage of the alarm to play "X", and in the comments column to explain the situation; false alarms also in the corresponding comments column to fill in the truth.

Table 2 Construction quality sampling and acceptance

Item Requirements Methods Inspection Results Sampling Percentage

Qualified Basic Qualified Unqualified

Front-end equipment 1 Installation location (direction) reasonable, effective on-site sampling and observation 5% to 10%

(at least 3 acceptance of less than 10)

2 Installation quality (process) solid, neat, beautiful, standardized

2 Installation quality (process) solid, neat, beautiful, standardized spot spot spot check observation

3 cable connection video cable a line in place, reliable connectors, power lines and signal lines, control lines are separated, the direction of the straight, no twisted Review, spot check or against the drawings

4 Energized normal work site energized check 100%

Control Room Terminal Equipment 5 operating desk, rack installation smooth, reasonable site Spot check

6 control equipment installation, easy to operate, safe on-site observation

7 switches, buttons, flexible, safe on-site observation

8 rack, equipment grounding in line with the GB50057 equipotential grounding requirements on-site observation

9 grounding resistance in line with the GB50348 specification, Article 3.9.3 of the relevant requirements against the inspection report or according to the GB50348 specification. Inspection report or according to GB50348 specification 6.3.6 relevant requirements

10 lightning protection measures in line with GB50348 specification 3.9.5 relevant requirements Check the inspection report, on-site observation

11 rack cable tie and marking neatly, there are obvious numbering, marking on-site observation Random inspection

12 power supply into the cable marking lead-in Line end marking obvious, reliable on-site observation

13 power working properly on-site power check 100%

Quality of pipeline laying 14 open pipeline solid and beautiful, and interior decoration coordination, anti-interference on-site observation Spot check 1 ~ 2

15 junction boxes, cable connectors vertical and horizontal intersection with the splitter box, cable installation is fixed, standardized on-site observation Spot check 1 ~ 2

15 junction boxes, cable connectors vertical and horizontal crossings, cable installation, fixed, standardized on-site observation Spot check 1 ~ 2

15 junction boxes, cable connectors vertical and horizontal crossings, cable installation, fixed, standardized on-site observation 2 places

16 hidden works with acceptance review with hidden works with acceptance checklist and acceptance review

(If there is no hidden works with acceptance checklist, briefly explain in this column)

Inspection results statistics: KS (pass rate) Installation quality Inspection conclusions

Construction acceptance group signature: acceptance date:

Note:

1 acceptance requirements, the installation of cable fixed, standardized site observation spot check 1 ~ 2

16 hidden works with acceptance review with hidden works and acceptance review

Construction acceptance group signatures: Acceptance date:

Note:


1 acceptance requirements and methods related to specific specifications are to "Security Engineering Technical Specification" (GB50348 specification) relevant requirements shall prevail.

2 in the inspection results column, according to the actual situation in the corresponding space √ (left column √, considered qualified; in the column √, considered basically qualified; right column √, considered unqualified).

3 Inspection results statistics: KS (pass rate) = number of passes + number of basic passes × 0.6 / number of project review (number of project review if there is no requirement or actual lack of unchecked, not counted).

4 inspection conclusion: KS (pass rate) ≥ 0.8, judged to be passed; 0.8 & gt; KS ≥ 0.6, judged to be basically passed; KS & gt;

Question 9: how to write the acceptance conclusion of the acceptance letter of the completion of the quality of the construction project -, test batch quality acceptance records

1, supervision acceptance records -Whether qualified.

2, supervision acceptance conclusion - the main control items all qualified, general items to meet the specification requirements, this test batch qualified.

Second, the quality acceptance record of sub-projects

1, supervision and acceptance conclusion (above) - whether qualified.

2, acceptance conclusion (below) - this sub-item qualified.

3, sub-division project quality acceptance record

Supervision acceptance opinion - the contained sub-items are not missing and all qualified, this sub-division is qualified, agreed to acceptance.

Fourth, the acceptance record of the quality of sub-division works

Acceptance opinion of the acceptance group - no omission of the sub-division included, and all qualified, this sub-division is qualified, agreed to acceptance.

Question 10: How to write the project completion report ah? Engineering Completion Report

First, the construction profile and construction process

1, XXX plant a project is located in XX City, is invested by the development of XXX, XXX City Architectural Design Institute is responsible for geological survey, XXX City Architectural Design Co. The project is a two-story factory building, concrete frame structure, building area of 2428O, the total cost of 1.8116 million yuan. The foundation of this project adopts prestressed concrete pipe pile foundation. The foundation bearing concrete is C25, and the foundation mat is C15 concrete 150mm. masonry is made of MU7.5 shale bricks with M7.5 mixed mortar masonry. The interior decoration adopts general plastering and sweeping white gray water. Doors and windows are made of roller shutter, anti-burglary iron door, fireproof door and silver-white aluminum alloy window respectively. Outdoor decoration adopts glass mosaic on the wall. The roof is 1:2.5 cement waterproof mortar 20 thick leveling layer; polyurethane 3mm waterproof coating; 100mm foam concrete heat insulation layer and find the slope 2%.

2. The commencement date of this project is September 15, 2009, and the progress of the project is as follows:

This project completed the pile foundation project in late September 2009, and the vertical compressive static loading test of single pile and the test of reflective wave method of the foundation pile conducted by XXX Municipal Construction Engineering Quality Inspection Center meet the design requirements. From mid-October 2009, the construction of pile bearing platform, foundation beam and structure above ±0.00 started, and in late January 2010, the structure was topped off. In the meantime, the construction of internal and external wall masonry, external wall decoration, door and window installation, etc. In early March 2010, the overall project was basically completed.

Second, the project characteristics and main measures

1, project characteristics

(1) The project duration is short.

(2) High quality requirements.

2, the main measures

(1) for the short duration of the characteristics of the project, the use of computers for engineering data preparation, management. Construction layout to facilitate construction, reduce secondary transportation; and according to the construction progress of the organization of engineering materials procurement and construction equipment into the field, reduce idle time. In this way, both to ensure the quality of the project, accelerate the construction progress, but also reduce construction costs.

(2) For the quality requirements of this project, the template support of portal scaffolding is selected to accelerate the construction progress. The characteristics of the high quality requirements of the decoration, we deployed a high level of professionalism, experienced technicians responsible for the construction management of the project, to carry out comprehensive quality management activities. Project management staff division of labor is clear, clear division of authority and responsibility, the construction team can only enter the field after passing the examination, rewards and penalties are clear, encouraging excellence, greatly mobilizing the enthusiasm of the construction team to ensure the quality of the project. In the construction process, the implementation of quality and technical delivery of work and "three inspection" system; to strengthen the practice of quality control, reduce rework; seize the hidden project acceptance and visa work of the project.

3, in civilized construction and production safety, our company has invested a lot of money and safety production facilities, the project department to strengthen communication, the implementation of the job responsibility system, in accordance with the "Building Construction Safety Inspection Standards" (JGJ59-99) and "Guangdong Province, civilized construction engineering construction inspection and scoring rules," the requirements of the decomposition of the responsibility of the person, strict management, reasonable stacking of materials, machinery and equipment, the construction site to ensure that In addition to the daily inspection, we regularly organize relevant personnel to inspect the safety production and civilized construction every month, and do the safety evaluation of each stage. During the construction period, five phases were inspected and rated, and each time reached the qualified standard, self-assessment grade: qualified. Throughout the construction process, no safety accidents.

Third, the results of self-assessment of project quality

The project has been completed in accordance with the requirements of the construction contract and the content of the design drawings. In the entire construction process, the strict implementation of relevant laws, regulations and mandatory standards for engineering construction. The test blocks, specimens and related materials involving structural safety have been tested by witness sampling in accordance with the regulations and in line with the requirements: the important branch projects involving the use of functional requirements for sampling and testing, and the results are in line with the specification requirements. All concealed works during construction are accepted by the design and the representative of Party A and meet the requirements. In the construction process of this project, **** carried out four settlement observations, the maximum settlement of 7mm, the minimum settlement of 5mm, from the resulting observation data reflects the overall uniformity of the building settlement, the settlement difference between two adjacent points within the allowable range, the building settlement in line with the specification requirements, the building is not found to be sinking, cracking, leakage phenomenon.

The project ***5 divisional projects, quality qualified, quality control information is basically complete, the main engineering materials and components have qualified documents, general quality of perception, engineering quality qualified. Project information is complete, in line with the specification acceptance requirements, can pass the acceptance.

Project Manager:

Technical Manager:

XXX City Construction Engineering Co. >>