The implementation program of poverty alleviation and relocation work

Beishe Township is located in the western tableland of Pingshun County, around the north of Lucheng, west of the suburbs, southwest of the border with Hu Guan.

The township has jurisdiction over 25 administrative villages, 36 natural manor, with a total land area of 102,986 acres, arable land area of 27,414 acres, 5,081 households, 16,085 mouths.

Among them: Qinjia after 7 villages are located on both sides of the Xilinggou, transportation is inconvenient, information is closed, nine droughts in ten years, the natural conditions are quite poor, the level of agricultural productivity is relatively low, farmers mainly rely on planting, aquaculture, labor export for a living.

According to the spirit of the higher levels of poverty alleviation and relocation, combined with the actual situation in my township, after a full study, now apply for Qinjia Hou and other 7 villages, 13 natural manor, 117 households, 417 mouths of the implementation of poverty alleviation and relocation, the specific circumstances are as follows:

A basic situation of the village of the relocation of the village

Beishe Township*** Qinjia Hou and other 7 villages involved in the application for immigration and relocation, of which After the Qinjia (2 natural manor) relocation of the entire village of 42 households, 125 people; Northwest slope village east head of the natural manor of 5 households, 25 people; Zhuangshang village on the north bank of the natural manor of 22 households, 82 people; Niujia after the village of Ximai, east of the 2 natural manor of 8 households, 38 people; East River village of the new countryside, Changjia after the South Bank on the East River, 4 natural manor of 19 households, 71 people; Jilin village, the back of the gully of the natural manor of 3 households, 13 people; Beishe Village, the Southwest gully of the natural manor of 18 households, 63 people.

Reasons for relocation:

Through the field investigation of seven villages, including Qinjia Hou, the main reasons for the implementation of relocation are as follows:

1, backward transportation conditions.

The villagers who want to relocate 117 households are located in the ruins of the gully area, living in the place of steep slopes, narrow roads, curved, clear dusty, rainy roads muddy, large and medium-sized trucks can not enter the village, resulting in the masses of production, living difficulties, agricultural products, difficult to transport and marketing, the masses of difficult to travel to the outside world of the economic exchanges and communication with the information lagged behind seriously.

2, water difficulties.

Due to the remoteness of the area, the villagers are very poor draught conditions, most of the villagers still rely on precipitation, encountering weather drought often lack of water, and water sources are poor, safe water is not guaranteed.

3, living conditions are poor, there is a great security risks.

Most of the people need to relocate to live in the 60s and 70s in the soil kiln cave or adobe house, due to the age of repair, most of the people's houses there are cracks in the kiln, the roof beams, puisne rotten, the wall off the soil, often leaky rain.

To the masses of life and property threat, there is a great security risks.

4, difficult to go to school, difficult to get to the doctor, communication network coverage.

The seven villages relocated from the surrounding schools are more than 3 kilometers away, the far more than 6 kilometers, the children to go to school is difficult, resulting in individual children drop out of school for some reason.

Most of the children were moved to other places for schooling.

In terms of medical care, it is very inconvenient for the public to see a doctor, there is a lack of medicine, and some diseases are often delayed, missing the best treatment time, increasing the burden on the public, and the public's health is not guaranteed.

In addition, the cultural life is backward, television, telephone and other communications can not be covered, and communication with the outside world is difficult, and the lack of knowledge of agricultural science and technology, market information channels, resulting in stereotypes, a single mode of agricultural production, the economy and culture is very backward.

Second, the basic situation of the relocation site

In view of the above reasons and the actual situation, through a number of meetings, focusing on the views of the masses, 7 villages in my township after the Qinjia 117 households 417 people to implement the relocation, the choice of new immigrant areas with the following favorable conditions.

1, Beishe Village, the new immigrant area

(1) Geographic location.

The new area of Beishe Village is located in Beishe Village after the North Building.

The terrain is flat, the traffic is convenient, the planning is functional, the structure is optimized, the layout is reasonable, and it meets the conditions for moving in.

(2) Building scale and land occupation.

The resettlement site *** planning 117 households with a population of 417, covering an area of 33774.62 square meters (50.66 acres), which can accommodate migrant relocation households.

(3) Favorable conditions for relocating to a new area

Beishe Village is the seat of the township government, political, economic and cultural center.

① Superior transportation conditions, the provincial highway Li Dong line and county road into a small line through the village, the masses travel and transportation conditions are very convenient.

② water and electricity communication facilities are fully functional.

The village existing 5000 cubic meters cistern 2, water from the centralized water supply project in Pingshun, can meet the 4000 people normal water, to meet the national drinking water standards.

In terms of power supply, the village has 2 sets of 500KVA transformers and 3 sets of 100KVA transformers, which can guarantee the daily electricity consumption of 5000 people.

In terms of communication, there is one base station each for mobile, Netcom and Unicom, and cable TV was opened for use in 2000.

It can fully satisfy the use of migration.

③ Reasonable allocation of education and medical resources.

The village has a middle school with water, electricity and heating, and an elementary school with a boarding system.

The village has a secondary school with water, electricity and heating, and a primary school with a boarding system.

It can accommodate 1,000 students.

The library, instrument room, playground, cafeteria, dormitory, teaching equipment and other teaching facilities are complete.

In 2011, a new high-standard, 1775.32 square meters of total area of a health center and a village health center, there are 14 medical personnel, 30 beds, equipped with ultrasound, electrocardiogram, fluoroscopy, gastroscopy, laboratory and other medical facilities, to facilitate access to health care for the masses to provide protection.

④ Meet the needs of the masses' cultural life.

Beishe Township is a large cultural township, the village cultural activities and scientific and technological cultural reading room can further enrich the cultural life of the masses.

Third, the construction scale content and source of funds

1, the construction scale content

Migrant construction project project covers a total area of 33774.62 square meters (50.66 acres).

Among them, the immigrant relocated households housing and compound construction area of 40.66 acres, alleyway hardening, greening, water pipeline network, agricultural power lines, and other public **** facilities occupies an area of 10 acres, the housing construction standards are divided into 2 types of households.

The details are as follows:

(1) Residential Project:

① Construction of 74 sets of three two-storey immigrant housing, each household covers an area of 168 square meters, residence construction area of 95 square meters.

The main door, toilet and courtyard 73 square meters.

② construction of a five-story unit building 44 households, construction area of 5300 square meters, building covers an area of 1060 square meters, courtyard area of 1060 square meters.

(2) street project:

Hardening of the main lane 250 meters, 5 meters wide; branch lane 180 meters, 4 meters wide; hardening area of 1970 square meters.

(3) water supply project:

The main water supply pipe is made of 50PE plastic pipe, the branch pipe is made of 40PE and 25PE plastic pipe, and each household is installed with standpipe faucet and water meter.

*** Installation of 5680 meters of water supply pipes and 51 water meter wells.

(4) Power Distribution Project:

1 high-voltage transformer, 5680 meters of low-voltage transmission lines and household lines, 118 sets of supporting household electrical equipment.

(5) village greening:

671 meters of tree planting and greening around the small area, a small park greening area of 672 square meters.

(6) Site leveling:

Due to the unevenness of the existing house sites, site leveling needs to be done again.

***Moving 10,000 cubic meters of earth and stone.

(7) Above-ground recreational activities field, underground parking lot, covering an area of 1512 square meters.

2, the source of funds

(1) investment budget

The project estimates a total investment of 25.628 million yuan.

Among them: 25.478 million yuan construction and installation costs, other costs of 150,000 yuan, the specific investment in various projects are as follows:

① Residential projects: 74 three two-story building, investment of 14.8 million yuan, an average of 200,000 yuan of investment per household;

② five-story unit building 44 households, investment of 8.12 million yuan, an average of 180,000 yuan of investment per household;

③ street project: hardening 1970 square meters, 120 yuan per square meter, an investment of 236,400 yuan;

④ water supply project: 5,680 meters, 45 yuan per meter, an investment of 255,600 yuan;

⑤ high and low power transmission and distribution project: 5,680 meters, 118 sets of power equipment supporting, an investment of 950,000 yuan;

⑥ greening project: around the Greening 641 meters, green park 672 square meters, an investment of 200,000 yuan;

⑦ site leveling 10,000 cubic meters of earth and stone, 16 yuan per cubic meter, an investment of 160,000 yuan;

⑧ above ground recreation ground, underground parking lot of 1512 square meters, 500 yuan per square meter, an investment of 756,000 yuan;

⑨ other costs 150,000 yuan.

We apply for national migrant relocation subsidies and provincial and municipal matching funds, migrant housing construction funds are insufficient mainly by the masses of self-financing, self-financing is: a small amount of personal savings; secondly, the rural credit unions small loans to support agriculture; thirdly, relatives and friends to fund and individuals and villagers to invest in each other's work and labor.

Program 2: the implementation of the program of poverty alleviation and relocation

First, the project background

Ning County, Xinzhuang Town, Jiejia Village is located in the southern end of Dongzhi Plateau, 45 kilometers away from the county, the town of the large differences in natural and economic conditions, the development of the region between the very unbalanced.

There are also administrative villages in the town, XX villagers groups live in the lack of water, less electricity, no roads, information is closed, extreme backwardness of the infrastructure, slow economic development, the natural conditions are extremely poor ditch, bay, beam, mount, palm and other places.

These areas are arid mountainous areas and poverty-stricken areas, and the people in these areas are difficult to get out of poverty under the limitations of the extremely poor natural environmental conditions. In order to completely change their living and survival environments, it is necessary to resolve to implement the poverty alleviation and migratory relocation project for food and clothing relief, which is important to change the conditions of existence, steadily protect the results of poverty alleviation, promote social stability and regional economic development, promote rural townships and cities, change the Ecological environment to save construction funds, improve the efficiency of investment in infrastructure, improve the quality of the population, promote the comprehensive and coordinated economic and social development of poor areas, and actively respond to the call of the Party Central Committee to build a moderately prosperous society in all aspects is completely necessary, but also practical, poverty alleviation and cure the root of the initiative.

XXXX

Second, the project overview

Xinzhuang Town is located in the southwestern part of Ning County, Dongzhi Plateau, the southern end of the east involving the Malian River, and the middle of the village boundaries, southwest of the Jinghe River, and Shaanxi Province, Changwu County, Ning County, Changqingqiao Town adjacent to the north of the township of Taichang.

The altitude is 896?1213 meters, and the relative height difference is 3170 meters.

North latitude 35?20?, east longitude 107?48?.

The annual rainfall is 500?600MM, the average temperature is 8.7℃, and the number of hours of sunshine is 2365.7 hours, the climate is mild, and there is plenty of light.

The town **** jurisdiction of 24 administrative villages, 140 village groups, 8616 households, a total population of 36,094 people, of which the agricultural population of 35,146 people, non-agricultural population of 948 people, the population kiln degree of 282 people per square kilometer, the money town of the total land area of 128 square kilometers, arable land area of 72,567 acres.

Second socio-economic conditions

According to statistics provided, in 2004, the town realized GDP of 60.64 million yuan, per capita GDP of 1,680 yuan, farmers per capita net income of 1,716 yuan.

Total grain output of 14,200 tons, per capita grain output of XX kilograms.

The number of households with electricity in the town, neighborhoods and 13 villages with running water, running water benefited 2975 households, benefiting the population of 13,388 people.

The total length of the town and village roads 52 kilometers, asphalt highway 8.6 kilometers, 67.5 kilometers of gravel road surface, the town of the village village through the car, through the mail.

7 administrative villages on the cable phone, the town's fixed telephone installed capacity reached 758, built 3 mobile communication base station.

Third, the basic situation of the project area

1, the reasons for relocation

Relocation of natural villages in the area are in the Loess Plateau arid and semi-arid mountainous areas, the residents basically live in ? The residents basically live in the area where there is no village in front of them and no store behind them.

Farmers live in extremely dispersed and remote, water, electricity and road infrastructure conditions are extremely poor, low economic income, extreme poverty, cultural backwardness, closed information, single structure of the agricultural industry, backward production methods, the quality of the population is generally low, and is a downward trend, backward living conditions, etc.

In addition to the above, the government has also developed a series of measures to improve the quality of life in the mountains.

In short, drought and lack of water, no electricity, no road, stopping the occlusion, difficult to go to school, difficult to get medical care, these factors are the main reason for the relocation of poor immigrants in my town.

2, move out of the way

Xinzhuang Town, food for work relocation to take the villagers group as a unit of the overall relocation, centralized resettlement way.

The relocation area does not leave one person and one household, so that the relocation area can be closed to grazing, afforestation, and rapid restoration of ecological vegetation.

3, relocation personnel

20XX plans to relocate people *** XX households, XX people, including XX village XX group XX households XX people; XX village XX group XX XX households XX people; XX village XX group XX households XX people; XX village XX group XX households XX people; XX people in the relocation of the elderly XX, children XX people, labor force XX people.

The roster of relocated people is shown in the attached table.

A basic situation of the resettlement area

Two resettlement areas *** have a land area of XX acres, of which XX acres of arable land, XXXX acres of abandoned land, XX acres of reclaimed land.

Resettlement areas to choose the terrain is flat, fertile soil, good farming conditions, political, economic and cultural developed areas, schools, hospitals are available, television, telephone smooth, attached to the love to eat the main highway through the groundwater resources to ensure that people and livestock drinking water, electric power facilities, near the brick and tile factories, cement prefabrication factories and farms, to enable a portion of the masses close to the work and family farming.

It can also enter the small towns to work and do business, receiving a large number of reclaimable land in the area, the per capita production of about XX kilograms of grain, the per capita GDP of XX yuan, the per capita net income of the farmers to reach more than XXXX yuan.

Southwest gate village resettlement area.

It is the seat of the town government, is the town's `political, economic and cultural center, the early green highway through the place, the village has XX households, XX mouths, the local per capita arable land of XX acres, per capita net income of farmers XX yuan, can be relocated for the farmers to provide land of XX acres.

The surrounding water, electricity and road utilities are complete, and the mass base is good, which can provide XX mu of land for migrants.

Fourth, the construction goals

The overall goal is: one year relocation to build a home, two years of settlement to grasp the income, three years out of poverty and get rich.

1, infrastructure surface.

After the implementation of the project, the relocation of immigrants households have an area of mu, living area of XX square meters, per capita living area of XX square meters, per capita living area of XX square meters of a set of residential, water, electricity, roads and other infrastructure is perfect.

2. Improve education, medical and other service facilities.

Increase the area of school buildings XX square meters, renovate school buildings XX square meters, build a new health clinic for two years, equipped with education, health professionals and technicians, to ensure that the children of farmers moving into the same year can be enrolled in school education, the masses can be access to health care services.

3, the economic objectives: moving into the farmers 1?3 years per capita net income of XX yuan, per capita food production of more than XX kilograms.

V. Construction Program

A personnel relocation program

20XX plans to relocate people *** XX households XX people, specifically, the southwest door village resettlement point to receive XX village XX households XX people, to receive XX village XX households XX people; the village resettlement point of Jiejia to receive XX village XX households XX people, to receive XX village XX households XX people.

Second resettlement area construction content and program

1, land development program

In order to solve the most basic survival of the people moved into the area have guaranteed conditions, the two resettlement points **** to provide development and utilization of XX acres of land, the amount of earth is XX cubic meters.

The main reclamation of old farms and leveling of abandoned land, of which the XX group of Southwest Gate Village provides XX mu of land for development and utilization.

2, power supply

In order to solve the problem of mass lighting, the need to move into the village to install 2 sets of 30KV distribution substation, 10KV line XX kilometers, 0.4KV line XX kilometers, household meter project XX households.

3, roads

The plan is to build agricultural level and residential roads XX kilometers, of which XX kilometers in the southwest door resettlement point, XX kilometers in the Jiejia resettlement point.

4, human and animal drinking water project

Construction of 2 places for human and animal drinking water, a new well, 16 meters 30 cubic meters of water tower 1 and supporting facilities; building water supply room, maintenance wells XX, laying water supply pipeline XX meters.

5, health clinic

In order to improve the rural health service system, to meet the needs of the residents of health care, the plan is to build a new village medical health clinic for two years, with a floor area of XX square meters, of which each resettlement construction of brick structure tiled room of XX square meters, were set up outpatient clinic, pharmacy, treatment room and observation room.

6, school

In order to make the relocation of the children of farmers can go to school in a timely manner, as needed for the two settlements to expand the school building XX square meters, repair and renovation of the old school building XX square meters, the purchase of tables and chairs XX sets.

7 Residential

Through the development of abandoned Zhuangji and abandoned land for migrants to provide agricultural residential base of XX acres, the construction of XX acres of farm dwellings XX sets of building area of XX square meters, the construction of XX meters of fences, and the construction of gates, toilets, pigsties and so on.

8, the new XX village department, construction area of XX square meters, for the brick structure tiled house.

Six, the investment estimate

An investment estimate based on

1, "Gansu Province, water conservancy and hydropower construction project estimates quota" (1996);

2, "Gansu Province, the construction project base price quota" (2000) residential buildings, water conservancy, transportation, agriculture and electricity, health, education and other relevant regulations and quotas, combined with the specific circumstances of the project to work for food! Preparation.

Second investment estimates

Ning County in 20XX **** the establishment of two immigrant sites, the relocation of immigrants XX households, the estimated *** need funds XX million yuan, per capita XX yuan.

Among them: basic farmland development XX million yuan; production infrastructure XX million yuan; public **** infrastructure XX million yuan; building XX million yuan; the first productivity subsidies XX million yuan; relocation costs XX million yuan; personnel training costs XX million yuan,; survey and design costs XX million yuan; project management costs XX million yuan (see the schedule of the proposed budget).

Three financing

The source of financing is: the need for national investment of XXXX million yuan, of which XXXX million yuan of cash for work, mainly used for land development, agricultural water conservancy, roads and other aspects of the construction; special funds within the budget of XX million yuan, mainly used for the construction of health centers, schools, agricultural power lines and other construction subsidies; municipal financial supporting funds XX million yuan, mainly used for production and living subsidies and farmer training and other aspects of construction. Living subsidies and farmers training and other aspects of construction subsidies; local governments and the masses to raise XX million yuan, mainly for immigrants to build houses.

Program 3: implementation of land relocation for poverty alleviation

To implement the spirit of the city's poverty alleviation and development work conference, according to the "People's Government of the Guangxi Zhuang Autonomous Region on the poverty-stricken areas? Relocation, landless resettlement? and the construction of apartments for migrant workers" requirements, to ensure the smooth implementation of the construction of the city's relocation project for poverty alleviation, combined with the actual situation in our city, has formulated this work program.

I. Relocation and resettlement in general

(a) relocation and resettlement scope and object

Jinchengjiang District, Luocheng County, Huanjiang County, Nandan County, Tian'e County, Donglan County, Bama County, Fengshan County, Du'an County, Dahua County and other 10 counties (districts), per capita cultivated land area of less than 0.5 acres, and do not have the basic conditions of survival or the geological hazards of the serious threat to the rural The rural population, as well as relatively affluent life, relatively have the potential for development, entrepreneurial ability and employment conditions.

(2) relocation and resettlement mode

Relocation of poverty alleviation in the county as the basic implementation unit, the implementation of the county or township-wide relocation project, and to take a centralized resettlement-based approach, relying on the development trend of the county's economy of urbanization, industrialization, industrialization of agriculture, according to the ? Resettlement without soil? The model of unified planning, step by step implementation.

First, relying on the county around the suburbs combined with the area of relocation; second, relying on the development of small towns, combined with the demand for township expansion relocation; third, the living environment scattered, poor ecological conditions, backward infrastructure, poor production and living conditions of the rural population relocated to the convenient transportation, relatively good resources in the region.

(C) relocation tasks

2012-2020, the city plans to relocate the rural poor population of about 33,000 households of 150,000 people, while attracting some of the relatively affluent life, relatively with the potential for development, entrepreneurship and employment conditions of the rural population relocated to the townships and counties or project parks around the total population is expected to amount to 60,000 households of 300,000 people.

? Twelfth Five-Year? During the period (2012-2015), the city plans to relocate the rural poor population of 17,208 households 81,450 people.

Among them:

2012 plans to relocate the rural poor population of 5,577 households 26,140 people;

2013 plans to relocate the rural poor population of 4,338 households 20,451 people;

2014 plans to relocate the rural poor population of 3,688 households 17,744 people;

2015 Plans to relocate and resettle 3,605 rural poor people 17,115 people.

(D) Financing

? Twelfth Five-Year? During the period (2012-2015), the city's relocation and resettlement areas for poverty alleviation need to carry out housing and ancillary facilities, road hardening, drinking water projects for humans and animals, land development and adjustment, water conservancy channels, household biogas digesters and electrification projects, **** need to invest about 2 billion yuan of funds.

The implementation of land poverty alleviation and relocation project funding plan from the national land poverty alleviation and relocation project funds, the central financial special funds, the autonomous region's financial special funds, local matching funds, the masses of self-financing and other five parts of financing.

Second, the counties (districts)? Twelfth Five-Year? During the relocation of poverty alleviation work program

(a) Jinchengjiang District

1, relocation and resettlement tasks

2012-2015 relocation and resettlement of the rural poor population of the scale of 579 households 2456 people.

Among them:

2012 relocation and resettlement of 258 households 1106 people;

2013 relocation and resettlement of 122 households 557 people;

2014 relocation and resettlement of 104 households 411 people;

2015 relocation and resettlement of 95 households 382 people.

2, the main construction content

Housing construction: 2012-2015 *** need to relocate 579 households 2456 people, according to the standard calculation of the average household 120m2, mainly brick structure, *** need to build 69480m2.

Drinking water for humans and animals: resettlement areas to meet the standard of safe drinking water in rural areas, the estimated budget *** need to build new drinking water for humans and animals 45 places, of which 830m3 cisterns, 47.34 kilometers of water pipelines.

Road construction: the new cemented gravel country road 18.8Km, according to the design of the four lower road surface; resettlement point of the Tun road hardening 46,666 square meters.

Biogas digester: in order to solve the problem of relocation of poor households living energy, combined with the conditions suitable and the needs of the masses, *** need to build 249 new biogas digesters.

Energized project: 30.5 kilometers of 400V low-voltage transmission lines were set up.

As the implementation of Jinchengjiang District are geologic hazards avoidance relocation, take the Tun resettlement method, you can use the original public **** infrastructure, do not need to support the construction of schools, health rooms and other public **** service facilities.

3, financing

(1) sources of funds

Estimated total investment of 124.46 million yuan, the source of funds for: the central relocation funds 15.6 million yuan, accounting for 12.5%; local supporting investment of 3.52 million yuan, accounting for 2.8%; integration of other funds and relocation of the masses of self-financing 105.4 million yuan, accounting for 84.7%.

(2) investment

The central subsidy investment for the construction of relocated people's basic production facilities and necessary living facilities, including housing, basic farmland, water conservancy facilities, rural roads and necessary education, culture, health and other facilities.

The central subsidized investment shall not be used for production and business projects, including the purchase of equipment, means of transportation, processing projects, etc., as well as compensation for the expropriation of land and houses.

(B) Huanjiang County

1, relocation and resettlement tasks

2012 to 2015 relocation and resettlement of the rural poor population of 985 4324 people, of which:

2012 relocation and resettlement of 235 households 1024 people;

2013 relocation and resettlement of 275 households 1200 people;

In 2014, 250 households were relocated and 1,100 people were resettled;

In 2015, 225 households were relocated and 1,000 people were resettled.

2, the main construction content

New housing and ancillary facilities 107,250 square meters; 42 kilometers of farmland water conservancy facilities; the construction of 46 kilometers of roads through the village; 1,000 square meters of health centers; village public **** facilities of 8,600 square meters; follow-up industrial development projects; ecological construction projects.

3, financing

(1) investment sources

? Twelfth Five-Year? During the period, Huanjiang County relocation of poverty alleviation pilot project total investment of 97 million yuan, of which, the central relocation of poverty alleviation funds 40.15 million yuan, the integration of the central relevant support for agriculture investment of 12 million yuan, the central poverty alleviation funds of 8.6 million, the local government investment of 4.85 million yuan, the masses of self-financed funds 31.4 million yuan.

(2) Funding

The central subsidy investment is used to build the basic production facilities and necessary living facilities for the relocated people, including housing, basic farmland, water conservancy facilities, rural roads, and the necessary education, culture, health and other facilities.

The central subsidized investment shall not be used for production and business projects, including the purchase of equipment, means of transportation, processing projects, etc., as well as compensation for the expropriation of land and houses.

(C) Luocheng County

1, relocation and resettlement tasks

2012 to 2015 relocation and resettlement of the rural poor population of 3,677 16,988 people, of which:

2012 relocation and resettlement of 1,277 5,788 people;

2013 relocation and resettlement of 1,000 households 4500 people;

2014 relocation and resettlement of 800 households 4000 people;

2015 relocation and resettlement of 600 households 2700 people.

2, the main construction content

Construction of housing and ancillary facilities in the area of 145,600m2, of which the housing construction area of 89,600m2, the construction of ancillary facilities in the area of 56,000m2.

Reconstruction and expansion of rural highways 94km; the number of new drinking water project 25, to solve the immigrant drinking water population of 1,120 households 4,790 people.

New or restored irrigated area of 1,300 acres, low-yield field renovation of 1,000 acres, the construction of 67km channels, field hardening and other projects, development and adjustment of farmland area of 500 acres.

800 new biogas digesters, with a volume of 6400m3.

3, financing

(1) investment sources

? Twelfth Five-Year? During the period, the total investment of the pilot project of poverty alleviation and relocation in Luocheng County is 500,000,000 yuan, of which, the central poverty alleviation and relocation funds of 180,000,000 yuan, 20,000,000 yuan of local government investment, 50,000,000 yuan of financial poverty alleviation supporting funds of the state and autonomous regions, and 25,000,000 yuan of self-financing funds from the masses.

(2) Investment

The central subsidy investment is used for the construction of the relocated people's basic production facilities and necessary living facilities, including housing, basic farmland, water conservancy facilities, rural roads, and the necessary education, culture, health and other facilities.

The central subsidized investment shall not be used for production and business projects, including the purchase of equipment, means of transportation, processing projects, etc., as well as compensation for the expropriation of land and houses.

(D) Bama County

1, relocation and resettlement tasks

2012 to 2015 relocation and resettlement of the rural poor population of 1,972 households of 9,492 people, of which:

2012 relocation and resettlement of 863 households of 4,366 people;

2013 relocation and resettlement of 429 households of 1,945 people;

In 2014, 322 households and 1,466 people were relocated;

In 2015, 358 households and 1,715 people were relocated.