Industrial pipeline inspection system?

What is the specific content of industrial pipeline inspection system? Zhong Da Consulting will answer your questions below.

1.

In order to standardize the behavior of pipeline safety inspectors, unsafe behaviors around the pipeline were found during the inspection.

In order to ensure the safe operation of the company's natural gas pipeline, this system is formulated in accordance with the principle of "early detection, early communication and early prevention" in line inspection.

2. Scope of application

It is applicable to the safety inspection management of natural gas pipelines, ancillary facilities and valve chambers of Ou Lin Company.

3. Measures and methods

3. 1 The comprehensive management safety supervision department is responsible for compiling and revising the system, inspecting, supervising and assessing the implementation of pipeline safety inspection, conducting pipeline safety inspection and major inspection from time to time, and taking the lead in organizing the company to solve pipeline safety problems.

3.2 The Engineering Department is the direct implementation department of pipeline safety inspection, responsible for the daily safety inspection of pipelines and the management of pipeline safety inspectors, and responsible for on-site stopping, reporting and taking preventive measures against acts endangering pipeline safety. Responsible for arranging personnel to conduct on-site monitoring and management of the construction near the pipeline.

3.3 Comprehensive Safety Supervision Department is responsible for examining and approving the construction technical schemes of other units crossing pipelines and affecting pipeline safety, providing and determining the technical parameters such as the location and buried depth of pipelines on site, and assisting the Engineering Department in the supervision and management of pipeline construction.

3.4 Full-time pipeline safety inspectors are responsible for the daily inspection of pipelines, distributing publicity materials, stopping the construction that may endanger the safety of pipelines, and recording and reporting the problems found on site; Conduct on-site monitoring according to the work arrangement.

working procedure

4. 1 frequency of pipeline safety inspection

Full-time pipeline safety inspectors shall conduct pipeline safety inspection at least once a day, the station shall conduct spot check once a day, and the production and operation department shall organize line safety inspection once a week; The company is led by HSE department and organizes line inspection and inspection once a month.

4.2 Inspection Report of Safety Inspector

4.2. 1 station shall standardize the management of inspectors. Full-time pipeline safety inspectors must report to the stationmaster or station inspector when starting the inspection at the departure station, including the time of starting the inspection, the expected time of arrival at the destination or the time of meeting and reporting at special sections.

4.2.2 Upon arrival at the terminal, the inspector shall submit the inspection record of the day (see Appendix 1: Pipeline Safety Inspection Record Form), report the problems found in the inspection and obtain instructions from the stationmaster. The production and operation department should consider setting up a place to submit and collect inspectors' patrol records, collect inspectors' patrol records regularly, check their records and guide them to improve.

4.3 On-site inspection

4.3. 1 patrol preparation. When conducting pipeline safety inspection, all personnel conducting pipeline safety inspection must first wear labor protection articles according to the weather conditions, carry backpacks, and carry regulations on protecting oil and gas pipelines, communication tools, record forms and ballpoint pens.

4.3.2 During pipeline inspection, hazards should be identified, attention should be paid to road traffic safety, safety belts should be fastened when riding vehicles, and preventive measures such as preventing poisonous snakes, heatstroke prevention and falling should be taken. In case of rainstorm and mountain torrents, patrol in dangerous areas should be stopped, and line patrol should be organized immediately after rainstorm.

4.3.3 The production and operation department should increase patrol personnel and strengthen patrol density in rainy season.

4.4 Inspection of key lines

4.4. 1 the production and operation department shall establish an account of key inspection areas (appendix 2: statistical table of key inspection sections of pipelines and list of inspectors), which shall be distributed to relevant personnel for key management and reported to the HSE department for retention. Full-time inspectors and resident leaders shall be determined in key inspection areas, including shallow water fields, fish ponds and banana forests, river crossing areas, densely populated areas and areas with frequent construction activities. These areas have inconvenient transportation and may be damaged by farming, pond cleaning and other construction.

4.4.2 Full-time pipeline safety patrol personnel and station patrol personnel should be very clear about the key patrol areas of their patrol lines, adhere to the key patrol and foot patrol when patrolling the lines, and fill in the patrol records of the key patrol areas.

4.4.3 The discovered buildings near the pipeline100m should be included in the key inspection area. For the construction that may cross the pipeline or be within 5 meters from the center line of the pipeline, HSE department and engineering department should be informed in advance so as to take corresponding measures.

4.4.4 The station should check the key patrol area at least once a week.

4.4.5 The Production & Operation Department updates the Statistical Table of Key Inspection Sections of Pipelines and the List of Inspection Personnel once a month, and reports it to the HSE Department for timely update.

4.5 Prevention and management of external construction activities

4.5. 1 preventive coordination and communication. When the line patrol personnel find that there is construction outside the pipeline 100 meters, they should ask the construction personnel whether the construction can be extended to the scope of pipeline protection. If possible, inform the requirements of pipeline protection laws and regulations, obtain the contact telephone number of the contact person, determine the ways and steps for further coordination and solution, and report the situation to the Production and Operation Department. The distance between construction activities and pipelines is different, and its management measures and related requirements are shown in the following table:

Construction activity distance, pipeline spacing and management measures requirements

Building activity distance

management measure

Other requirements

Starting from the center line of the pipeline

< 5m

Assign a special person to supervise the site all day.

If there is hot work, it must be approved by HSE department. Ground-breaking operations should determine the basic data such as the location, direction and buried depth of pipelines and optical cables, and manual excavation is not allowed. Examine and approve the construction plan and sign the safety production agreement.

Starting from the center line of the pipeline

5 m -50 m

Full-time inspectors check and report the construction progress every day.

1. Blasting operation is not allowed.

2. An isolation zone shall be established around the pipeline, and warning signs shall be set.

Starting from the center line of the pipeline

50m-100m

Ask the constructors about their construction progress and possible expansion scope.

Inform the requirements of pipeline protection laws and regulations, get the contact number of the contact person, and report to the production operation department.

4.5.2 Hazard notification. The production and operation department should send people to the site to know the situation in advance and do the following work well:

Clarify the potential hazards, consequences and legal responsibilities of natural gas pipelines, issue the Regulations on the Protection of Oil and Gas Pipelines, inform us of the requirements for pipeline protection, and exchange contact information and contact personnel.

4.5.3 Plan approval. For the construction crossing the pipeline or within 5 meters from the center line of the pipeline, the construction unit is required to prepare a detailed and feasible construction technical scheme, which shall be approved by the Engineering Department.

4.5.4 Sign a safety production agreement. For the construction crossing the pipeline or within 5 meters from the center line of the pipeline, the HSE department shall sign a "Safety Production Agreement" with the other party to determine the construction time and notify the production and operation department. If possible, the construction unit shall be required to pay a security deposit.

4.5.5 Construction process management. The production and operation departments shall strengthen the supervision and management of the construction activities around the pipeline.

4.5.5. 1 Arrange guardians. During the construction of pipeline accessories, the production and operation department will arrange supervisors to supervise, and the engineering department will send people to cooperate when necessary; For important construction such as hot work, HSE department should also arrange personnel for on-site safety management. Construction without the consent of the company should be resolutely stopped.

4.5.5.2 construction progress report. Inspection personnel or on-site monitoring personnel should know the construction progress from the construction unit, report the progress of the construction unit and its potential impact on the pipeline every day, and reflect the report in the daily newspaper to facilitate the relevant departments of the company to formulate measures.

4.6 Handling and reporting of problems found during inspection

4.6. 1 Report on dangerous behaviors. When inspectors or any personnel of the company find any behavior endangering pipeline safety, they should immediately stop it and report it to the production and operation department. At the same time, inspectors should distribute the brochure of Regulations on the Protection of Oil and Gas Pipelines to the implementers of hazardous activities, explain the harmful consequences and discourage them from stopping hazardous activities. Inspectors should know before reporting:

The name of the construction unit, the name of the person in charge of the construction content, the contact telephone number and the implementation of the hazard source.

4.6.2 If inspectors cannot stop their hazardous activities after being dissuaded, they should report to the dispatcher on duty of the production and operation department, who should arrange station managers to go to the scene to check the situation, and collect and obtain evidence of hazardous activities at the scene to stop their hazardous activities.

4.6.3 When the station manager can't stop the dangerous activities, the person in charge of the production and operation department should report to the HSE department, which will take the lead and coordinate the company's resources to deal with them.

4.6.4 For serious illegal acts that may lead to pipeline rupture and leakage, the police should immediately call "1 10" for handling.

4.7 Inspection records

4.7. 1 The inspectors fill in the "Inspection Record Form for Pipeline Safety Inspection" on the same day, and the production operation department will report the problems found in the daily newspaper.

4.7.2 Inspectors shall regularly sort out the "Safety Inspection Records", and the Production and Operation Department shall check the rigor and authenticity of the records.

4.8 Education and training

The production and operation department organizes safety study and business training for full-time pipeline safety inspectors once a month, including company rules and regulations, line hazard identification and risk prevention, record filling, etc. , so as to improve the safety awareness, inspection skills and sense of responsibility of inspectors, and ensure that the inspection work can achieve "early detection, early communication and early prevention". Training activities should be recorded.

4.9 Assessment

4.9. 1 The production and operation department shall check the inspector's working attitude and duty performance at least once a month.

4.9.2 The Production and Operation Department shall supervise and assess the externally hired pipeline safety inspectors, and formulate detailed assessment methods according to the requirements of this system. If the inspection work is not detailed, the inspection is not carried out according to the required time and place, or the problems found in the inspection are not reported in time, and the problems found are not discouraged or the responsibilities of the Committee are not delegated, the economic assessment should be carried out.

4.9.3 Pipeline safety inspectors who cause pipeline damage and serious problems shall be reported to the General Management Department for dismissal.