Very good. This month, the main above-ground structure of approximately 3319㎡, the main basement of approximately 870㎡, approximately 43% of masonry work on plots A and B, and 35% of internal and external painting work have been completed. The current total progress: The main above-ground structure of plots A and B is about 113,300 m2, accounting for 91.5%, the main basement project is about 37,500 m2, accounting for 94.7%, the masonry work of plots A and B is 68%, and the internal and external painting works are 55%.